Non Associated Natural Gas (NANG. 21.5.1 In the event of a Discovery of NANG in the Contract Area, the Contractor shall promptly report such Discovery to the Management Committee and the Government and the provisions of Articles 10.1 and 10.2 shall apply. The remaining provisions of Article 10 would apply to the Discovery and development of NANG only insofar as they are not inconsistent with the provisions of this Article. Notwithstanding the provisions of Article 3, the Contractor shall be entitled to retain the Discovery Area subject to the provisions of this Article 21. 21.5.2 If, pursuant to Article 10.1, the Contractor gives notification that the Discovery is of potential commercial interest, the Contractor shall submit to the Management Committee, within one (1) year from the date of notification of the above said Discovery, the proposed Appraisal Programme, including a Work Programme and Budget to carry out an adequate and effective appraisal of such Discovery, to determine (i) without delay, whether such Discovery is a Commercial Discovery and (ii) with reasonable precision, the boundaries of the area to be delineated as the Development Area. Such proposed Appraisal Programme shall be supported by all relevant data such as Well data, Contractor’s best estimate of reserve range and production potential, and shall indicate the date of commencement of the proposed Appraisal Programme. 21.5.3 The proposed Appraisal Programme together with the Work Programme and Budget referred to in Article 21.5.2 shall be reviewed by the Management Committee within sixty (60) days of its submission by the Contractor. The Management Committee shall offer its comments within the said period. The said Appraisal Programme together with the Work Programme and Budget submitted by the Contractor as revised or modified or amended in light of the Management Committee review and advice, shall be adopted as the Appraisal Programme and the Contractor shall promptly proceed with implementation of the said Programme. 21.5.4 If on the basis of the results of the Appraisal Programme, the Contractor is of the opinion that NANG has been discovered in commercial quantities, it shall submit to the Management Committee as soon as practicable but not later than three (3) years from the date of notification of the aforementioned Discovery, a proposal for the declaration of the Discovery as a Commercial Discovery. Such proposal shall take into account the Government’s policies on Gas utilization and propose alternative options, if any for use or consumption of the NANG and be accompanied by a report on the Discovery supported by, inter alia, technical and economic data, evaluations, interpretations and analyses of such data and feasibility studies relating to the Discovery prepared by or on behalf of the Contractor, and other relevant information. If no proposal is submitted to the Management Committee by the Contractor within three (3) years from the said Discovery, the Contractor shall relinquish its rights to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area. 21.5.5 Where the Contractor has submitted a proposal for the declaration of a Discovery as a Commercial Discovery, the Management Committee shall consider the proposal of the Contractor with reference to commercial utilization or commercial development of the NANG in the domestic market or elsewhere and in the context of Government’s policy on Gas utilization and the chain of activities required to bring the NANG from the Delivery Point to potential consumers in the domestic market or elsewhere. The Management Committee may, within eighty five (85) days of the submission of the said proposal, request the Contractor to submit any additional information on the Discovery, the anticipated markets or any other related matter, that may reasonably be required to facilitate a review. The Contractor shall submit the required information within thirty (30) days of the request by the Management Committee. The Management Committee will advise the Contractor of its review within one hundred and thirty five (135) days from the submission of proposal or within fifty five (55) days from the receipt of additional information, as the case may be, on the proposal made by the Contractor to declare the Discovery as a Commercial Discovery. 21.5.6 If the Contractor declares the Discovery a Commercial Discovery after taking into account the advice of the Management Committee as referred to in the Article 21.5.5, the Contractor shall, within one (1) year of the declaration of the Discovery as a Commercial Discovery, submit a development plan for the development of the Discovery to the Management Committee for approval. Such plan shall be supported by all relevant information including, inter alia, the information required in Article 10.7. 21.5.7 Unless otherwise agreed by the Management Committee, it shall consider the proposed development plan and give their approval within one hundred and sixty five (165) days of submission thereof or eighty five (85) days from the receipt of the clarifications/additional information from the Contractor. Any clarification/additional information required by the Management Committee shall be asked for within eighty five (85) days of receipt of the proposal from the Contractor. The Contractor shall provide such additional information within thirty (30) days from the receipt of request by the Management Committee. If the Management Committee fails to convey its decision within one hundred and sixty five (165) days from the submission of the development plan or eighty five (85) days from the receipt of the clarifications/additional information, whichever is later, the Contractor may submit the development plan for the approval of the Government. Also, where, the Management Committee rejects the development plan of the Contractor, the Contractor can submit the development plan for the approval of the Government. 21.5.8 Where the development plan is submitted to the Government for approval pursuant to Article 21.5.7, the Government shall convey its decision within one hundred and fifteen (115) days from the date of receipt of the proposal from the Contractor. Government, where it considers necessary, may ask clarifications/additional information from the Contractor within eighty five (85) days and shall convey its decision within fifty five (55) days from the date of receipt of such clarifications/additional information. 21.5.9 If the Government has failed to approve or disapproves the Contractor’s proposed development plan, within one hundred and fifteen (115) days from receipt or within fifty five (55) days from the receipt of clarifications/ information from the Contractor as mentioned in the Article 21.5.8, the Government shall advise the Contractor, in writing, of the reasons for such failure or disapproval and the Government and the Contractor shall meet to discuss the said development plan and the reasons for the said failure to approve or disapproval, and use their best efforts to agree on appropriate modifications thereto to meet the Government’s concerns or objections. Thereafter, the Contractor shall have the right to resubmit, within eighty five (85) days of communication from the Government, the proposed development plan duly amended to meet the Government’s concerns. Such right of resubmission of the proposed development plan shall be exercisable by the Contractor only once. The Government will respond to the re-submitted plan within one hundred and fifteen (115) days. If no such plan is submitted to the Government within the above specified period, the Contractor shall relinquish its right to develop such Gas Discovery and such Discovery shall be excluded from the Contract Area. 21.5.10 In the event that the Management Committee or Government, as may be the case, approves the Contractor’s development plan for the development of such Commercial Discovery, with such modifications and amendments as the Management Committee or Government, as may be the case, may approve, the said Gas Discovery shall be promptly developed by the Contractor in accordance with the approved plan which shall be the Development Plan. 21.5.11 The Contractor will have a two (2) years period, from the date of approval of the Development Plan by the Management Committee or Government, to tie-up the market(s) for sale of Non-associated Natural Gas. 21.5.12 In the event the Contractor does not commence development of such Discovery within ten (10) years from the date of the first Discovery Well, the Contractor shall relinquish its right to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
Appears in 4 contracts
Samples: Production Sharing Contract (Geoglobal Resources Inc), Production Sharing Contract (Geoglobal Resources Inc), Production Sharing Contract (Geoglobal Resources Inc)
Non Associated Natural Gas (NANG. 21.5.1 In the event of a Discovery of NANG in the Contract Area, the Contractor shall promptly report such Discovery to the Management Committee and the Government and the provisions of Articles 10.1 and 10.2 shall apply. The remaining provisions of Article 10 would apply to the Discovery and development of NANG only insofar as they are not inconsistent with the provisions of this Article. Notwithstanding the provisions of Article 3, the Contractor shall be entitled to retain the Discovery Area subject to the provisions of this Article 21.
