Loss of Data. 29.1. The Contractor acknowledges that the Authority‟s Data is the property of the Authority and the Authority hereby reserves all Intellectual Property Rights which may subsist in the Authority‟s Data. The Contractor shall not delete or remove any notices contained within or relating to the Authority‟s Data. 29.2. The Contractor shall not store, copy, disclose, or use the Authority‟s Data except as necessary for the performance by the Contractor of its obligations under this Contract or as otherwise expressly authorised in writing by the Authority. 29.3. To the extent that Authority‟s Data is held and/or processed by the Contractor, the Contractor shall supply that Authority‟s Data to the Authority as requested by the Authority in the format specified in Section 4 (Services Scope). 29.4. The Contractor shall take responsibility for preserving the integrity of the Authority‟s Data and preventing the corruption or loss of the Authority‟s Data. 29.5. The Contractor shall perform secure back-ups of all Authority‟s Data and shall ensure that up-to-date back-ups are stored off-site. The Contractor shall ensure that such back-ups are available to the Authority at all times upon request and are delivered to the Authority at no less than three monthly intervals. 29.6. In the event that the Authority‟s Data is corrupted, lost or sufficiently degraded as a result of any Default by the Contractor the Authority may, in addition to any other remedies that may be available to it either under this Contract or otherwise: 29.6.1. require the Contractor (at the Contractor's expense) to restore or procure the restoration of Authority Data and the Contractor shall do so as soon as practicable but not later than one month; and/or 29.6.2. the Authority may itself restore or procure restoration of the Authority‟s Data and shall be repaid by the Contractor any reasonable expenses incurred in doing so. 29.7. If at any time the Contractor suspects or has reason to believe that the Authority‟s Data has or may become corrupted, lost or sufficiently degraded in any way for any reason, then the Contractor shall notify the Authority immediately and inform the Authority of the remedial action the Contractor proposes to take.
Appears in 3 contracts
Samples: Contract for Provision of Security Guarding Services, Contract for Security Services, Contract for Security Guarding Services
Loss of Data. 29.1. 20.1 The Contractor CONTRACTOR acknowledges that the Authority‟s AUTHORITY’s Data is the property of the Authority AUTHORITY and the Authority AUTHORITY hereby reserves all Intellectual Property Rights Rights, which may subsist in the Authority‟s AUTHORITY’s Data. The Contractor CONTRACTOR shall not delete or remove any notices contained within or relating to the Authority‟s AUTHORITY’s Data.
29.2. 20.2 The Contractor CONTRACTOR shall not store, copy, disclose, or use the Authority‟s AUTHORITY’s Data except as necessary for the performance by the Contractor CONTRACTOR of its obligations under this Contract or as otherwise expressly authorised in writing by the AuthorityAUTHORITY.
29.3. 20.3 To the extent that Authority‟s AUTHORITY’s Data is held and/or processed by the ContractorCONTRACTOR, the Contractor CONTRACTOR shall supply that Authority‟s AUTHORITY’s Data to the Authority AUTHORITY as requested by the Authority AUTHORITY in the format specified in Section 4 the Specification (Services Scope).
29.4. 20.4 The Contractor CONTRACTOR shall take responsibility for preserving the integrity of the Authority‟s AUTHORITY’s Data and preventing the corruption or loss of the Authority‟s AUTHORITY’s Data.
29.5. 20.5 The Contractor CONTRACTOR shall perform secure back-ups of all Authority‟s AUTHORITY’s Data and shall ensure that up-to-date back-ups are stored off-site. The Contractor shall ensure that such back-ups are available to the Authority AUTHORITY at all times upon request and are delivered to the Authority at no less than three monthly intervalsrequest.
