Limitation on General Condition Costs. 24.4.1 For General Conditions Cost, Owner will pay CM General Conditions Costs up to a maximum of Percent ( %) of the Construction Cost Limitation of the Project. 24.4.2 Based on the anticipated CCL in Paragraph 24.1, the General Conditions Costs would be the maximum total stipulated amount of: 24.4.3 If the Owner agrees to a change in the Guaranteed Maximum Price during the Construction Phase that results from a change in the scope of the project, the maximum allowable amount of General Conditions Costs shall be equitably adjusted. The limit on allowable reimbursements of General Conditions Costs will not be adjusted for changes to the project that do not change the Guaranteed Maximum Price. 24.4.4 The maximum allowable amount of General Conditions Costs established for the Project and incorporated by a GMP Change Order cannot be subsequently increased except with the express written approval of the ODR. Such approval will normally only be given if there is a substantial change in the scope of the project.
Appears in 4 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Limitation on General Condition Costs. 24.4.1 For General Conditions Cost, Owner will pay CM General Conditions Costs up to a maximum of Percent ( %) of the Construction Cost Limitation CCL of the Project.
24.4.2 Based on the anticipated CCL in Paragraph 24.1, the General Conditions Costs would be the maximum total stipulated amount of:of Dollars ($ ).
24.4.3 If the Owner agrees to a change in the Guaranteed Maximum Price GMP during the Construction Phase that results from a change in the scope of the project, the maximum allowable amount of General Conditions Costs shall be equitably adjusted. The limit on allowable reimbursements of General Conditions Costs will not be adjusted for changes to the project that do not change the Guaranteed Maximum PriceGMP.
24.4.4 The maximum allowable amount of General Conditions Costs established for the Project and incorporated by a GMP Change Order cannot be subsequently increased except with the express written approval of the ODR. Such approval will normally only be given if there is a substantial change in the scope of the project.
Appears in 3 contracts
Samples: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement, Construction Manager at Risk Agreement
Limitation on General Condition Costs. 24.4.1 For General Conditions Cost, Owner will pay CM General Conditions Costs up to a maximum of Percent ( %) of the Construction Cost Limitation of the Project.
24.4.2 Based on the anticipated CCL in Paragraph 24.1, the General Conditions Costs would be the maximum total stipulated amount of:: and No/100 Dollars ($ )
24.4.3 If the Owner agrees to a change in the Guaranteed Maximum Price during the Construction Phase that results from a change in the scope of the project, the maximum allowable amount of General Conditions Costs shall be equitably adjusted. The limit on allowable reimbursements of General Conditions Costs will not be adjusted for changes to the project that do not change the Guaranteed Maximum Price.
24.4.4 The maximum allowable amount of General Conditions Costs established for the Project and incorporated by a GMP Change Order cannot be subsequently increased except with the express written approval of the ODR. Such approval will normally only be given if there is a substantial change in the scope of the project.
Appears in 1 contract
Samples: Construction Contract
Limitation on General Condition Costs. 24.4.1 For General Conditions Cost, Owner will pay CM The maximum allowable amount of General Conditions Costs up (as authorized to a maximum be reimbursed as Direct Construction Costs under Paragraph 13.1) payable to the Design/Build Contractor during the Construction Phase of Percent ( the Project shall not exceed <<Percent>> Dollars (0.00%) of the Construction Cost Limitation of CCL for the Project.
24.4.2 Based on the anticipated CCL in Paragraph 24.1established at the time of this Agreement, the maximum allowable amount of General Conditions Costs would be the maximum total stipulated amount of:: <<Amount>> Dollars ($0).
24.4.3 If the Owner agrees to a change an increase in the Guaranteed Maximum Price GMP during the Construction Phase Phase, that results from a change in the scope of the project, the maximum allowable amount of General Conditions Costs shall be equitably adjusted. The limit on allowable reimbursements of General Conditions Costs will not be adjusted for changes to the project that do not change the Guaranteed Maximum PriceGMP.
24.4.4 The maximum allowable amount of General Conditions Costs established for the Project and incorporated by a GMP Change Order cannot be subsequently increased except with the express written approval of the ODR. Such approval will normally only be given if there is a substantial change in the scope of the project.