Milestone Deadlines Sample Clauses

Milestone Deadlines. Notwithstanding the qualified nature of Orchard’s obligations under clause 4.1(b), the Parties acknowledge that any delay by Orchard in the provision of documentation and/or materials or performance of its activities set out in the Collaboration Plan (together the “Orchard Performance Obligations”) could prevent BioMedica from achieving the Milestones on or before the dates for such achievement as set out in Schedule 3. In the event that there is a delay in the performance of any Orchard Performance Obligations caused by Orchard and such delay directly or indirectly prevents BioMedica from achieving a Milestone on or before the dates for such achievement as set out in Schedule 3, the dates for achieving the affected Milestone and any linked subsequent Milestones which are affected by such delay shall be extended by the length of such delay. In the event that the Parties are unable to agree on (i) whether the delay in the performance of any Orchard Performance Obligations caused the delay or directly or indirectly prevented BioMedica from achieving a Milestone by the due date; or (ii) the applicable extension to such dates, the matter shall be referred to the Steering Committee for determination in accordance with clause 2.6.
AutoNDA by SimpleDocs
Milestone Deadlines. The Vendor’s timely performance of all Work is of the essence. The Vendor shall develop a Schedule for the Authority’s approval that conforms to the milestone deadlines (“Milestone Deadlines”) described below and in accordance with the requirements in the Technical Specifications. Once approved, the Schedule shall become a Contract Document.
Milestone Deadlines. For purposes of the Lease and this Tenant Work Letter, Landlord shall achieve the following milestones (each a “Milestone”) by the applicable date set forth below (such applicable date, a “Milestone Deadline”), subject to extension for Tenant Delay and Force Majeure Delay (defined below). • Substantial Completion Date – June 1, 2018. • Final Completion DateApril 1, 2019. • Completion of the Hotel and The Sanctuary – April 1, 2019.

Related to Milestone Deadlines

  • Time Deadlines Tenant shall use its best, good faith, efforts and all due diligence to cooperate with the Architect, the Engineers, and Landlord to complete all phases of the Construction Drawings and the permitting process and to receive the permits, and with Contractor for approval of the "Cost Proposal," as that term is defined in Section 4.2 of this Tenant Work Letter, as soon as possible after the execution of the Lease, and, in that regard, shall meet with Landlord on a scheduled basis to be determined by Landlord, to discuss Tenant's progress in connection with the same. The applicable dates for approval of items, plans and drawings as described in this Section 3, Section 4, below, and in this Tenant Work Letter are set forth and further elaborated upon in Schedule 1 (the "Time Deadlines"), attached hereto. Tenant agrees to comply with the Time Deadlines.

  • Milestone A principal event specified in the Contract Documents including the Material Completion and Occupancy Date and other events relating to an intermediate completion date or time.

  • Development Milestones In addition to its obligations under Paragraph 7.1, LICENSEE specifically commits to achieving the following development milestones in its diligence activities under this AGREEMENT: (a) (b).

  • Milestone Event Milestone Payment [***] [***]

  • Development Milestone Payments In partial consideration for the rights and licenses granted to Coya hereunder, within ten days after the first achievement of each milestone event in a given Indication set forth in this Section 5.2 (Development Milestone Payments) with respect to a Product (each, a “Development Milestone Event”) by or on behalf of Coya or any of its Affiliates or Sublicensees, Coya shall provide ARScience Bio written notice to ARScience Bio identifying the Development Milestone Event achieved. Upon receipt of any such notice of first achievement of a Development Milestone Event by Coya or its Affiliates or Sublicensees, ARScience Bio will promptly invoice Coya for the applicable Development Milestone Event and Coya will make a milestone payment to ARScience Bio in the amount set forth in this Section 5.2 (Development Milestone Payments) corresponding to such Development Milestone Event (each, a “Development Milestone Payment”) within 45 days of receipt of such invoice. On an Indication-by-Indication basis, each Development Milestone Payment shall be payable only upon the first achievement of the corresponding Development Milestone Event by a Product, in any given Indication for which the Development Milestone Events have not been previously achieved (each such Indication, a “New Indication”). No amounts shall be due for subsequent or repeated achievements of such Development Milestone Event with respect to the same or different Mono Product or Combination Product, as applicable, in such Indication. Accordingly and for clarity, the Development Milestone Payment shall be paid only once, when first achieved by Coya, an Affiliate or a Sublicensee, but no payment shall be due if the same milestone is subsequently achieved by one of Coya, an Affiliate or a Sublicensee. For clarity, the amounts owed in Column (a) below shall be due for the first Combination Product to achieve the Development Milestone Events in a New Indication and the amounts owned in Column (c) below shall be due for the first Mono Product to achieve the Development Milestone Events in a New Indication. Any Combination Product or Mono Product to achieve the Development Milestone Events in a New Indication after the first achievement of the Development Milestone Events as described in the foregoing sentence will cause the amounts in Column (b) with respect to a Combination Product and Column (d) with respect to a Mono Product to be due and payable by Coya upon each such occurrence. If the first Product to achieve a Development Milestone Event in any Indication is a Combination Product, the amounts in Column (a) below shall be due and payable by Coya. If the next Product to achieve a Development Milestone Event in a New Indication is a Mono Product, the amounts in Column (c) below would be due and payable by Coya; provided, that if such next Product to achieve a Development Milestone Event in a New Indication is a Combination Product, the amounts in Column (b) would be due and payable by Coya. By way of example, if a Combination Product achieves IND Acceptance in ALS, and is the first Product to achieve a Development Milestone Event under this Agreement, [***] will be due and payable by Coya. If subsequently a Mono Product achieves IND Acceptance in ALS, no Development Milestone Payments will be due and payable by Coya under this Agreement. However, if subsequently any Combination Product achieves IND Acceptance in Alzheimer’s disease, [***] would be due and payable by Coya.

