Monthly Construction Progress Report. On or before the last Business Day of any calendar month during the Construction Period, a report executed by a Borrower’s Authorized Representative that: (A) specifies the amount of Total Project Costs expended since the Effective Date as well as during the preceding calendar month and the amount of Total Project Costs estimated to be required to complete the Project; (B) provides a demonstration that the Borrower has sufficient funds (including funds on hand and funds obtainable without undue delay or conditions that cannot reasonably be satisfied by the Borrower as and when such funds are needed) to complete the Project; (C) provides an assessment of the overall construction progress of the Project since the date of the last report and since the Effective Date, together with an assessment of how such progress compares to the Construction Schedule; (D) specifies the most recent projections for the Substantial Completion Date as compared to the Projected Substantial Completion Date specified in the Financial Plan most recently approved by the TIFIA Lender; (E) provides a detailed description of all material problems (including actual and anticipated cost and/or schedule overruns, if any) encountered or anticipated in connection with the construction of the Project since the date of the last report, together with an assessment of how such problems may impact the Construction Schedule and the meeting of critical dates thereunder and a detailed description of the proposed solutions to any such problems; (F) specifies the delivery status of major equipment and the effect, if any, that the anticipated delivery dates of such equipment has on the overall Construction Schedule; (G) specifies any proposed or pending change orders; (H) specifies any material changes or deviations from the Borrower’s land procurement plans or schedule; (I) includes a copy of each report delivered by a Construction Contractor to the Borrower that has not previously been delivered to the TIFIA Lender in a prior report delivered pursuant to this Section 23(b)(i) (Monthly Construction Progress Report); and (J) provides a discussion or analysis of such other matters related to the Project as the TIFIA Lender may reasonably request. The Borrower shall respond, and use commercially reasonable efforts to cause the Construction Contractors to respond, to the TIFIA Lender’s inquiries regarding such report, the construction of the Project and any Construction Contractor’s performance of its obligations under the Construction Agreement to which such Construction Contractor is a party.
Appears in 2 contracts
Samples: Tifia Loan Agreement, Tifia Loan Agreement
Monthly Construction Progress Report. On or before the last Business Day of any calendar month during the Construction Period, a report executed by a Borrower’s Authorized Representative that:
(A) : specifies the amount of Total Project Costs expended since the Effective Date as well as during the preceding calendar month and the amount of Total Project Costs estimated to be required to complete the Project;
(B) ; provides a demonstration that the Borrower has sufficient funds (including funds on hand and funds obtainable without undue delay or conditions that cannot reasonably be satisfied by the Borrower as and when such funds are needed) to complete the Project;
(C) ; provides an assessment of the overall construction progress of the Project since the date of the last report and since the Effective Date, together with an assessment of how such progress compares to the Construction Schedule;
(D) ; specifies the most recent projections for the Substantial Completion Date as compared to the Projected Substantial Completion Date specified in the Financial Plan most recently approved by the TIFIA Lender;
(E) ; provides a detailed description of all material problems (including actual and anticipated cost and/or schedule overruns, if any) encountered or anticipated in connection with the construction of the Project since the date of the last report, together with an assessment of how such problems may impact the Construction Schedule and the meeting of critical dates thereunder and a detailed description of the proposed solutions to any such problems;
(F) ; specifies the delivery status of major equipment and the effect, if any, that the anticipated delivery dates of such equipment has on the overall Construction Schedule;
(G) ; specifies any proposed or pending change orders;
(H) ; specifies any material changes or deviations from the Borrower’s land procurement plans or schedule;
(I) ; includes a copy of each report delivered by a Construction Contractor to the Borrower that has not previously been delivered to the TIFIA Lender in a prior report delivered pursuant to this Section 23(b)(i) (Monthly Construction Progress Report); and