29.6. 20.6 In the event that the Authority‟s AUTHORITY’s Data is corrupted, lost or sufficiently degraded as a result of any Default by the Contractor CONTRACTOR the Authority AUTHORITY may, in addition to any other remedies that may be available to it either under this Contract or otherwise:
29.6.1. 20.6.1 require the Contractor CONTRACTOR (at the ContractorCONTRACTOR's expense) to restore or procure the restoration of Authority AUTHORITY Data and the Contractor CONTRACTOR shall do so as soon as practicable but not later than one monthmonth from the date of any Notice issued under this Sub-Condition 20.6; and/or
29.6.2. the Authority 20.6.2 The AUTHORITY may itself restore or procure restoration of the Authority‟s AUTHORITY’s Data and shall be repaid by the Contractor CONTRACTOR any reasonable expenses incurred in doing so.
29.7. 20.7 If at any time the Contractor CONTRACTOR suspects or has reason to believe that the Authority‟s AUTHORITY’s Data has or may become corrupted, lost or sufficiently degraded in any way for any reason, then the Contractor CONTRACTOR shall notify the Authority AUTHORITY immediately and inform the Authority AUTHORITY of the remedial action the Contractor CONTRACTOR proposes to take.
Appears in 2 contracts
Samples: Security Guarding Services Agreement, Security Guarding Services Agreement
Loss of Data. 29.1. 30.1 The Contractor acknowledges that the Authority‟s Authority’s Data is the property of the Authority and the Authority hereby reserves all Intellectual Property Rights which may subsist in the Authority‟s Authority’s Data. The Contractor shall not delete or remove any notices contained within or relating to the Authority‟s Authority’s Data.
29.2. 30.2 The Contractor shall not store, copy, disclose, or use the Authority‟s Authority’s Data except as necessary for the performance by the Contractor of its obligations under this Contract or as otherwise expressly authorised in writing by the Authority.
29.3. 30.3 To the extent that Authority‟s Authority’s Data is held and/or processed by the Contractor, the Contractor shall supply that Authority‟s Authority’s Data to the Authority as requested by the Authority in the format specified in Section 4 (Services Scope).
29.4. 30.4 The Contractor shall take responsibility for preserving the integrity of the Authority‟s Authority’s Data and preventing the corruption or loss of the Authority‟s Authority’s Data.
29.5. 30.5 The Contractor shall perform secure back-ups of all Authority‟s Authority’s Data and shall ensure that up-to-date back-ups are stored off-site. The Contractor shall ensure that such back-ups are available to the Authority at all times upon request and are delivered to the Authority at no less than three monthly intervals.
29.6. 30.6 In the event that the Authority‟s Authority’s Data is corrupted, lost or sufficiently degraded as a result of any Default by the Contractor the Authority may, in addition to any other remedies that may be available to it either under this Contract or otherwise:
29.6.1. 30.6.1 require the Contractor (at the Contractor's expense) to restore or procure the restoration of Authority Data and the Contractor shall do so as soon as practicable but not later than one month; and/or
29.6.2. 30.6.2 the Authority may itself restore or procure restoration of the Authority‟s Authority’s Data and shall be repaid by the Contractor any reasonable expenses incurred in doing so.
29.7. 30.7 If at any time the Contractor suspects or has reason to believe that the Authority‟s Authority’s Data has or may become corrupted, lost or sufficiently degraded in any way for any reason, then the Contractor shall notify the Authority immediately and inform the Authority of the remedial action the Contractor proposes to take.
Appears in 2 contracts
Samples: Contract for Media Monitoring and Evaluation Services, Contract for Supply of Goods
Loss of Data. 29.1. 30.1 The Contractor acknowledges that the Authority‟s Authority’s Data is the property of the Authority and the Authority hereby reserves all Intellectual Property Rights which may subsist in the Authority‟s Authority’s Data. The Contractor shall not delete or remove any notices contained within or relating to the Authority‟s Authority’s Data.
29.2. 30.2 The Contractor shall not store, copy, disclose, or use the Authority‟s Authority’s Data except as necessary for the performance by the Contractor of its obligations under this Contract or as otherwise expressly authorised in writing by the Authority.
29.3. 30.3 To the extent that Authority‟s Authority’s Data is held and/or processed by the Contractor, the Contractor shall supply that Authority‟s Authority’s Data to the Authority as requested by the Authority in the format specified in Section 4 (Services Scope).
