Measures to be taken. A Party affected by an event of Force Majeure shall continue to perform its obligations under the Contract as far as is reasonably practical, and shall take all reasonable measures to minimize the consequences of any event of Force Majeure.
Appears in 2 contracts
Samples: Request for Proposal, Request for Proposal
Measures to be taken. (a) A Party affected by an event of Force Majeure shall continue to perform its obligations under the Contract as far as is reasonably practical, practical and shall take all reasonable measures to minimize the consequences of any event of Force Majeure.
Appears in 1 contract
Samples: Contract for Legal Services
Measures to be taken. (a) A Party affected by an event of Force Majeure shall continue to perform its obligations under the Contract as far as is reasonably practical, practical and shall take all reasonable measures to minimize minimise the consequences of any event of Force Majeure.
Appears in 1 contract
Samples: Consultants’ Services Contract
Measures to be taken. A Party affected by an event of Force Majeure shall continue to perform its obligations under the Contract Agreement as far as is reasonably practical, and shall take all reasonable measures to minimize the consequences of any event of Force Majeure. A Party affected by an event of Force Majeure shall notify the other Party of such event as soon as possible, and in any case not later than ____days following the occurrence of such event, providing evidence of the nature and cause of such event, and shall similarly give written notice of the restoration of normal conditions as soon as possible.
Appears in 1 contract
Samples: Credit Facility Agreement
Measures to be taken. A 5.4 Party affected by an event of Force Majeure shall continue to perform its obligations under the Contract Agreement as far as is reasonably practical, and shall take all reasonable measures to minimize minimise the consequences of any event of Force Majeure.
Appears in 1 contract
Samples: Consultancy Services Agreement