Monthly Progress Payments. 6.2.1 On the tenth (10th) day of each month, Design-Builder shall submit for Department’s review and approval its Application for Payment requesting payment for all Work performed as of the first day of such month and coinciding with the progress reflected in the monthly Baseline Schedule update. The Application for Payment shall be accompanied by all supporting documentation required by the Contract Documents and/or established at the meeting required by .1 Design-Builder shall identify each activity, and the value in dollars of such activity, in accordance with Section 6.1.1 above. Applications for Payment shall be made based on the following earned values. .1 Design-Builder shall earn twenty percent (20%) of the value of an activity upon initiation of the respective activity. .2 Design-Builder shall earn eighty percent (80%) of the value of an activity upon completion of the respective activity. .2 QA/QC shall be an integral part of each activity. As part of each Application for Payment that includes completed activities, Design-Builder shall submit with the Application for Payment evidence of the QA/QC reviews, including any checklists, summary data, high- level/outline calculations or design checks, and evaluations of the work and the qualifications of the responsible personnel that completed the work, etc., that the relevant QA or QC reviewer relied on to make its determination the Work is complete and conforms to the requirements of the Contract Documents. Furthermore, the QAM shall: (a) verify that the design included in each activity has been completed in accordance with the Contract Documents; (b) certify that the construction included in each activity has been completed in accordance with the Contract Documents; and (c) certify that all required QA/QC tests, measurements, permits or other requirements have been completed and all non-conformance reports relative to the respective activity have been resolved. The QAM’s certification for monthly Application of Payment for construction activities shall include the following statement: As the Quality Assurance Manager, I certify, to the best of my knowledge, information and belief based upon and to the extent of: (i) current on-site observations and field testing required to be performed; and (ii) material certifications and test reports, that each Work Package shown herein as complete has been completed in accordance with the Contract Documents, and that all required QA/QC tests, measurements, permits or other requirements have been completed and all non-conformance reports relative to a respective Work Package have been resolved except for the attached list of open issues. 6.2.2 The Application for Payment may request payment for equipment and materials not yet incorporated into the Project, provided that: (i) Department, in its sole discretion, agrees that it is willing to allow payment for such equipment and materials; (ii) Department is satisfied that the equipment and materials are suitably stored at either the Site or another acceptable location; (iii) the equipment and materials are protected by suitable insurance; and (iv) upon payment, Department will receive the equipment and materials free and clear of all liens and encumbrances. 6.2.3 The Application for Payment shall constitute Design-Builder’s representation that the Work has been performed consistent with the Contract Documents, has progressed to the point indicated in the Application for Payment, and that title to all Work will pass to Department free
Appears in 2 contracts
Samples: Lump Sum Design Build Agreement, Lump Sum Design Build Agreement
Monthly Progress Payments. 6.2.1 On the tenth (10th) day of each month, Design-Builder shall submit for Department’s review and approval its Application for Payment requesting payment for all Work performed as of the first day of such month and coinciding with the progress reflected in the monthly Baseline Schedule update. The Application for Payment shall be accompanied by all supporting documentation required by the Contract Documents and/or established at the meeting required byby Section 2.1.2 hereof. Payment shall be made in accordance with the following earned value calculation:
.1 Design-Builder shall identify each activity, and the value in dollars of such activity, in accordance with Section 6.1.1 above. Applications for Payment shall be made based on the following earned values.
.1 Design-Builder shall earn twenty percent (20%) of the value of an activity upon initiation of the respective activity.
.2 Design-Builder shall earn eighty percent (80%) of the value of an activity upon completion of the respective activity.
.2 QA/QC shall be an integral part of each activity. As part of each Application for Payment that includes completed activities, Design-Builder shall submit with the Application for Payment evidence of the QA/QC reviews, including any checklists, summary data, high- level/outline calculations or design checks, and evaluations of the work and the qualifications of the responsible personnel that completed the work, etc., that the relevant QA or QC reviewer relied on to make its determination the Work is complete and conforms to the requirements of the Contract Documents. Furthermore, the QAM Builder’s designated quality assurance manager shall: (a) verify that the design included in each activity has been completed in accordance with the Contract Documents; (b) certify that the construction included in each activity has been completed in accordance with the Contract Documents; and (c) certify that all required QA/QC tests, measurements, permits or other requirements have been completed and all non-conformance reports relative to the respective activity have been resolved. The QAM’s certification Design- Builder shall submit with the Application for monthly Application Payment evidence of Payment for construction activities shall include the following statement: As QA/QC reviews, including any checklists, summary data, high-level/outline calculations or design checks, and evaluations of the Quality Assurance Managerwork and the qualifications of the responsible personnel that completed the work, I certifyetc., that the relevant QA or QC reviewer relied on to make its determination the work is complete and conforms to the best requirements of my knowledge, information and belief based upon and to the extent of: (i) current on-site observations and field testing required to be performed; and (ii) material certifications and test reports, that each Work Package shown herein as complete has been completed in accordance with the Contract Documents, and that all required QA/QC tests, measurements, permits or other requirements have been completed and all non-conformance reports relative to a respective Work Package have been resolved except for the attached list of open issues.