29.4. 30.4 The Contractor shall take responsibility for preserving the integrity of the Authority‟s Authority’s Data and preventing the corruption or o r loss of the Authority‟s Authority’s Data.
29.5. 30.5 The Contractor shall perform secure back-ups of all Authority‟s Authority’s Data and shall ensure that up-to-date back-ups are stored off-site. The Contractor shall ensure that such back-ups are available to the Authority at all times upon request and are delivered to the Authority at no less than three monthly intervals.
29.6. 30.6 In the event that the Authority‟s Authority’s Data is corrupted, lost or sufficiently degraded as a result of any Default by the Contractor the Authority may, in addition to any other remedies that may be available to it either under this Contract or otherwise:
29.6.1. 30.6.1 require the Contractor (at the Contractor's expense) to restore or procure the restoration of Authority Data and the Contractor shall do so as soon as practicable but not later than one month; and/or
29.6.2. 30.6.2 the Authority may itself restore or procure restoration of the Authority‟s Authority’s Data and shall be repaid by the Contractor any reasonable expenses incurred in doing so.
29.7. 30.7 If at any time the Contractor suspects or has reason to believe that the Authority‟s Authority’s Data has or may become corrupted, lost or sufficiently degraded in any way for any reason, then the Contractor shall notify the Authority immediately and inform the Authority of the remedial action the Contractor proposes to take.
Appears in 1 contract
Samples: Security Guarding Contract
Loss of Data. 29.1. 29.1 The Contractor acknowledges that the Authority‟s Authority’s Data is the property of the Authority and the Authority hereby reserves all Intellectual Property Rights which may subsist in the Authority‟s Authority’s Data. The Contractor shall not delete or remove any notices contained within or relating to the Authority‟s Authority’s Data.
29.2. 29.2 The Contractor shall not store, copy, disclose, or use the Authority‟s Authority’s Data except as necessary for the performance by the Contractor of its obligations under this Contract or as otherwise expressly authorised in writing by the Authority.
29.3. 29.3 To the extent that Authority‟s Authority’s Data is held and/or processed by the Contractor, the Contractor shall supply that Authority‟s Authority’s Data to the Authority as requested by the Authority in the format specified in Section 4 (Services Scope).
29.4. 29.4 The Contractor shall take responsibility for preserving the integrity of the Authority‟s Authority’s Data and preventing the corruption or loss of the Authority‟s Authority’s Data.
29.5. 29.5 The Contractor shall perform secure back-ups of all Authority‟s Authority’s Data and shall ensure that up-to-date back-ups are stored off-site. The Contractor shall ensure that such back-ups are available to the Authority at all times upon request and are delivered to the Authority at no less than three monthly intervals.
29.6. 29.6 In the event that the Authority‟s Authority’s Data is corrupted, lost or sufficiently degraded as a result of any Default by the Contractor the Authority may, in addition to any other remedies that may be available to it either under this Contract or otherwise:
29.6.1. 29.6.1 require the Contractor (at the Contractor's expense) to restore or procure the restoration of Authority Data and the Contractor shall do so as soon as practicable but not later than one month; and/or
29.6.2. 29.6.2 the Authority may itself restore or procure restoration of the Authority‟s Authority’s Data and shall be repaid by the Contractor any reasonable expenses incurred in doing so.
29.7. 29.7 If at any time the Contractor suspects or has reason to believe that the Authority‟s Authority’s Data has or may become corrupted, lost or sufficiently degraded in any way for any reason, then the Contractor shall notify the Authority immediately and inform the Authority of the remedial action the Contractor proposes to take.
Appears in 1 contract
Loss of Data. 29.119.1. The Contractor acknowledges that the Authority‟s Data is the property of the Authority and the Authority hereby reserves all Intellectual Property Rights which may subsist in the Authority‟s Data. The Contractor shall not delete or remove any notices contained within or relating to the Authority‟s Data.
29.219.2. The Contractor shall not store, copy, disclose, or use the Authority‟s Data except as necessary for the performance by the Contractor of its obligations under this Contract or as otherwise expressly authorised in writing by the Authority.