21.5.2 If, pursuant to Article 10.1, the Contractor gives notification that the Discovery is of potential commercial interest, the Contractor shall submit to the Management Committee, within one (1) year from the date of notification of the above said Discovery, the proposed Appraisal Programme, including a Work Programme and Budget to carry out an adequate and effective appraisal of such Discovery, to determine (i) without delay, whether such Discovery is a Commercial Discovery and (ii) with reasonable precision, the boundaries of the area to be delineated as the Development Area. Such proposed Appraisal Programme shall be supported by all relevant data such as Well data, Contractor’s 's best estimate of reserve range and production potential, and shall indicate the date of commencement of the proposed Appraisal Programme.
21.5.3 The proposed Appraisal Programme together with the Work Programme and Budget referred to in Article 21.5.2 shall be reviewed by the Management Committee within sixty (60) days of its submission by the Contractor. The Management Committee shall offer its comments within the said period. The said Appraisal Programme together with the Work Programme and Budget submitted by the Contractor as revised or modified or amended in light of the Management Committee review and advice, shall be adopted as the Appraisal Programme and the Contractor shall promptly proceed with implementation of the said Programme.
21.5.4 If on the basis of the results of the Appraisal Programme, the Contractor is of the opinion that NANG has been discovered in commercial quantities, it shall submit to the Management Committee as soon as practicable but not later than three (3) years from the date of notification of the aforementioned Discovery, a proposal for the declaration of the Discovery as a Commercial Discovery. Such proposal shall take into account the Government’s policies on Gas utilization and propose alternative options, if any for use or consumption of the NANG and be accompanied by a report on the Discovery supported by, inter alia, technical and economic data, evaluations, interpretations and analyses of such data and feasibility studies relating to the Discovery prepared by or on behalf of the Contractor, and other relevant information. If no proposal is submitted to the Management Committee by the Contractor within three (3) years from the said Discovery, the Contractor shall relinquish its rights to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
21.5.5 Where the Contractor has submitted a proposal for the declaration of a Discovery as a Commercial Discovery, the Management Committee shall consider the proposal of the Contractor with reference to commercial utilization or commercial development of the NANG in the domestic market or elsewhere and in the context of Government’s policy on Gas utilization and the chain of activities required to bring the NANG from the Delivery Point to potential consumers in the domestic market or elsewhere. The Management Committee may, within eighty five (85) days of the submission of the said proposal, request the Contractor to submit any additional information on the Discovery, the anticipated markets or any other related matter, that may reasonably be required to facilitate a review. The Contractor shall submit the required information within thirty (30) days of the request by the Management Committee. The Management Committee will advise the Contractor of its review within one hundred and thirty five (135) days from the submission of proposal or within fifty five (55) days from the receipt of additional information, as the case may be, on the proposal made by the Contractor to declare the Discovery as a Commercial Discovery.
21.5.6 If the Contractor declares the Discovery a Commercial Discovery after taking into account the advice of the Management Committee as referred to in the Article 21.5.5, the Contractor shall, within one (1) year of the declaration of the Discovery as a Commercial Discovery, submit a development plan for the development of the Discovery to the Management Committee for approval. Such plan shall be supported by all relevant information including, inter alia, the information required in Article 10.7.
21.5.7 Unless otherwise agreed by the Management Committee, it shall consider the proposed development plan and give their approval within one hundred and sixty five (165) days of submission thereof or eighty five (85) days from the receipt of the clarifications/additional information from the Contractor. Any clarification/additional information required by the Management Committee shall be asked for within eighty five (85) days of receipt of the proposal from the Contractor. The Contractor shall provide such additional information within thirty (30) days from the receipt of request by the Management Committee. If the Management Committee fails to convey its decision within one hundred and sixty five (165) days from the submission of the development plan or eighty five (85) days from the receipt of the clarifications/additional information, whichever is later, the Contractor may submit the development plan for the approval of the Government. Also, where, the Management Committee rejects the development plan of the Contractor, the Contractor can submit the development plan for the approval of the Government.
21.5.8 Where the development plan is submitted to the Government for approval pursuant to Article 21.5.7, the Government shall convey its decision within one hundred and fifteen (115) days from the date of receipt of the proposal from the Contractor. Government, where it considers necessary, may ask clarifications/additional information from the Contractor within eighty five (85) days and shall convey its decision within fifty five (55) days from the date of receipt of such clarifications/additional information.
21.5.9 If the Government has failed to approve or disapproves the Contractor’s proposed development plan, within one hundred and fifteen (115) days from receipt or within fifty five (55) days from the receipt of clarifications/ information from the Contractor as mentioned in the Article 21.5.8, the Government shall advise the Contractor, in writing, of the reasons for such failure or disapproval and the Government and the Contractor shall meet to discuss the said development plan and the reasons for the said failure to approve or disapproval, and use their best efforts to agree on appropriate modifications thereto to meet the Government’s concerns or objections. Thereafter, the Contractor shall have the right to resubmit, within eighty five (85) days of communication from the Government, the proposed development plan duly amended to meet the Government’s concerns. Such right of resubmission of the proposed development plan shall be exercisable by the Contractor only once. The Government will respond to the re-submitted plan within one hundred and fifteen (115) days. If no such plan is submitted to the Government within the above specified period, the Contractor shall relinquish its right to develop such Gas Discovery and such Discovery shall be excluded from the Contract Area.
21.5.10 In the event that the Management Committee or Government, as may be the case, approves the Contractor’s development plan for the development of such Commercial Discovery, with such modifications and amendments as the Management Committee or Government, as may be the case, may approve, the said Gas Discovery shall be promptly developed by the Contractor in accordance with the approved plan which shall be the Development Plan.
