Common use of No Damage for Delay Clause in Contracts

No Damage for Delay. No payment, compensation or adjustment of any kind, other than an approved extension of time, shall be made to the Engineer for damages because of hindrances or delays from any cause in the progress of the work, whether such hindrances or delays be avoidable or unavoidable. The Engineer agrees that it will make no claim for compensation or damages for any such delays and will accept as full satisfaction for such delays the extensions of time.

Appears in 5 contracts

Samples: Contract for Engineering Services, Contract for Engineering/Consulting Services, Contract for Engineering Services

AutoNDA by SimpleDocs

No Damage for Delay. No payment, compensation or adjustment of any kind, kind other than an approved extension of time, time shall be made to the Engineer for damages because of hindrances or delays from any cause in the progress of the work, whether such hindrances or delays be avoidable or unavoidable. The Engineer agrees that it will make no claim for compensation or damages for any such delays and will accept as full satisfaction for such delays the extensions of time.

Appears in 1 contract

Samples: Engineering and Testing Services Agreement

AutoNDA by SimpleDocs

No Damage for Delay. No payment, compensation or adjustment of any kind, kind (other than an approved extension of time, ) shall be made to the Engineer [Architect or Engineer] for damages because of hindrances or delays from any cause in the progress of the work, whether such hindrances or delays be avoidable or unavoidable. The Engineer [Architect or Engineer] agrees that it will make no claim for compensation or damages for any such delays and will accept as full satisfaction for such delays the extensions of time.

Appears in 1 contract

Samples: Contract for Architectural or Engineering Services

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!