29.319.3. To the extent that Authority‟s Data is held and/or processed by the Contractor, the Contractor shall supply that Authority‟s Data to the Authority as requested by the Authority in the format specified in Section 4 (Services Scope).
29.419.4. The Contractor shall take responsibility for preserving the integrity of the Authority‟s Data and preventing the corruption or loss of the Authority‟s Data. .
29.519.5. The Contractor shall perform secure back-ups of all Authority‟s Data and shall ensure that up-to-date back-ups are stored off-sitesite in accordance with the Business Continuity and Disaster Recovery Plan. The Contractor shall ensure that such back-ups are available to the Authority at all times upon request and are delivered to the Authority at no less than three 3 monthly intervals.
29.619.6. In the event that the Authority‟s Data is corrupted, lost or sufficiently degraded as a result of any Default by the Contractor the Authority may, in addition to any other remedies that may be available to it either under this Contract or otherwise:
29.6.119.6.1. require the Contractor (at the Contractor's expense) to restore or procure the restoration of Authority Data and the Contractor shall do so as soon as practicable but not later than one month7 working days; and/or
29.6.219.6.2. the Authority may itself restore or procure restoration of the Authority‟s Data and shall be repaid by the Contractor any reasonable expenses incurred in doing so.
29.719.7. If at any time the Contractor suspects or has reason to believe that the Authority‟s Data has or may become corrupted, lost or sufficiently degraded in any way for any reason, then the Contractor shall notify the Authority immediately and inform the Authority of the remedial action the Contractor proposes to take.
Appears in 1 contract
Samples: Cleaning Services Agreement
Loss of Data. 29.120.1. The Contractor acknowledges that the Authority‟s Data is the property of the Authority and the Authority hereby reserves all Intellectual Property Rights which may subsist in the Authority‟s Data. The Contractor shall not delete or remove any notices contained within or relating to the Authority‟s Data.
29.220.2. The Contractor shall not store, copy, disclose, or use the Authority‟s Data except as necessary for the performance by the Contractor of its obligations under this Contract or as otherwise expressly authorised in writing by the Authority.
29.320.3. To the extent that Authority‟s Data is held and/or processed by the Contractor, the Contractor shall supply that Authority‟s Data to the Authority as requested by the Authority in the format specified in Section 4 (Services Scope).
29.420.4. The Contractor shall take responsibility for preserving the integrity of the Authority‟s Data and preventing the corruption or loss of the Authority‟s Data. .
29.520.5. The Contractor shall perform secure back-ups of all Authority‟s Data and shall ensure that up-to-date back-ups are stored off-sitesite in accordance with the Business Continuity and Disaster Recovery Plan. The Contractor shall ensure that such back-ups are available to the Authority at all times upon request and are delivered to the Authority at no less than three 1 monthly intervals.
29.620.6. In the event that the Authority‟s Data is corrupted, lost or sufficiently degraded as a result of any Default by the Contractor the Authority may, in addition to any other remedies that may be available to it either under this Contract or otherwise:
29.6.120.6.1. require the Contractor (at the Contractor's expense) to restore or procure the restoration of Authority Data and the Contractor shall do so as soon as practicable but not later than one month; and/or
29.6.2. 2 days after the Authority may itself restore or procure restoration of the Authority‟s Data and shall be repaid by the Contractor any reasonable expenses incurred in doing soevent.
29.720.7. If at any time the Contractor suspects or has reason to believe that the Authority‟s Data has or may become corrupted, lost or sufficiently degraded in any way for any reason, then the Contractor shall notify the Authority immediately and inform the Authority of the remedial action the Contractor proposes to take.
Appears in 1 contract
Samples: Software License Agreement
Loss of Data. 29.1. The Contractor acknowledges that the Authority‟s Data is the property of the Authority and the Authority hereby reserves all Intellectual Property Rights which may subsist in the Authority‟s Data. The Contractor shall not delete or remove any notices contained within or relating to the Authority‟s Data.
