PROGRESS PAYMENT.
9.2.1 City shall retain five percent (5%) of the undisputed amount due on each progress payment, or the percentage stated in the Notice Inviting Bids, whichever is greater, as retention to ensure full and complete performance of the Work. Subject to City’s right of withholding under Paragraph 9.4.2 of these General Conditions, City agrees to pay to Contractor within thirty (30) Days of receipt of a properly submitted Application for Payment an amount equal to ninety-five percent (95%), or a lesser amount if corresponding to a higher retention percentage, if applicable, of the sum of the following, excepting therefrom any amounts which are disputed by City:
(i) Construction Manager’s determination of the value, expressed as a percentage of the Contract Sum, of the Work in permanent place that has been tested and accepted as of the end of the preceding month.
(ii) Construction Manager’s determination of the value of materials suitably stored but not yet incorporated into the Work, subject to Paragraph 9.3.6 of these General Conditions.
(iii) Less amounts previously paid.
9.2.2 At any Time after fifty percent (50%) of the Work has been determined by Construction Manager to be completed, City may in its sole discretion, make any of the remaining progress payments in accordance with the calculation in Paragraph 9.2.1 of these General Conditions based on one hundred percent (100%) of City’s determination of the value of the Work in place and of stored materials not yet incorporated into the Work.
9.2.3 Progress payments shall not be construed as City's Acceptance of any or all of the Work and shall not be a waiver of any or all rights City has under the Contract Documents.
PROGRESS PAYMENT. 5.4.1 After receipt by the Contract Administrator of a Proper Invoice submitted by the Contractor in accordance with 5.3 – PROPER INVOICES:
.1 the Contract Administrator shall promptly inform the Owner of the date of receipt of the Proper Invoice;
PROGRESS PAYMENT. The Contract Price shall be due and payable by the Buyer to the Builder in installments as indicated on Schedule 1 attached hereto.
PROGRESS PAYMENT. The Incubatee is allowed to claim the Progress Payment after provision of: - Documentation evidencing the actual achievement of the milestone(s) as defined in the Payment Plan specified hereunder; - Invoice(s) covering the purchase of licences and/or the costs of product development.
PROGRESS PAYMENT. The term "
PROGRESS PAYMENT. The contractor's compensation shall be paid as set forth in the contract. 8.3
PROGRESS PAYMENT. A monthly payment made by the County to the Contractor after submission of an Application for Progress Payment by Contractor and subsequent issuance of a Certificate for Payment by the County.
PROGRESS PAYMENT. Grantee may opt to receive a portion of the Grant after starting but prior to completing work on the Project (“Progress Payment”). Grantee shall provide GOCO with a progress report detailing expenditures and progress made to date (“Progress Report”). The Progress Report must be submitted using GOCO’s Progress Report form (available at xxx.xxxx.xxx or by contacting GOCO). GOCO may, in its discretion, request additional documentation to support making a Progress Payment. A Progress Payment shall not exceed 50% of the Grant or the maximum percentage of funds GOCO can expend for the project to date based on the program’s matching requirements, whichever is less. A Progress Payment shall be considered a loan until the Project is complete and Final Payment (as defined below) has been made.
PROGRESS PAYMENT. Delete in its entirety and replace with: The Owner shall make payments to the Contractor on account as provided in Article A-5 of the Agreement – PAYMENT 30 days after the date of a certificate for payment issued by the Consultant.
PROGRESS PAYMENT. For work reimbursed on an hourly basis, the Consultant shall indicate for each employee, his or her name, job title, the number of hours worked, rate of pay for each employee, a computation of amounts due for each employee, and the total amount due for each project task. Consultant shall verify all statements submitted for payment in compliance with Minnesota Statutes Sections 471.38 and 471.391. For reimbursable expenses, if provided for in Exhibit A, the Consultant shall provide an itemized listing and such documentation as reasonably required by the City. Each invoice shall contain the City’s project number and a progress summary showing the original (or amended) amount of the contract, current billing, past payments and unexpended balance of the contract.