Metering Data. At Developer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of Interconnection.
Appears in 208 contracts
Samples: Generator Interconnection Agreement, Service Agreement, Standard Large Generator Interconnection Agreement
Metering Data. At Developer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of Interconnection.
Appears in 28 contracts
Samples: Standard Large Generator Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Metering Data. At Developer’s 's expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of Interconnection.
Appears in 24 contracts
Samples: Interconnection Agreement, Large Generator Interconnection Agreement, Large Generator Interconnection Agreement
Metering Data. At Developer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of Interconnection.
Appears in 24 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Metering Data. At Developer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Merchant Transmission Facility to the Point of Interconnection.
Appears in 16 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Metering Data. At Developer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of Interconnection.Interconnection.
Appears in 12 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Metering Data. At Developer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission OwnerNational Grid, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of Interconnection.
Appears in 10 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Metering Data. At Developer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and the NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from transmitted by the Large Generating Transmission Facility to at the Point of Interconnection.
Appears in 4 contracts
Samples: Service Agreement, Interconnection Agreement, Transmission Facility Interconnection Agreement
Metering Data. At DeveloperDeveloper’sConnecting Transmission Owner’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of InterconnectionInterconnectionat the Metering Points.
Appears in 3 contracts
Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement
Metering Data. At Developer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of Interconnection.. COMMUNICATIONS
Appears in 3 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Metering Data. At Developer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of Interconnection.. 30 SERVICE AGREEMENT NO. 2475
Appears in 2 contracts
Samples: Large Generator Interconnection Agreement (Lgia), Interconnection Agreement
Metering Data. At Developer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISO. Such telemetered data SERVICE AGREEMENT NO. 1894 shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of Interconnection.
Appears in 2 contracts
Samples: Standard Large Generator Interconnection Agreement, Standard Large Generator Interconnection Agreement
Metering Data. At Developer’s expense, the theThe metered data at the Metering Points shall be telemetered to one or more locations as currently designated by the Connecting Transmission Owner, Developer and the NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of InterconnectionInterconnectionat the Metering Points.
Appears in 1 contract
Metering Data. At Transmission Developer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of InterconnectionInterconnectionat the Metering Points.
Appears in 1 contract
Metering Data. At Transmission Developer’s expense, the metered data shall be telemetered to one or more locations designated by NYISO and Connecting Transmission Owner, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of InterconnectionInterconnectionat the Metering Points.
Appears in 1 contract
Metering Data. At Developer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of Interconnection.. 31 SERVICE AGREEMENT NO. 2629
Appears in 1 contract
Metering Data. At Developer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating GeneratingMerchant Transmission Facility to the Point of Interconnection.
Appears in 1 contract
Samples: Interconnection Agreement
Metering Data. At DeveloperDeveloper’sCon Xxxxxx’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISONYISOthe Parties. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of Interconnection.
Appears in 1 contract
Metering Data. At DeveloperDeveloper’sInterconnection Customer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer DeveloperInterconnection Customer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of Interconnection.
Appears in 1 contract
Samples: Sithe Interconnection Agreement
Metering Data. At Developer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of Interconnection.. SERVICE AGREEMENT NO. 1774
Appears in 1 contract
Samples: Lgia
Metering Data. At Developer’s expense, the metered data shall be telemetered to one or more locations designated by Connecting Transmission Owner, Developer and NYISO. Such telemetered data shall be used, under normal operating conditions, as the official measurement of the amount of energy delivered from the Large Generating Facility to the Point of Interconnection.official
Appears in 1 contract