Common use of No Damage for Delay Clause in Contracts

No Damage for Delay. Contractor agrees to perform the Work and to require the subcontractors to perform the Work in a timely and proper method so as to meet the dates reflected on the progress schedule. In the event that the Contractor is delayed in the performance of the Work through no fault of the Contractor or its subcontractors, and for causes set forth in Section 3.03(a), and defined therein as Excusable Delay, then the Contractor may seek a time extension in accordance with the provisions of Section 3.03(b). Contractor agrees that such time extension is its sole and exclusive remedy for any damages regardless of the cause of such delays. Contractors also agrees that the Owner shall not be liable for any other monetary damages sustained by Contractor for acceleration, disruption, inefficiencies, suspension or resequencing of the Work or any other damages related to the progress schedule regardless of the cause of such damages. The Owner shall not be liable for consequential damages of any nature for any reason at any time.

Appears in 3 contracts

Samples: Lump Sum Construction Contract, Lump Sum Construction Contract, Lump Sum Construction Contract

AutoNDA by SimpleDocs

No Damage for Delay. Contractor XXXX agrees to perform the Work work and to require the subcontractors to perform the Work in a timely and proper method so as to meet the dates reflected on the progress schedule. In the event that the Contractor XXXX is delayed in the performance of the Work through no fault of the Contractor XXXX or its subcontractors, and for causes set forth in Section 3.03(a5.03(a), and defined therein as Excusable Delay, then the Contractor XXXX may seek a time extension in accordance with the provisions of Section 3.03(b5.03(b). Contractor XXXX agrees that such time extension is its sole and exclusive remedy for any damages regardless of the cause of such delays. Contractors . XXXX also agrees that the Owner shall not be liable for any other monetary damages sustained by Contractor XXXX for acceleration, disruption, inefficiencies, suspension or resequencing of the Work or any other damages related to the progress schedule regardless of the cause of such damages. The Owner shall not be liable for consequential damages of any nature for any reason at any time. The Project owns the float.

Appears in 1 contract

Samples: Construction Management Agreement

No Damage for Delay. Contractor agrees to perform the Work and to require the subcontractors to perform the Work in a timely and proper method so as to meet the dates reflected on the progress schedule. In the event that the Contractor is delayed in the performance of the Work through no fault of the Contractor or its subcontractors, and for causes set forth in Section 3.03(a), and defined therein as Excusable Delay, then the Contractor may seek a time extension in accordance with the provisions of Section 3.03(b). Contractor agrees that such time extension is its sole and exclusive remedy for any damages regardless of the cause of such delays. Contractors Contractor also agrees that the Owner shall not be liable for any other monetary damages sustained by Contractor or its subcontractors for acceleration, disruption, inefficiencies, suspension or resequencing of the Work or any other damages related to the progress schedule regardless of the cause of such damages. The Owner shall not be liable for consequential damages of any nature for any reason at any time.

Appears in 1 contract

Samples: Construction Contract

AutoNDA by SimpleDocs

No Damage for Delay. Contractor agrees to perform the Work and to require the subcontractors to perform the Work in a timely and proper method so as to meet the dates reflected on the progress schedule. In the event that the Contractor is delayed in the performance of the Work through no fault of the Contractor or its subcontractors, and for causes set forth in Section 3.03(a), and defined therein as Excusable Delay, then the Contractor may seek a time extension in accordance with the provisions of Section 3.03(b). Contractor agrees that such time extension is its sole and exclusive remedy for any damages regardless of the cause of such delays. Contractors also agrees that the Owner shall not be liable for any other monetary damages sustained by Contractor or its subcontractors for acceleration, disruption, inefficiencies, suspension or resequencing of the Work or any other damages related to the progress schedule regardless of the cause of such damages. The Owner shall not be liable for consequential damages of any nature for any reason at any time.

Appears in 1 contract

Samples: Construction Contract

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!