21.5.11 The Contractor will have a two (2) years period, from the date of approval of the Development Plan by the Management Committee or Government, to tie-up the market(s) for sale of Non-associated Natural Gas.
21.5.12 In the event the Contractor does not commence development of such Discovery within ten (10) years from the date of the first Discovery Well, the Contractor shall relinquish its right to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
Appears in 3 contracts
Samples: Production Sharing Contract, Production Sharing Contract (Geoglobal Resources Inc.), Production Sharing Contract (Geoglobal Resources Inc.)
Non Associated Natural Gas (NANG. 21.5.1 In the event of a Discovery of NANG in the Contract Area, the Contractor shall promptly report such Discovery to the Management Committee and the Government and the provisions of Articles 10.1 and 10.2 shall apply. The remaining provisions of Article 10 would apply to the Discovery and development of NANG only insofar as they are not inconsistent with the provisions of this Article. Notwithstanding the provisions of Article 3, the Contractor shall be entitled to retain the Discovery Area subject to the provisions of this Article 21.
21.5.2 If, pursuant to Article 10.1, the Contractor gives notification that the Discovery is of potential commercial interest, the Contractor shall submit to the Management Committee, within one (1) year from the date of notification of the above said Discovery, the proposed Appraisal Programme, including a Work Programme and Budget to carry out an adequate and effective appraisal of such Discovery, to determine (i) without delay, whether such Discovery is a Commercial Discovery and (ii) with reasonable precision, the boundaries of the area to be delineated as the Development Area. Such proposed Appraisal Programme shall be supported by all relevant data such as Well data, Contractor’s best estimate of reserve range and production potential, and shall indicate the date of commencement of the proposed Appraisal Programme.
21.5.3 The proposed Appraisal Programme together with the Work Programme and Budget referred to in Article 21.5.2 shall be reviewed by the Management Committee within sixty (60) days of its submission by the Contractor. The Management Committee shall offer its comments within the said period. The said Appraisal Programme together with the Work Programme and Budget submitted by the Contractor as revised or modified or amended in light of the Management Committee review and advice, shall be adopted as the Appraisal Programme and the Contractor shall promptly proceed with implementation of the said Programme.
21.5.4 If on the basis of the results of the Appraisal Programme, the Contractor is of the opinion that NANG XXXX has been discovered in commercial quantities, it shall submit to the Management Committee as soon as practicable but not later than three (3) years from the date of notification of the aforementioned Discovery, a proposal for the declaration of the Discovery as a Commercial Discovery. Such proposal shall take into account the Government’s policies on Gas utilization and propose alternative options, if any for use or consumption of the NANG and be accompanied by a report on the Discovery supported by, inter alia, technical and economic data, evaluations, interpretations and analyses of such data and feasibility studies relating to the Discovery prepared by or on behalf of the Contractor, and other relevant information. If no proposal is submitted to the Management Committee by the Contractor within three (3) years from the said Discovery, the Contractor shall relinquish its rights to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
21.5.5 Where the Contractor has submitted a proposal for the declaration of a Discovery as a Commercial Discovery, the Management Committee shall consider the proposal of the Contractor with reference to commercial utilization or commercial development of the NANG in the domestic market or elsewhere and in the context of Government’s policy on Gas utilization and the chain of activities required to bring the NANG from the Delivery Point to potential consumers in the domestic market or elsewhere. The Management Committee may, within eighty five (85) days of the submission of the said proposal, request the Contractor to submit any additional information on the Discovery, the anticipated markets or any other related matter, that may reasonably be required to facilitate a review. The Contractor shall submit the required information within thirty (30) days of the request by the Management Committee. The Management Committee will advise the Contractor of its review within one hundred and thirty five (135) days from the submission of proposal or within fifty five (55) days from the receipt of additional information, as the case may be, on the proposal made by the Contractor to declare the Discovery as a Commercial Discovery.
21.5.6 If the Contractor declares the Discovery a Commercial Discovery after taking into account the advice of the Management Committee as referred to in the Article 21.5.5, the Contractor shall, within one (1) year of the declaration of the Discovery as a Commercial Discovery, submit a development plan for the development of the Discovery to the Management Committee for approval. Such plan shall be supported by all relevant information including, inter alia, the information required in Article 10.7.
21.5.7 Unless otherwise agreed by the Management Committee, it shall consider the proposed development plan and give their approval within one hundred and sixty five (165) days of submission thereof or eighty five (85) days from the receipt of the clarifications/clarifications/ additional information from the Contractor. Any clarification/additional information required by the Management Committee shall be asked for within eighty five (85) days of receipt of the proposal from the Contractor. The Contractor shall provide such additional information within thirty (30) days from the receipt of request by the Management Committee. If the Management Committee fails to convey its decision within one hundred and sixty five (165) days from the submission of the development plan or eighty five (85) days from the receipt of the clarifications/additional information, whichever is later, the Contractor may submit the development plan for the approval of the Government. Also, where, the Management Committee rejects the development plan of the Contractor, the Contractor can submit the development plan for the approval of the Government.
21.5.8 Where the development plan is submitted to the Government for approval pursuant to Article 21.5.7, the Government shall convey its decision within one hundred and fifteen (115) days from the date of receipt of the proposal from the Contractor. Government, where it considers necessary, may ask clarifications/additional information from the Contractor within eighty five (85) days and shall convey its decision within fifty five (55) days from the date of receipt of such clarifications/additional information.
21.5.9 If the Government has failed to approve or disapproves the Contractor’s proposed development plan, within one hundred and fifteen (115) days from receipt or within fifty five (55) days from the receipt of clarifications/ information from the Contractor as mentioned in the Article 21.5.8, the Government shall advise the Contractor, in writing, of the reasons for such failure or disapproval and the Government and the Contractor shall meet to discuss the said development plan and the reasons for the said failure to approve or disapproval, and use their best efforts to agree on appropriate modifications thereto to meet the Government’s concerns or objections. Thereafter, the Contractor shall have the right to resubmit, within eighty five (85) days of communication from the Government, the proposed development plan duly amended to meet the Government’s concerns. Such right of resubmission of the proposed development plan shall be exercisable by the Contractor only once. The Government will respond to the re-submitted plan within one hundred and fifteen (115) days. If no such plan is submitted to the Government within the above specified period, the Contractor shall relinquish its right to develop such Gas Discovery and such Discovery shall be excluded from the Contract Area.
