MAINTENANCE INSPECTIONS. 6.1 If the Buyer, on reasonable grounds and based on the number of Unscheduled Outages and Scheduled Outages in any rolling six (6) Month period and the Energy Output of the Facility Unit, at any time is of the opinion that the Facility Unit is not being Maintained to the standard of a Reasonable and Prudent Operator, it may require that the Independent Engineer conduct an inspection (and, based on the outcome of the inspection, such tests of the Facility Unit's condition as may be necessary) to ascertain whether the Facility is being Maintained to the standard of a Reasonable and Prudent Operator. The Buyer shall provide the seller with 1 weeks notice of the intended inspection. 6.2 If the inspection and, if applicable, tests detailed in clause 6.1 show that the Facility Unit is being Maintained to the standard of a Reasonable and Prudent Operator, the Buyer shall bear all costs of conducting such inspection and tests, including the Seller's reasonable costs and losses. If the inspection and, if applicable, tests show that the Facility Unit is not being Maintained to the standard of a Reasonable and Prudent Operator, the Buyer may require the Seller to undertake such works as may be performed by a Reasonable and Prudent Operator to ensure that the Facility Unit is Maintained to such standard, and the Seller shall bear all costs of conducting such inspection and tests and performing such works, including the Buyer's reasonable costs. 6.3 Any dispute arising from or relating to the performance of the inspection or tests by the Independent Engineer or the results thereof shall be referred to and determined by an Independent Expert in accordance with the provisions of clause 28 Fast-Track Dispute Resolution).
Appears in 6 contracts
Samples: Power Purchase Agreement, Power Purchase Agreement, Power Purchase Agreement
MAINTENANCE INSPECTIONS. 6.1 If the Buyer, on reasonable grounds and based on the number of Unscheduled Outages and Scheduled Outages in any rolling six (6) Month period and the Energy Output of the Facility UnitFacility, at any time is of the opinion that the Facility Unit is not being Maintained to the standard of a Reasonable and Prudent Operator, it may require that the Independent Engineer conduct an inspection (and, based on the outcome of the inspection, such tests of the Facility UnitFacility's condition as may be necessary) to ascertain whether the Facility is being Maintained to the standard of a Reasonable and Prudent Operator. The Buyer shall provide the seller with 1 weeks notice of the intended inspection.
6.2 If the inspection and, if applicable, tests detailed in clause 6.1 show that the Facility Unit is being Maintained to the standard of a Reasonable and Prudent Operator, the Buyer shall bear all costs of conducting such inspection and tests, including the Seller's reasonable costs and losses. If the inspection and, if applicable, tests show that the Facility Unit is not being Maintained to the standard of a Reasonable and Prudent Operator, the Buyer may require the Seller to undertake such works as may be performed by a Reasonable and Prudent Operator to ensure that the Facility Unit is Maintained to such standard, and the Seller shall bear all costs of conducting such inspection and tests and performing such works, including the Buyer's reasonable costs.
6.3 Any dispute arising from or relating to the performance of the inspection or tests by the Independent Engineer or the results thereof shall be referred to and determined by an Independent Expert in accordance with the provisions of clause 28 27 (Fast-Track Dispute Resolution).
Appears in 1 contract
Samples: Power Purchase Agreement
MAINTENANCE INSPECTIONS. 6.1 If the Buyer, on reasonable grounds and based on the number of Unscheduled Outages and Scheduled Outages in any rolling six (6) 6 Month period and the Energy Output of the Facility UnitFacility, at any time is of the opinion that the Facility Unit is not being Maintained to the standard of a Reasonable and Prudent Operator, it may require that the Independent Engineer conduct an inspection (and, based on the outcome of the inspection, such tests of the Facility UnitFacility's condition as may be necessary) to ascertain whether the Facility is being Maintained to the standard of a Reasonable and Prudent Operator. The Buyer shall provide the seller with 1 weeks notice of the intended inspection.
6.2 If the inspection and, if applicable, tests detailed in clause 6.1 show that the Facility Unit is being Maintained to the standard of a Reasonable and Prudent Operator, the Buyer shall bear all costs of conducting such inspection and tests, including the Seller's reasonable costs and losses. If the inspection and, if applicable, tests show that the Facility Unit is not being Maintained to the standard of a Reasonable and Prudent Operator, the Buyer may require the Seller to undertake such works as may be performed by a Reasonable and Prudent Operator to ensure that the Facility Unit is Maintained to such standard, and the Seller shall bear all costs of conducting such inspection and tests and performing such works, including the Buyer's reasonable costs.
6.3 Any dispute arising from or relating to the performance of the inspection or tests by the Independent Engineer or the results thereof shall be referred to and determined by an Independent Expert in accordance with the provisions of clause 28 27 (Fast-Track Dispute Resolution).
Appears in 1 contract
Samples: Power Purchase Agreement