Limitation on Delay and Disruption Damages. Delay damages shall be compensable hereunder only in the case of Delays to the extent that they entitle Contractor to an extension of the Contract Time and result from the following (and no other Delays): (a) An Owner-Directed Change that is the result of a written order designated to be a Directive Letter under Article 14.2; (b) A suspension of the Work under Article 14.17; or
Appears in 2 contracts
Samples: California High Speed Train Project Agreement, General Provisions Agreement
Limitation on Delay and Disruption Damages. Delay damages shall be compensable hereunder only in the case of Delays to the extent that they entitle Contractor to an extension of the Contract Time and result from the following (and no other Delays):): %20Au
(a) An Owner-Directed Change that is the result of a a. A written order designated to be a Directive Letter under Article 14.2;
(b) b. A suspension of the Work under Article 14.17; orand
Appears in 1 contract
Samples: General Provisions Agreement
Limitation on Delay and Disruption Damages. Delay damages shall be compensable hereunder only in the case of Delays to the extent that they entitle Contractor to an extension of the Contract Time a Milestone Acceptance Deadline and result from the following (and no other Delays):
(a) An OwnerAuthority-Directed Change that is the result of a written order designated to be a Directive Letter under Article 14.2;16.2;
(b) A suspension of the Work under Article 14.1716.20; or
Appears in 1 contract
Samples: Track and Systems Agreement