21.5.10 In the event that the Management Committee or Government, as may be the case, approves the Contractor’s development plan for the development of such Commercial Discovery, with such modifications and amendments as the Management Committee or Government, as may be the case, may approve, the said Gas Discovery shall be promptly developed by the Contractor in accordance with the approved plan which shall be the Development Plan.
21.5.11 The Contractor will have a two (2) years period, from the date of approval of the Development Plan by the Management Committee or Government, to tie-up the market(s) for sale of Non-associated Natural Gas.
21.5.12 In the event the Contractor does not commence development of such Discovery within ten (10) years from the date of the first Discovery Well, the Contractor shall relinquish its right to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
Appears in 2 contracts
Samples: Production Sharing Contract, Production Sharing Contract
Non Associated Natural Gas (NANG. 21.5.1 In the event of a Discovery of NANG in the Contract Area, the Contractor shall promptly report such Discovery to the Management Committee and the Government and the provisions of Articles 10.1 and 10.2 shall apply. The remaining provisions of Article 10 would apply to the Discovery and development of NANG only insofar as they are not inconsistent with the provisions of this Article. Notwithstanding the provisions of Article 3, the Contractor shall be entitled to retain the Discovery Area subject to the provisions of this Article 21.
21.5.2 If, pursuant to Article 10.1, the Contractor gives notification that the Discovery is of potential commercial interest, the Contractor shall submit to the Management Committee, within one (1) year from the date of notification of the above said Discovery, the proposed Appraisal Programme, including a Work Programme and Budget to carry out an adequate and effective appraisal of such Discovery, to determine (i) without delay, whether such Discovery is a Commercial Discovery and (ii) with reasonable precision, the boundaries of the area to be delineated as the Development Area. Such proposed Appraisal Programme shall be supported by all relevant data such as Well data, Contractor’s 's best estimate of reserve range and production potential, and shall indicate the date of commencement of the proposed Appraisal Programme.
21.5.3 The proposed Appraisal Programme together with the Work Programme and Budget referred to in Article 21.5.2 shall be reviewed by the Management Committee within sixty (60) days of its submission by the Contractor. The Management Committee shall offer its comments within the said period. The said Appraisal Programme together with the Work Programme and Budget submitted by the Contractor as revised or modified or amended in light of the Management Committee review and advice, shall be adopted as the Appraisal Programme and the Contractor shall promptly proceed with implementation of the said Programme.
21.5.4 If on the basis of the results of the Appraisal Programme, the Contractor is of the opinion that NANG XXXX has been discovered in commercial quantities, it shall submit to the Management Committee as soon as practicable but not later than three (3) years from the date of notification of the aforementioned Discovery, a proposal for the declaration of the Discovery as a Commercial Discovery. Such proposal shall take into account the Government’s policies on Gas utilization and propose alternative options, if any for use or consumption of the NANG and be accompanied by a report on the Discovery supported by, inter alia, technical and economic data, evaluations, interpretations and analyses of such data and feasibility studies relating to the Discovery prepared by or on behalf of the Contractor, and other relevant information. If no proposal is submitted to the Management Committee by the Contractor within three (3) years from the said Discovery, the Contractor shall relinquish its rights to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
21.5.5 Where the Contractor has submitted a proposal for the declaration of a Discovery as a Commercial Discovery, the Management Committee shall consider the proposal of the Contractor with reference to commercial utilization or commercial development of the NANG in the domestic market or elsewhere and in the context of Government’s policy on Gas utilization and the chain of activities required to bring the NANG from the Delivery Point to potential consumers in the domestic market or elsewhere. The Management Committee may, within eighty five (85) days of the submission of the said proposal, request the Contractor to submit any additional information on the Discovery, the anticipated markets or any other related matter, that may reasonably be required to facilitate a review. The Contractor shall submit the required information within thirty (30) days of the request by the Management Committee. The Management Committee will advise the Contractor of its review within one hundred and thirty five (135) days from the submission of proposal or within fifty five (55) days from the receipt of additional information, as the case may be, on the proposal made by the Contractor to declare the Discovery as a Commercial Discovery.
21.5.6 If the Contractor declares the Discovery a Commercial Discovery after taking into account the advice of the Management Committee as referred to in the Article 21.5.5, the Contractor shall, within one (1) year of the declaration of the Discovery as a Commercial Discovery, submit a development plan for the development of the Discovery to the Management Committee for approval. Such plan shall be supported by all relevant information including, inter alia, the information required in Article 10.7.
21.5.7 Unless otherwise agreed by the Management Committee, it shall consider the proposed development plan and give their approval within one hundred and sixty five (165) days of submission thereof or eighty five (85) days from the receipt of the clarifications/additional information from the Contractor. Any clarification/additional information required by the Management Committee shall be asked for within eighty five (85) days of receipt of the proposal from the Contractor. The Contractor shall provide such additional information within thirty (30) days from the receipt of request by the Management Committee. If the Management Committee fails to convey its decision within one hundred and sixty five (165) days from the submission of the development plan or eighty five (85) days from the receipt of the clarifications/additional information, whichever is later, the Contractor may submit the development plan for the approval of the Government. Also, where, the Management Committee rejects the development plan of the Contractor, the Contractor can submit the development plan for the approval of the Government.
21.5.8 Where the development plan is submitted to the Government for approval pursuant to Article 21.5.7, the Government shall convey its decision within one hundred and fifteen (115) days from the date of receipt of the proposal from the Contractor. Government, where it considers necessary, may ask clarifications/additional information from the Contractor within eighty five (85) days and shall convey its decision within fifty five (55) days from the date of receipt of such clarifications/additional information.
21.5.9 If the Government has failed to approve or disapproves the Contractor’s proposed development plan, within one hundred and fifteen (115) days from receipt or within fifty five (55) days from the receipt of clarifications/ information from the Contractor as mentioned in the Article 21.5.8, the Government shall advise the Contractor, in writing, of the reasons for such failure or disapproval and the Government and the Contractor shall meet to discuss the said development plan and the reasons for the said failure to approve or disapproval, and use their best efforts to agree on appropriate modifications thereto to meet the Government’s concerns or objections. Thereafter, the Contractor shall have the right to resubmit, within eighty five (85) days of communication from the Government, the proposed development plan duly amended to meet the Government’s concerns. Such right of resubmission of the proposed development plan shall be exercisable by the Contractor only once. The Government will respond to the re-submitted plan within one hundred and fifteen (115) days. If no such plan is submitted to the Government within the above specified period, the Contractor shall relinquish its right to develop such Gas Discovery and such Discovery shall be excluded from the Contract Area.
