Common use of Manual Disconnect Switch Clause in Contracts

Manual Disconnect Switch. 5.1. Participant must install a manual, lockable, visible load break disconnect switch between the generation source and the Distributor’s system that is visibly marked “Participant Generation Disconnect.” The disconnect shall be mounted separate from but adjacent to the Distributor’s meter socket. The Participant shall ensure that such manual disconnect switch shall remain readily accessible to Distributor and be capable of being locked in the open position with a single Distributor utility padlock. A permanent, weatherproof single line diagram of the facility must be located adjacent to the disconnect switch. Names and current telephone numbers of at least two persons authorized to provide access to the facility that have authority to make decisions regarding the interconnection and operation of the Qualifying System will be included.

Appears in 6 contracts

Samples: Interconnection and Parallel Operation Agreement, Interconnection Agreement, Interconnection Agreement

AutoNDA by SimpleDocs

Manual Disconnect Switch. 5.1. Participant must install a manual, lockable, visible load break disconnect switch between the generation source and the Distributor’s system that is visibly marked “Participant Generation Disconnect.” ”. The disconnect shall be mounted separate from but adjacent to the Distributor’s meter socket. The Participant shall ensure that such manual disconnect switch shall remain readily accessible to Distributor and be capable of being locked in the open position with a single Distributor utility padlock. A permanent, weatherproof single line diagram of the facility must be located adjacent to the disconnect switch. Names and current telephone numbers of at least two persons authorized to provide access to the facility that have authority to make decisions regarding the interconnection and operation of the Qualifying System will be included.

Appears in 1 contract

Samples: Interconnection Agreement

Manual Disconnect Switch. 5.1. Participant must install a manual, lockable, visible load break disconnect switch between the generation source and the DistributorLPC’s system that is visibly marked “Participant Generation Disconnect.” ”. The disconnect shall be mounted separate from from, but adjacent to to, the DistributorLPC’s meter socket. The Participant shall ensure that such manual disconnect switch shall remain readily accessible to Distributor LPC, and be capable of being locked in the open position with a single Distributor LPC utility padlock. A permanent, weatherproof single line diagram of the facility must be located adjacent to the disconnect switch. Names and current telephone numbers of at least two persons authorized to provide access to the facility that have authority to make decisions regarding the interconnection and operation of the Qualifying System will be included.

Appears in 1 contract

Samples: Interconnection Agreement

Manual Disconnect Switch. 5.1. Participant must install a manual, lockable, visible load break disconnect switch between the generation source and the DistributorCORED’s system that is visibly marked “Participant Generation Disconnect.” ”. The disconnect switch shall be mounted separate from but adjacent to the DistributorCORED’s meter socket. The Participant shall ensure that such manual disconnect switch shall remain readily accessible to Distributor CORED and be capable of being locked in the open position with a single Distributor CORED utility padlock. A permanent, weatherproof single line diagram of the facility must be located adjacent to the disconnect switch. Names and current telephone numbers of at least two persons authorized to provide access to the facility that have authority to make decisions regarding the interconnection and operation of the Qualifying System will be included.

Appears in 1 contract

Samples: Interconnection Agreement

AutoNDA by SimpleDocs

Manual Disconnect Switch. 5.1. Participant must install a manual, lockable, visible load break disconnect switch between the generation source Qualifying System and the Distributor’s system HUB's System that is visibly marked “Participant "Generation Disconnect." The disconnect shall be mounted separate from but adjacent to the Distributor’s HUB's meter socket. The Participant shall ensure that such manual disconnect switch shall remain readily accessible to Distributor HUB and be capable of being locked in the open position with a single Distributor HUB utility padlock. A permanent, weatherproof single single-line diagram of the facility must be located adjacent to the disconnect switch. Names and current telephone numbers of at least two persons authorized to provide access to the facility that have authority to make decisions regarding the interconnection and operation of the Qualifying System will shall be includedincluded with the diagram.

Appears in 1 contract

Samples: Interconnection, Metering, and Parallel Operation Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!