6.2.2 The Application for Payment may request payment for equipment and materials not yet incorporated into the Project, provided that: (i) Department, in its sole discretion, agrees that it is willing to allow payment for such equipment and materials; (ii) Department is satisfied that the equipment and materials are suitably stored at either the Site or another acceptable location; (iii) the equipment and materials are protected by suitable insurance; and (iv) upon payment, Department will receive the equipment and materials free and clear of all liens and encumbrances.
6.2.3 The Application for Payment shall constitute Design-Builder’s representation that the Work has been performed consistent with the Contract Documents, has progressed to the point indicated in the Application for Payment, and that title to all Work will pass to Department freefree and clear of all claims, liens, encumbrances, and security interests upon the incorporation of the Work into the Project, or upon Design-Builder’s receipt of payment, whichever occurs earlier.
Appears in 1 contract
Samples: Lump Sum Design Build Agreement
Monthly Progress Payments. 6.2.1 On the tenth (10th) day of each month, Design-Builder shall submit for Department’s review and approval its Application for Payment requesting payment for all Work performed as of the first day of such month and coinciding with the progress reflected in the monthly Baseline Schedule update. The Application for Payment shall be accompanied by all supporting documentation required by the Contract Documents and/or established at the meeting required byby Section 2.1.2 hereof. Payment shall be made in accordance with the following earned value calculation:
.1 Design-Builder shall identify each activity, and the value in dollars of such activity, in accordance with Section 6.1.1 above. Applications for Payment shall be made based on the following earned values.
.1 Design-Builder shall earn twenty percent (20%) of the value of an activity upon initiation of the respective activity.
.2 Design-Builder shall earn eighty percent (80%) of the value of an activity upon completion of the respective activity.
.2 QA.0 XX/QC XX shall be an integral part of each activity. As part of each Application for Payment that includes completed activities, Design-Builder Builder’s designated quality assurance managerBuilder shall submit with the Application for Payment evidence of the QA/QC reviews, including any checklists, summary data, high- high-level/outline calculations or design checks, and evaluations of the work and the qualifications of the responsible personnel that completed the work, etc., that the relevant QA or QC reviewer relied on to make its determination the Work is complete and conforms to the requirements of the Contract Documents. Furthermore, the QAM shall: (a) verify that the design included in each activity has been completed in accordance with the Contract Documents; (b) certify that the construction included in each activity has been completed in accordance with the Contract Documents; and (c) certify that all required QA/QC tests, measurements, permits or other requirements have been completed and all non-non- conformance reports relative to the respective activity have been resolved. The Design-Builder shall submit with the Application for Payment evidence of the QA/QC reviews, including any checklists, summary data, high-level/outline calculations or design checks, and evaluations of the work and the qualifications of the responsible personnel that completed the work, etc., that the relevant QA or QC reviewer relied on to make its determination the work is complete and conforms to the requirements of the Contract Documents.The QAM’s certification for monthly Application of Payment for construction activities shall include the following statement: As the Quality Assurance Manager, I certify, to the best of my knowledge, information and belief based upon and to the extent of: (i) current on-site observations and field testing required to be performed; and (ii) material certifications and test reports, that each Work Package shown herein as complete has been completed in accordance with the Contract Documents, and that all required QA/QC tests, measurements, permits or other requirements have been completed and all non-conformance reports relative to a respective Work Package have been resolved except for the attached list of open issues.
6.2.2 The Application for Payment may request payment for equipment and materials not yet incorporated into the Project, provided that: (i) Department, in its sole discretion, agrees that it is willing to allow payment for such equipment and materials; (ii) Department is satisfied that the equipment and materials are suitably stored at either the Site or another acceptable location; (iii) the equipment and materials are protected by suitable insurance; and (iv) upon payment, Department will receive the equipment and materials free and clear of all liens and encumbrances.
6.2.3 The Application for Payment shall constitute Design-Builder’s representation that the Work has been performed consistent with the Contract Documents, has progressed to the point indicated in the Application for Payment, and that title to all Work will pass to Department freefree and clear of all claims, liens, encumbrances, and security interests upon the incorporation of the Work into the Project, or upon Design-Builder’s receipt of payment, whichever occurs earlier.
Appears in 1 contract
Samples: Lump Sum Design Build Agreement