21.5.10 In the event that the Management Committee or Government, as may be the case, approves the Contractor’s development plan for the development of such Commercial Discovery, with such modifications and amendments as the Management Committee or Government, as may be the case, may approve, the said Gas Discovery shall be promptly developed by the Contractor in accordance with the approved plan which shall be the Development Plan.
21.5.11 The Contractor will have a two (2) years period, from the date of approval of the Development Plan by the Management Committee or Government, to tie-up the market(s) for sale of Non-associated Natural Gas.
21.5.12 In the event the Contractor does not commence development of such Discovery within ten (10) years from the date of the first Discovery Well, the Contractor shall relinquish its right to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
Appears in 2 contracts
Samples: Production Sharing Contract, Production Sharing Contract
Non Associated Natural Gas (NANG. 21.5.1 In the event of a Discovery of NANG in the Contract Area, the Contractor shall promptly report such Discovery to the Management Committee and the Government and the provisions of Articles 10.1 and 10.2 shall apply. The remaining provisions of Article 10 would apply to the Discovery and development of NANG only insofar as they are not inconsistent with the provisions of this Article. Notwithstanding the provisions of Article 3, the Contractor shall be entitled to retain the Discovery Area subject to the provisions of this Article 21.
21.5.2 If, pursuant to Article 10.1, the Contractor gives notification that the Discovery is of potential commercial interest, the Contractor shall submit to the Management Committee, within one (1) year from the date of notification of the above said Discovery, the proposed Appraisal Programme, including a Work Programme and Budget to carry out an adequate and effective appraisal of such Discovery, to determine (i) without delay, whether such Discovery is a Commercial Discovery and (ii) with reasonable precision, the boundaries of the area to be delineated as the Development Area. Such proposed Appraisal Programme shall be supported by all relevant data such as Well data, Contractor’s 's best estimate of reserve range and production potential, and shall indicate the date of commencement of the proposed Appraisal Programme.
21.5.3 The proposed Appraisal Programme together with the Work Programme and Budget referred to in Article 21.5.2 shall be reviewed by the Management Committee within sixty (60) days of its submission by the Contractor. The Management Committee shall offer its comments within the said period. The said Appraisal Programme together with the Work Programme and Budget submitted by the Contractor as revised or modified or amended in light of the Management Committee review and advice, shall be adopted as the Appraisal Programme and the Contractor shall promptly proceed with implementation of the said Programme.
21.5.4 If on the basis of the results of the Appraisal Programme, the Contractor is of the opinion that NANG has been discovered in commercial quantities, it shall submit to the Management Committee as soon as practicable but not later than three (3) years from the date of notification of the aforementioned Discovery, a proposal for the declaration of the Discovery as a Commercial Discovery. Such proposal shall take into account the Government’s policies on Gas utilization and propose alternative options, if any for use or consumption of the NANG and be accompanied by a report on the Discovery supported by, inter alia, technical and economic data, evaluations, interpretations and analyses of such data and feasibility studies relating to the Discovery prepared by or on behalf of the Contractor, and other relevant information. If no proposal is submitted to the Management Committee by the Contractor within three (3) years from the said Discovery, the Contractor shall relinquish its rights to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
21.5.5 Where the Contractor has submitted a proposal for the declaration of a Discovery as a Commercial Discovery, the Management Committee shall consider the proposal of the Contractor with reference to commercial utilization or commercial development of the NANG in the domestic market or elsewhere and in the context of Government’s policy on Gas utilization and the chain of activities required to bring the NANG from the Delivery Point to potential consumers in the domestic market or elsewhere. The Management Committee may, within eighty five (85) days of the submission of the said proposal, request the Contractor to submit any additional information on the Discovery, the anticipated markets or any other related matter, that may reasonably be required to facilitate a review. The Contractor shall submit the required information within thirty (30) days of the request by the Management Committee. The Management Committee will advise the Contractor of its review within one hundred and thirty five (135) days from the submission of proposal or within fifty five (55) days from the receipt of additional information, as the case may be, on the proposal made by the Contractor to declare the Discovery as a Commercial Discovery.
21.5.6 If the Contractor declares the Discovery a Commercial Discovery after taking into account the advice of the Management Committee as referred to in the Article 21.5.5, the Contractor shall, within one (1) year of the declaration of the Discovery as a Commercial Discovery, submit a development plan for the development of the Discovery to the Management Committee for approval. Such plan shall be supported by all relevant information including, inter alia, the information required in Article 10.7.
21.5.7 Unless otherwise agreed by the Management Committee, it shall consider the proposed development plan and give their approval within one hundred and sixty five (165) days of submission thereof or eighty five (85) days from the receipt of the clarifications/additional information from the Contractor. Any clarification/additional information required by the Management Committee shall be asked for within eighty five (85) days of receipt of the proposal from the Contractor. The Contractor shall provide such additional information within thirty (30) days from the receipt of request by the Management Committee. If the Management Committee fails to convey its decision within one hundred and sixty five (165) days from the submission of the development plan or eighty five (85) days from the receipt of the clarifications/additional information, whichever is later, the Contractor may submit the development plan for the approval of the Government. Also, where, the Management Committee rejects the development plan of the Contractor, the Contractor can submit the development plan for the approval of the Government.
21.5.8 Where the development plan is submitted to the Government for approval pursuant to Article 21.5.7, the Government shall convey its decision within one hundred and fifteen (115) days from the date of receipt of the proposal from the Contractor. Government, where it considers necessary, may ask clarifications/additional information from the Contractor within eighty five (85) days and shall convey its decision within fifty five (55) days from the date of receipt of such clarifications/additional information.