  • Milestones Subject to the provisions of the SGIP, the Parties shall agree on milestones for which each Party is responsible and list them in Attachment 4 of this Agreement. A Party’s obligations under this provision may be extended by agreement. If a Party anticipates that it will be unable to meet a milestone for any reason other than a Force Majeure event, it shall immediately notify the other Parties of the reason(s) for not meeting the milestone and (1) propose the earliest reasonable alternate date by which it can attain this and future milestones, and (2) requesting appropriate amendments to Attachment 4. The Party affected by the failure to meet a milestone shall not unreasonably withhold agreement to such an amendment unless it will suffer significant uncompensated economic or operational harm from the delay, (1) attainment of the same milestone has previously been delayed, or (2) it has reason to believe that the delay in meeting the milestone is intentional or unwarranted notwithstanding the circumstances explained by the Party proposing the amendment.

  • Regulatory Milestones Celgene shall make the following approval milestone payments to Jounce that are set forth below upon the first achievement by or on behalf of Celgene, its Affiliates or Sublicensees of the Regulatory Milestone Events set forth below with respect to the first Co-Co Product that achieves such event. For clarity, each milestone set forth below shall be due and payable one time only (regardless of the number of Co-Co Products to achieve any such Regulatory Milestone Event). CERTAIN CONFIDENTIAL PORTIONS OF THIS EXHIBIT WERE OMITTED AND REPLACED WITH “[***]”. A COMPLETE VERSION OF THIS EXHIBIT HAS BEEN FILED SEPARATELY WITH THE SECRETARY OF THE SECURITIES AND EXCHANGE COMMISSION PURSUANT TO AN APPLICATION REQUESTING CONFIDENTIAL TREATMENT PURSUANT TO RULE 406 PROMULGATED UNDER THE SECURITIES ACT OF 1933, AS AMENDED. Regulatory Milestone Event (For the first Co-Co Product that achieves such event) Milestone Payments (in $ millions) [***] [***] [***] [***] [***] [***] [***] [***] [***] [***] [***] [***] For each of Paragraphs (1) - (3) of this Exhibit C-2, the Parties understand and agree that in no event will more than one (1) milestone payment be paid with respect to any specific event triggering a payment under this Jounce Lead Co-Co Agreement.

  • Commercial Milestones In partial consideration of the rights granted by AstraZeneca to Licensee hereunder, Licensee shall pay to AstraZeneca the following payments, which shall be non-refundable, non-creditable and fully earned upon the first achievement of the applicable milestone event:

  • Milestone Fees Licensee will pay Milestone Fees indicated in Section 3.1(b) of the Patent & Technology License Agreement by the Quarterly Payment Deadline for the Contract Quarter in which the milestone events set forth in Section 3.1(b) of the Patent & Technology License Agreement are achieved.

  • Sales Milestones Subject to the terms and conditions set forth in the Agreement, in the event that the Annual Net Sales made by or on behalf of a Selling Entity for all Licensed Products in a given calendar year first exceeds a threshold set forth in the table immediately below, Pyxis shall pay to LCB the following one-time, non-refundable, non-creditable milestone payments. Annual Net Sales Milestone Threshold Payment (US Dollars) [***] [***] [***] [***] [***] [***] [***] [***] [***] [***] In the event that in a given calendar year more than one (1) Annual Net Sales milestone threshold is achieved, Pyxis shall pay to LCB each separate Annual Net Sales milestone payment with respect to each Annual Net Sales milestone threshold that is achieved in such calendar year. Pyxis shall notify LCB in writing upon the first achievement, in respect of a Licensed Product, by or on behalf of Pyxis or its Affiliate or Sublicensee, of each of the Milestones set forth in Section 5.2 (Development Milestones), Section 5.3 (Regulatory Milestones) and Section 5.4 (Sales Milestones) no later than [***] of Pyxis’s knowledge of achievement thereof, and in any event, each of the Milestones set forth in Section 5.4 (Sales Milestones) no later than [***] after the end of the applicable calendar year in which such Milestone is achieved. No later than [***] of receipt of an appropriate invoice from LCB, Pyxis shall pay the applicable payment due upon achievement of the corresponding Milestone Event. Each Milestone Event shall be deemed to be achieved once for all Licensed Products and shall be payable only once.