29.2. The Contractor shall not store, copy, disclose, or use the Authority‟s Data except as necessary for the performance by the Contractor of its obligations under this Contract or as otherwise expressly authorised in writing by the Authority.
29.3. To the extent that Authority‟s Data is held and/or processed by the Contractor, the Contractor shall supply that Authority‟s Data to the Authority as requested by the Authority in the format specified in Section 4 (Services Scope).
29.4. The Contractor shall take responsibility for preserving the integrity of the Authority‟s Data and preventing the corruption or loss of the Authority‟s Data.
29.5. The Contractor shall perform secure back-ups of all Authority‟s Data and shall ensure that up-to-date back-ups are stored off-site. The Contractor shall ensure that such back-ups are available to the Authority at all times upon request and are delivered to the Authority at no less than three monthly intervals.
29.6. In the event that the Authority‟s Data is corrupted, lost or sufficiently degraded as a result of any Default by the Contractor the Authority may, in addition to any other remedies that may be available to it either under this Contract or otherwise:
29.6.1. a) require the Contractor (at the Contractor's expense) to restore or procure the restoration of Authority Data and the Contractor shall do so as soon as practicable but not later than one month; and/or
29.6.2. b) the Authority may itself restore or procure restoration of the Authority‟s Data and shall be repaid by the Contractor any reasonable expenses incurred in doing so.
29.7. If at any time the Contractor suspects or has reason to believe that the Authority‟s Data has or may become corrupted, lost or sufficiently degraded in any way for any reason, then the Contractor shall notify the Authority immediately and inform the Authority of the remedial action the Contractor proposes to take.
Appears in 1 contract
Loss of Data. 29.120.1. The Contractor acknowledges that the Authority‟s Data is the property of the Authority and the Authority hereby reserves all Intellectual Property Rights which may subsist in the Authority‟s Data. The Contractor shall not delete or remove any notices contained within or relating to the Authority‟s Data.
29.220.2. The Contractor shall not store, copy, disclose, or use the Authority‟s Data except as necessary for the performance by the Contractor of its obligations under this Contract or as otherwise expressly authorised in writing by the Authority.
29.320.3. To the extent that Authority‟s Data is held and/or processed by the Contractor, the Contractor shall supply that Authority‟s Data to the Authority as requested by the Authority in the format specified in Section 4 (Services Scope).
29.420.4. The Contractor shall take responsibility for preserving the integrity of the Authority‟s Data and preventing the corruption or loss of the Authority‟s Data. .
29.520.5. The If required, as part of the contract, the Contractor shall perform secure back-ups of all Authority‟s Data and shall ensure that up-to-date back-ups are stored off-sitesite in accordance with the Business Continuity and Disaster Recovery Plan. The If this is applicable, the Contractor shall ensure that such back-ups are available to the Authority at all times upon request and are delivered to the Authority at no less than three 1 monthly intervals.
29.620.6. In the event that the Authority‟s Data is corrupted, lost or sufficiently degraded as a result of any Default by the Contractor the Authority may, in addition to any other remedies that may be available to it either under this Contract or otherwise:
29.6.120.6.1. require the Contractor (at the Contractor's expense) to restore or procure the restoration of Authority Data to the extent and in accordance with the requirements specified the Business Continuity and Disaster Recovery Provisions and the Contractor shall do so as soon as practicable but not later than one month; and/or
29.6.2. 2 days (48 hours) after the Authority may itself restore or procure restoration of the Authority‟s Data and shall be repaid by the Contractor any reasonable expenses incurred in doing soevent.
29.720.7. If at any time the Contractor suspects or has reason to believe that the Authority‟s Data has or may become corrupted, lost or sufficiently degraded in any way for any reason, then the Contractor shall notify the Authority immediately and inform the Authority of the remedial action the Contractor proposes to take.
Appears in 1 contract
Loss of Data. 29.1. 20.1 The Contractor acknowledges that the Authority‟s Data is the property of the Authority and the Authority hereby reserves all Intellectual Property Rights Rights, which may subsist in the Authority‟s Data. The Contractor shall not delete or remove any notices contained within or relating to the Authority‟s Data.