21.5.9 If the Government has failed to approve or disapproves the Contractor’s proposed development plan, within one hundred and fifteen (115) days from receipt or within fifty five (55) days from the receipt of clarifications/ information from the Contractor as mentioned in the Article 21.5.8, the Government shall advise the Contractor, in writing, of the reasons for such failure or disapproval and the Government and the Contractor shall meet to discuss the said development plan and the reasons for the said failure to approve or disapproval, and use their best efforts to agree on appropriate modifications thereto to meet the Government’s concerns or objections. Thereafter, the Contractor shall have the right to resubmit, within eighty five (85) days of communication from the Government, the proposed development plan duly amended to meet the Government’s concerns. Such right of resubmission of the proposed development plan shall be exercisable by the Contractor only once. The Government will respond to the re-submitted plan within one hundred and fifteen (115) days. If no such plan is submitted to the Government within the above specified period, the Contractor shall relinquish its right to develop such Gas Discovery and such Discovery shall be excluded from the Contract Area.
21.5.10 In the event that the Management Committee or Government, as may be the case, approves the Contractor’s development plan for the development of such Commercial Discovery, with such modifications and amendments as the Management Committee or Government, as may be the case, may approve, the said Gas Discovery shall be promptly developed by the Contractor in accordance with the approved plan which shall be the Development Plan.
21.5.11 The Contractor will have a two (2) years period, from the date of approval of the Development Plan by the Management Committee or Government, to tie-up the market(s) for sale of Non-associated Natural Gas.
21.5.12 In the event the Contractor does not commence development of such Discovery within ten (10) years from the date of the first Discovery Well, the Contractor shall relinquish its right to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
Appears in 2 contracts
Samples: Production Sharing Contract (Geoglobal Resources Inc.), Production Sharing Contract (Geoglobal Resources Inc.)
Non Associated Natural Gas (NANG. 21.5.1 a) In the event of a Discovery of NANG in the Contract Agreement Area, the Contractor shall promptly report such Discovery to the Management Advisory Committee and the Government PRDC and the provisions of Articles 10.1 Articles
28.1 and 10.2 28.2 shall apply. The remaining provisions of Article 10 28 would apply to the Discovery and development of NANG only insofar as they are not inconsistent with the provisions of this Article. Notwithstanding the provisions of Article 3, the Contractor shall be entitled to retain the Discovery Area subject to the provisions of this Article 2131.
21.5.2 b) If, pursuant to Article 10.128.1, the Contractor gives notification that the Discovery is of potential commercial interest, the Contractor shall submit to the Management CommitteeAdvisory Committee and the PRDC, within one hundred and eighty (1180) year days from the date of notification of the above said Discovery, the proposed Appraisal Programme, including a Work Programme and Budget to carry out an adequate and effective appraisal of such Discovery, to determine determine:
(i) without delay, whether such Discovery is a Commercial Discovery and Discovery; and
(ii) with reasonable precision, the boundaries of the area to be delineated as the Development Area. .
c) Such proposed Appraisal Programme shall be supported by all relevant data such as Well data, the Contractor’s best estimate of reserve range and production potential, and shall indicate the date of commencement of the proposed Appraisal Programme.
21.5.3 The proposed Appraisal Programme together with d) Up to six (6) months before the Work Programme and Budget referred to in Article 21.5.2 shall be reviewed by the Management Committee within sixty (60) days of its submission by the Contractor. The Management Committee shall offer its comments within the said period. The said Appraisal Programme together with the Work Programme and Budget submitted by the Contractor as revised or modified or amended in light end of the Management Committee review and advice, shall be adopted as the Appraisal Programme and the Contractor shall promptly proceed with implementation of the said Programme.
21.5.4 If on the basis of the results of the Appraisal Programme, the Contractor is of the opinion that NANG has been discovered in commercial quantities, it shall submit to the Management Committee as soon as practicable but not later than three (3) years from the date of notification of the aforementioned Discovery, a proposal for the declaration of the Discovery as a Commercial Discovery. Such proposal shall take into account the Government’s policies on Gas utilization and propose alternative options, if any for use or consumption of the NANG and be accompanied by a report on the Discovery supported by, inter alia, technical and economic data, evaluations, interpretations and analyses of such data and feasibility studies relating to the Discovery prepared by or on behalf of the Contractor, and other relevant information. If no proposal is submitted to the Management Committee by the Contractor within three (3) years from the said Discovery, the Contractor shall relinquish its rights to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
21.5.5 Where the Contractor has submitted a proposal for the declaration of a Discovery as a Commercial Discovery, the Management Committee shall consider the proposal of the Contractor with reference to commercial utilization or commercial development of the NANG in the domestic market or elsewhere and in the context of Government’s policy on Gas utilization and the chain of activities required to bring the NANG from the Delivery Point to potential consumers in the domestic market or elsewhere. The Management Committee may, within eighty five (85) days of the submission of the said proposal, request the Contractor to submit any additional information on the Discovery, the anticipated markets or any other related matter, that may reasonably be required to facilitate a review. The Contractor shall submit the required information within thirty (30) days of the request by the Management Committee. The Management Committee will advise the Contractor of its review within one hundred and thirty five (135) days from the submission of proposal or within fifty five (55) days from the receipt of additional information, as the case may be, on the proposal made by the Contractor to declare the Discovery as a Commercial Discovery.
21.5.6 If the Contractor declares the Discovery a Commercial Discovery after taking into account the advice of the Management Committee as referred to in the Article 21.5.5, the Contractor shall, within one (1) year of the declaration of the Discovery as a Commercial Discovery, submit a development plan for the development of the Discovery to the Management Committee for approval. Such plan shall be supported by all relevant information including, inter alia, the information required in Article 10.7.
21.5.7 Unless otherwise agreed by the Management Committee, it shall consider the proposed development plan and give their approval within one hundred and sixty five (165) days of submission thereof or eighty five (85) days from the receipt of the clarifications/additional information from the Contractor. Any clarification/additional information required by the Management Committee shall be asked for within eighty five (85) days of receipt of the proposal from the Contractor. The Contractor shall provide such additional information within thirty (30) days from the receipt of request by the Management Committee. If the Management Committee fails to convey its decision within one hundred and sixty five (165) days from the submission of the development plan or eighty five (85) days from the receipt of the clarifications/additional information, whichever is laterExploration Period, the Contractor may submit Appraisal Programmes for Discoveries encountered in its Agreement Area but not considered commercial at the development plan for the approval time of the Government. Also, where, the Management Committee rejects the development plan of the Contractor, the Contractor can submit the development plan for the approval of the Governmentdiscovery.
21.5.8 Where the development plan is submitted to the Government for approval e) If, pursuant to Article 21.5.728.1, the Government shall convey its decision within one hundred and fifteen (115) days from the date of receipt of the proposal from the Contractor. Government, where it considers necessary, may ask clarifications/additional information from the Contractor within eighty five (85) days and shall convey its decision within fifty five (55) days from the date of receipt of such clarifications/additional information.