(J) and provides a discussion or analysis of such other matters related to the Project as the TIFIA Lender may reasonably request. The Borrower shall respond, and use commercially reasonable efforts to cause the Construction Contractors to respond, to the TIFIA Lender’s inquiries regarding such report, the construction of the Project and any Construction Contractor’s performance of its obligations under the Construction Agreement to which such Construction Contractor is a party.. [Recovery Plan. If the monthly construction progress report described in Section 23(b)(i) (Monthly Construction Progress Report) or the monthly report issued pursuant to the FTA Project Management Oversight Regulations indicates either a failure to maintain the Construction Schedule, including a failure to achieve Substantial Completion by the Projected Substantial Completion Date or the anticipated Substantial Completion Date set forth in the previous monthly construction progress report provided pursuant to Section 23(b)(i) (Monthly Construction Progress Report), or actual or projected Eligible Project Cost overruns in excess of five percent (5%) of the Eligible Project Costs reflected in the Project Budget, or both, then the Borrower shall notify the TIFIA Lender and the FTA Regional Office of such failure and shall, upon request by the TIFIA Lender or the FTA Regional Office, provide the TIFIA Lender and the FTA Regional Office within thirty (30) days of receipt of such request, a Recovery Plan for review and acceptance by the TIFIA Lender and the FTA Regional Office.]125 [Quarterly Traffic and Operating Report. For the period commencing after the Substantial Completion Date, deliver to the TIFIA Lender, not later than ninety (90) days after the end of each financial quarter, a traffic and operating report showing (A) the operating data for the Project for the previous financial quarter, including total Project Revenues received and total Operations and Maintenance Expenses and Capital Expenditures incurred, (B) the variances for such period between the Project Revenues actually received and the budgeted Project Revenues as shown in the Financial Plan most recently approved by the TIFIA Lender, together with a brief narrative explanation of the reasons for any such variance of [ten percent (10%)] or more, and (C) the variances for such period between the actual Operations and Maintenance Expenses incurred and the budgeted Operations and Maintenance Expenses as shown in the Financial Plan, together with a brief narrative explanation of the reasons for any such variance of [ten percent (10%)] or more.]126
Appears in 1 contract
Samples: Tifia Loan Agreement
Monthly Construction Progress Report. On or before the last Business Day of any calendar month during the Construction Period, a report executed by a Borrower’s Authorized Representative that:
that (A) specifies the amount of Total Project Costs expended since the Effective Date as well as during the preceding calendar month and the amount of Total Project Costs estimated to be required to complete the Project;
, (B) provides a demonstration that the Borrower has sufficient funds (including funds on hand and funds obtainable without undue delay or conditions that cannot reasonably be satisfied by the Borrower as and when such funds are needed) to complete the Project;
, (C) provides an assessment of the overall construction progress of the Project since the date of the last report and since the Effective Date, together with an assessment of how such progress compares to the Construction Schedule;
, (D) specifies the most recent projections for the Substantial Completion Date as compared to the Projected Substantial Completion Date specified in the Financial Plan most recently approved by the TIFIA Lender;
, (E) provides a detailed description of all material problems (including actual and anticipated cost and/or schedule overruns, if any) encountered or anticipated in connection with the construction of the Project since the date of the last report, together with an assessment of how such problems may impact the Construction Schedule and the meeting of critical dates thereunder and a detailed description of the proposed solutions to any such problems;
, (F) specifies the delivery status of major equipment and the effect, if any, that the anticipated delivery dates of such equipment has on the overall Construction Schedule;
, (G) specifies any proposed or pending change orders;
, (H) specifies any material changes or deviations from the Borrower’s land procurement plans or schedule;
, (I) includes a copy of each report delivered by a Construction Contractor to the Borrower that has not previously been delivered to the TIFIA Lender in a prior report delivered pursuant to this Section 23(b)(i) (Monthly Construction Progress Report); and
, and (J) provides a discussion or analysis of such other matters related to the Project as the TIFIA Lender may reasonably request. The Borrower shall respond, and use commercially reasonable efforts to cause the Construction Contractors to respond, to the TIFIA Lender’s inquiries regarding such report, the construction of the Project and any Construction Contractor’s performance of its obligations under the Construction Agreement to which such Construction Contractor is a party.. [Recovery Plan. In the event that the monthly construction progress report described in Section 23(b)(i) (Monthly Construction Progress Report) or the monthly report issued pursuant to the FTA Project Management Oversight Regulations indicates either a failure to maintain the Construction Schedule, including a failure to achieve Substantial Completion by the Projected Substantial Completion Date or the anticipated Substantial Completion Date set forth in the previous monthly construction progress report provided pursuant to Section 23(b)(i) (Monthly Construction Progress Report), or actual or projected Eligible Project Cost overruns in excess of five percent (5%) of the Eligible Project Costs reflected in the Project Budget, or both, then the Borrower shall notify the TIFIA Lender and the FTA Regional Office of such failure and shall, upon request by the TIFIA Lender or the FTA Regional Office, provide the TIFIA Lender and the FTA Regional Office within thirty (30) days of receipt of such request, a Recovery Plan for review and acceptance by the TIFIA Lender and the FTA Regional Office.]125
Appears in 1 contract
Samples: Tifia Loan Agreement