Limitations on Liquidated Damages. (a) The aggregate amount of liquidated damages payable by Seller as Reduction Amounts under Section 24.2 (“Critical Milestone Guarantee Liquidated Damages”) shall not exceed, in the aggregate, an amount equal to 5% of the Purchase Price. (b) The amount of liquidated damages payable by Seller for delays in achieving Substantial Completion under Section 24.3 (“Liquidated Damages for Delay in Substantial Completion”) shall not exceed, in the aggregate, an amount equal to 30% of the Purchase Price.
Appears in 2 contracts
Samples: Asset Purchase Agreement, Asset Purchase and Sale Agreement
Limitations on Liquidated Damages.
(a) The aggregate amount of liquidated damages payable by Seller as Reduction Amounts under Section 24.2 (“Critical Milestone Guarantee Liquidated Damages”) shall not exceed, in the aggregate, an amount equal to 525% of the Purchase Price.
(b) The amount of liquidated damages payable by Seller for delays in achieving Substantial Completion under Section 24.3 (“Liquidated Damages for Delay in Substantial Completion”) shall not exceed, in the aggregate, an amount equal to 30% of the Purchase Price.
Appears in 1 contract
Samples: Asset Purchase and Sale Agreement
Limitations on Liquidated Damages.
(a) The aggregate amount of liquidated damages payable by Seller as Reduction Amounts under Section 24.2 (“Critical Milestone Guarantee Liquidated Damages”) shall not exceed, in the aggregate, an amount equal to 5% of the Purchase Price.
(b) The amount of liquidated damages payable by Seller for delays in achieving Substantial Completion under Section 24.3 (“Liquidated Damages for Delay in Substantial Completion”) shall not exceed, in the aggregate, an amount equal to 30% of the Purchase Price.
Appears in 1 contract
Samples: Asset Purchase and Sale Agreement
Limitations on Liquidated Damages.
(a) The aggregate amount of liquidated damages payable by Seller as Reduction Amounts under Section 24.2 (“Critical Milestone Guarantee Liquidated Damages”) shall not exceed, in the aggregate, an amount equal to 5% of the Purchase Price.
(b) The amount of liquidated damages payable by Seller for delays in achieving Substantial Completion under Section 24.3 (“Liquidated Damages for Delay in Substantial Completion”) shall not exceed, in the aggregate, an amount equal to 30% of the Purchase Price.
Appears in 1 contract
Samples: Asset Purchase Agreement
Limitations on Liquidated Damages.
(a) The aggregate amount of liquidated damages payable by Seller as Reduction Amounts under Section 24.2 (“Critical Milestone Guarantee Liquidated Damages”) shall not exceed, in the aggregate, an amount equal to 5125% of the Purchase Price.
(b) The amount of liquidated damages payable by Seller for delays in achieving Substantial Completion under Section 24.3 (“Liquidated Damages for Delay in Substantial Completion”) shall not exceed, in the aggregate, an amount equal to 30% of the Purchase Price.
Appears in 1 contract
Samples: Asset Purchase and Sale Agreement