21.5.9 If the Government has failed to approve or disapproves the Contractor’s proposed development plan, within one hundred and fifteen (115) days from receipt or within fifty five (55) days from the receipt of clarifications/ information from the Contractor as mentioned in the Article 21.5.8, the Government shall advise the Contractor, in writing, of the reasons for such failure or disapproval and the Government and the Contractor shall meet to discuss the said development plan and the reasons for the said failure to approve or disapproval, and use their best efforts to agree on appropriate modifications thereto to meet the Government’s concerns or objections. Thereafter, the Contractor shall have the right to resubmit, within eighty five (85) days of communication from the Government, the proposed development plan duly amended to meet the Government’s concerns. Such right of resubmission of the proposed development plan shall be exercisable by the Contractor only once. The Government will respond to the re-submitted plan within one hundred and fifteen (115) days. If no such plan is submitted to the Government within the above specified period, the Contractor shall relinquish its right to develop such Gas Discovery and such Discovery shall be excluded from the Contract Area.
21.5.10 In the event that the Management Committee or Government, as may be the case, approves the Contractor’s development plan for the development of such Commercial Discovery, with such modifications and amendments as the Management Committee or Government, as may be the case, may approve, the said Gas Discovery shall be promptly developed by the Contractor in accordance with the approved plan which shall be the Development Plan.
21.5.11 The Contractor will have a two (2) years period, from the date of approval of the Development Plan by the Management Committee or Government, to tie-up the market(s) for sale of Non-associated Natural Gas.
21.5.12 In the event the Contractor does not commence development notify the Advisory Committee and the PRDC that the Discovery is of potential commercial interest and the Advisory Committee and the PRDC are reasonably of the view that the Discovery merits appraisal the Contractor may be required to produce an Appraisal Programme with a Work Programme and Budget to carry out an adequate and effective appraisal of such Discovery within ten designed to achieve the objectives set out in sub-paragraphs (10i) years from the date and (ii) of the first Discovery Well, the Contractor shall relinquish its right to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Areaparagraph b).
Appears in 1 contract
Samples: Model Petroleum Resources Agreement
Non Associated Natural Gas (NANG. 21.5.1 In the event of a Discovery of NANG in the Contract Area, the Contractor shall promptly report such Discovery to the Management Committee and the Government and the provisions of Articles 10.1 and 10.2 shall apply. The remaining provisions of Article 10 would apply to the Discovery and development of NANG only insofar as they are not inconsistent with the provisions of this Article. Notwithstanding the provisions of Article 3, the Contractor shall be entitled to retain the Discovery Area subject to the provisions of this Article 21.
21.5.2 If, pursuant to Article 10.1, the Contractor gives notification that the Discovery is of potential commercial interest, the Contractor shall submit to the Management Committee, within one (1) year from the date of notification of the above said Discovery, the proposed Appraisal Programme, including a Work Programme and Budget to carry out an adequate and effective appraisal of such Discovery, to determine (i) without delay, whether such Discovery is a Commercial Discovery and (ii) with reasonable precision, the boundaries of the area to be delineated as the Development Area. Such proposed Appraisal Programme shall be supported by all relevant data such as Well data, Contractor’s best estimate of reserve range and production potential, and shall indicate the date of commencement of the proposed Appraisal Programme.
21.5.3 The proposed Appraisal Programme together with the Work Programme and Budget referred to in Article 21.5.2 shall be reviewed by the Management Committee within sixty (60) days of its submission by the Contractor. The Management Committee shall offer its comments within the said period. The said Appraisal Programme together with the Work Programme and Budget submitted by the Contractor as revised or modified or amended in light of the Management Committee review and advice, shall be adopted as the Appraisal Programme and the Contractor shall promptly proceed with implementation of the said Programme.
21.5.4 If on the basis of the results of the Appraisal Programme, the Contractor is of the opinion that NANG XXXX has been discovered in commercial quantities, it shall submit to the Management Committee as soon as practicable but not later than three (3) years from the date of notification of the aforementioned Discovery, a proposal for the declaration of the Discovery as a Commercial Discovery. Such proposal shall take into account the Government’s policies on Gas utilization and propose alternative options, if any for use or consumption of the NANG and be accompanied by a report on the Discovery supported by, inter alia, technical and economic data, evaluations, interpretations and analyses of such data and feasibility studies relating to the Discovery prepared by or on behalf of the Contractor, and other relevant information. If no proposal is submitted to the Management Committee by the Contractor within three (3) years from the said Discovery, the Contractor shall relinquish its rights to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
21.5.5 Where the Contractor has submitted a proposal for the declaration of a Discovery as a Commercial Discovery, the Management Committee shall consider the proposal of the Contractor with reference to commercial utilization or commercial development of the NANG in the domestic market or elsewhere and in the context of Government’s policy on Gas utilization and the chain of activities required to bring the NANG from the Delivery Point to potential consumers in the domestic market or elsewhere. The Management Committee may, within eighty five (85) days of the submission of the said proposal, request the Contractor to submit any additional information on the Discovery, the anticipated markets or any other related matter, that may reasonably be required to facilitate a review. The Contractor shall submit the required information within thirty (30) days of the request by the Management Committee. The Management Committee will advise the Contractor of its review within one hundred and thirty five (135) days from the submission of proposal or within fifty five (55) days from the receipt of additional information, as the case may be, on the proposal made by the Contractor to declare the Discovery as a Commercial Discovery.
21.5.6 If the Contractor declares the Discovery a Commercial Discovery after taking into account the advice of the Management Committee as referred to in the Article 21.5.5, the Contractor shall, within one (1) year of the declaration of the Discovery as a Commercial Discovery, submit a development plan for the development of the Discovery to the Management Committee for approval. Such plan shall be supported by all relevant information including, inter alia, the information required in Article 10.7.
21.5.7 Unless otherwise agreed by the Management Committee, it shall consider the proposed development plan and give their approval within one hundred and sixty five (165) days of submission thereof or eighty five (85) days from the receipt of the clarifications/additional information from the Contractor. Any clarification/additional information required by the Management Committee shall be asked for within eighty five (85) days of receipt of the proposal from the Contractor. The Contractor shall provide such additional information within thirty (30) days from the receipt of request by the Management Committee. If the Management Committee fails to convey its decision within one hundred and sixty five (165) days from the submission of the development plan or eighty five (85) days from the receipt of the clarifications/additional information, whichever is later, the Contractor may submit the development plan for the approval of the Government. Also, where, the Management Committee rejects the development plan of the Contractor, the Contractor can submit the development plan for the approval of the Government.
