Common use of No Additional Compensation for Early Completion Clause in Contracts

No Additional Compensation for Early Completion. Nothing contained in the Contract Documents creates any contractual right, express or implied, on the part of XXXX to early completion of the Project. Under no circumstances shall Owner owe additional compensation to XXXX for XXXX’x inability to achieve completion of the Project before the expiration of the Contract Time, whether or not such inability is caused by the acts or omissions of Owner or any other party for which Owner is responsible, regardless of any approval by Owner of the Accepted Construction Schedule.

Appears in 2 contracts

Samples: Risk Construction Agreement, Construction Manager at Risk Construction Contract

AutoNDA by SimpleDocs

No Additional Compensation for Early Completion. Nothing contained in the Contract Documents creates any contractual right, express or implied, on the part of XXXX to early C014393 completion of the Project. Under no circumstances shall Owner owe additional compensation to XXXX for XXXX’x inability to achieve completion of the Project before the expiration of the Contract Time, whether or not such inability is caused by the acts or omissions of Owner or any other party for which Owner is responsible, regardless of any approval by Owner of the Accepted Construction Schedule.

Appears in 1 contract

Samples: Construction Manager at Risk Construction Contract

No Additional Compensation for Early Completion. Nothing contained in the Contract Documents creates any contractual right, express or implied, on the part of XXXX to early C014392 52 of 123 completion of the Project. Under no circumstances shall Owner owe additional compensation to XXXX for XXXX’x inability to achieve completion of the Project before the expiration of the Contract Time, whether or not such inability is caused by the acts or omissions of Owner or any other party for which Owner is responsible, regardless of any approval by Owner of the Accepted Construction Schedule.

Appears in 1 contract

Samples: Construction Manager at Risk Construction Contract

AutoNDA by SimpleDocs

No Additional Compensation for Early Completion. Nothing contained in the Contract Documents creates any contractual right, express or implied, on the part of XXXX to early completion of the Project. Under no circumstances shall Owner owe additional compensation to XXXX for XXXX’x inability to achieve completion of the Project before the expiration of the Contract Time, whether or not such inability is caused by the acts or omissions of Owner or any other party for which Owner is responsible, regardless of any approval by Owner of the Accepted Construction Project Schedule.

Appears in 1 contract

Samples: Model Contract