Common use of Mitigation of Delay Clause in Contracts

Mitigation of Delay. Contractor shall take all reasonable actions to minimize the delay caused by any of the above factors, and shall notify Owner in writing with a copy to the Design Professional of any event allowing for excuse or delay not later than seven days after the Contractor first becomes aware of the event, or should have become aware, of the event; otherwise Contractor will be deemed to have waived the excuse or delay.

Appears in 43 contracts

Samples: Construction Contract, Construction Contract, Construction Contract