29.2. 20.2 The Contractor shall not store, copy, disclose, or use the Authority‟s Data except as necessary for the performance by the Contractor of its obligations under this Contract or as otherwise expressly authorised in writing by the Authority.
29.3. 20.3 To the extent that Authority‟s Data is held and/or processed by the Contractor, the Contractor shall supply that Authority‟s Data to the Authority as requested by the Authority in the format specified in Section 4 the Specification (Services Scope).
29.4. 20.4 The Contractor shall take responsibility for preserving the integrity of the Authority‟s Data and preventing the corruption or loss of the Authority‟s Data.
29.5. 20.5 The Contractor shall perform secure back-ups of all Authority‟s Data and shall ensure that up-up- to-date back-ups are stored off-site. The Contractor shall ensure that such back-ups are available to the Authority at all times upon request and are delivered to the Authority at no less than three monthly intervalsrequest.
29.6. 20.6 In the event that the Authority‟s Data is corrupted, lost or sufficiently degraded as a result of any Default by the Contractor the Authority may, in addition to any other remedies that may be available to it either under this Contract or otherwise:
29.6.1. 20.6.1 require the Contractor (at the Contractor's expense) to restore or procure the restoration of Authority Data and the Contractor shall do so as soon as practicable but not later than one monthmonth from the date of any Notice issued under this Sub- Condition 20.6; and/or
29.6.2. the 20.6.2 The Authority may itself restore or procure restoration of the Authority‟s Data and shall be repaid by the Contractor any reasonable expenses incurred in doing so.
29.7. 20.7 If at any time the Contractor suspects or has reason to believe that the Authority‟s Data has or may become corrupted, lost or sufficiently degraded in any way for any reason, then the Contractor shall notify the Authority immediately and inform the Authority of the remedial action the Contractor proposes to take.
Appears in 1 contract
Samples: Master Contract
Loss of Data. 29.120.1. The Contractor acknowledges that the Authority‟s Data is the property of the Authority and the Authority hereby reserves all Intellectual Property Rights which may subsist in the Authority‟s Data. The Contractor shall not delete or remove any notices contained within or relating to the Authority‟s Data.
29.220.2. The Contractor shall not store, copy, disclose, or use the Authority‟s Data except as necessary for the performance by the Contractor of its obligations under this Contract or as otherwise expressly authorised in writing by the Authority.
29.320.3. To the extent that Authority‟s Data is held and/or processed by the Contractor, the Contractor shall supply that Authority‟s Data to the Authority as requested by the Authority in the format specified in Section 4 IV (Services Scope).
29.420.4. The Contractor shall take responsibility for preserving the integrity of the Authority‟s Data and preventing the corruption or loss of the Authority‟s Data.
29.520.5. The Contractor shall perform secure back-ups of all Authority‟s Data and shall ensure that up-to-date back-ups are stored off-sitesite in accordance with the Business Continuity and Disaster Recovery Plan. The Contractor shall ensure that such back-back- ups are available to the Authority at all times upon request and are delivered to the Authority at no less than three monthly 1 month intervals.
29.620.6. In the event that the Authority‟s Data is corrupted, lost or sufficiently degraded as a result of any Default by the Contractor the Authority may, in addition to any other remedies that may be available to it either under this Contract or otherwise:
29.6.120.6.1. require the Contractor (at the Contractor's expense) to restore or procure the restoration of Authority Data to the extent and in accordance with the requirements specified in the Business Continuity and Disaster Recovery Provisions and the Contractor shall do so as soon as practicable but not later than one month; and/or
29.6.2. 2 days (48 hours) after the Authority may itself restore or procure restoration of the Authority‟s Data and shall be repaid by the Contractor any reasonable expenses incurred in doing soevent.
29.720.7. If at any time the Contractor suspects or has reason to believe that the Authority‟s Data has or may become corrupted, lost or sufficiently degraded in any way for any reason, then the Contractor shall notify the Authority immediately and inform the Authority of the remedial action the Contractor proposes to take.
Appears in 1 contract