21.5.8 Where the development plan is submitted to the Government for approval pursuant to Article 21.5.7, the Government shall convey its decision within one hundred and fifteen (115) days from the date of receipt of the proposal from the Contractor. Government, where it considers necessary, may ask clarifications/additional information from the Contractor within eighty five (85) days and shall convey its decision within fifty five (55) days from the date of receipt of such clarifications/additional information.
21.5.9 If the Government has failed to approve or disapproves the Contractor’s proposed development plan, within one hundred and fifteen (115) days from receipt or within fifty five (55) days from the receipt of clarifications/ information from the Contractor as mentioned in the Article 21.5.8, the Government shall advise the Contractor, in writing, of the reasons for such failure or disapproval and the Government and the Contractor shall meet to discuss the said development plan and the reasons for the said failure to approve or disapproval, and use their best efforts to agree on appropriate modifications thereto to meet the Government’s concerns or objections. Thereafter, the Contractor shall have the right to resubmit, within eighty five (85) days of communication from the Government, the proposed development plan duly amended to meet the Government’s concerns. Such right of resubmission of the proposed development plan shall be exercisable by the Contractor only once. The Government will respond to the re-submitted plan within one hundred and fifteen (115) days. If no such plan is submitted to the Government within the above specified period, the Contractor shall relinquish its right to develop such Gas Discovery and such Discovery shall be excluded from the Contract Area.
21.5.10 In the event that the Management Committee or Government, as may be the case, approves the Contractor’s development plan for the development of such Commercial Discovery, with such modifications and amendments as the Management Committee or Government, as may be the case, may approve, the said Gas Discovery shall be promptly developed by the Contractor in accordance with the approved plan which shall be the Development Plan.
21.5.11 The Contractor will have a two (2) years period, from the date of approval of the Development Plan by the Management Committee or Government, to tie-up the market(s) for sale of Non-associated Natural Gas.
21.5.12 In the event the Contractor does not commence development of such Discovery within ten (10) years from the date of the first Discovery Well, the Contractor shall relinquish its right to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
Appears in 1 contract
Samples: Production Sharing Agreement
Non Associated Natural Gas (NANG. 21.5.1 In the event of a Discovery of NANG in the Contract Area, the Contractor shall promptly report such Discovery to the Management Committee and the Government and the provisions of Articles Articles
10.1 and 10.2 shall apply. The remaining provisions of Article 10 would apply to the Discovery and development of NANG only insofar as they are not inconsistent with the provisions of this Article. Notwithstanding the provisions of Article 3, the Contractor shall be entitled to retain the Discovery Area subject to the provisions of this Article 21.
21.5.2 If, pursuant to Article 10.1, the Contractor gives notification that the Discovery is of potential commercial interest, the Contractor shall submit to the Management Committee, within one (1) year from the date of notification of the above said Discovery, the proposed Appraisal Programme, including a Work Programme and Budget to carry out an adequate and effective appraisal of such Discovery, to determine (i) without delay, whether such Discovery is a Commercial Discovery and (ii) with reasonable precision, the boundaries of the area to be delineated as the Development Area. Such proposed Appraisal Programme shall be supported by all relevant data such as Well data, Contractor’s 's best estimate of reserve range and production potential, and shall indicate the date of commencement of the proposed Appraisal Programme.
21.5.3 The proposed Appraisal Programme together with the Work Programme and Budget referred to in Article 21.5.2 shall be reviewed considered by the Management Committee within sixty one hundred and twenty (60120) days of its submission by the Contractor. The Management Committee shall review the Appraisal Programme of the Contractor and offer its comments within the said period. The said Appraisal Programme together with the Work Programme and Budget submitted by the Contractor as revised or modified or amended in light of the Management Committee review and advice, shall be adopted as the Appraisal Programme and the Contractor shall promptly proceed with implementation of the said Programme.
21.5.4 If on the basis of the results of the Appraisal Programme, the Contractor is of the opinion that NANG has been discovered in commercial quantities, it shall submit to the Management Committee as soon as practicable but not later than three (3) years from the date of notification of the aforementioned Discovery, a proposal for the declaration of the Discovery as a Commercial Discovery. Such proposal shall take into account the Government’s policies on Gas utilization and propose alternative options, if any for use or consumption of the NANG and be accompanied by a report on the Discovery supported by, inter alia, technical and economic data, evaluations, interpretations and analyses of such data and feasibility studies relating to the Discovery prepared by or on behalf of the Contractor, and other relevant information. If no proposal is submitted to the Management Committee by the Contractor within three (3) years from the said Discovery, the Contractor shall relinquish its rights to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
21.5.5 Where the Contractor has submitted a proposal for the declaration of a Discovery as a Commercial Discovery, the Management Committee shall consider the proposal of the Contractor with reference to commercial utilization or commercial development of the NANG in the domestic market or elsewhere and in the context of Government’s policy on Gas utilization and the chain of activities required to bring the NANG from the Delivery Point to potential consumers in the domestic market or elsewhere. The Management Committee may, within eighty five ninety (8590) days of the submission of the said proposal, request the Contractor to submit any additional information on the Discovery, the anticipated markets or any other related matter, that may reasonably be required to facilitate a review. The Contractor shall submit the required information within thirty (30) days of the request by the Management Committee. The Management Committee will advise the Contractor of its review within one hundred and thirty five fifty (135150) days from the submission of proposal or within fifty five sixty (5560) days from the receipt of additional information, as the case may be, on the proposal made by the Contractor to declare the Discovery as a Commercial Discovery.
21.5.6 If the Contractor declares the Discovery a Commercial Discovery after taking into account the advice of the Management Committee as referred to in the Article 21.5.5, the Contractor shall, within one one
(1) year of the declaration of the Discovery as a Commercial Discovery, submit a development plan for the development of the Discovery to the Management Committee for approval. Such plan shall be supported by all relevant information including, inter alia, the information required in Article 10.7.
21.5.7 Unless otherwise agreed by the Management Committee, it shall consider the proposed development plan and give their approval within one hundred and sixty five eighty (165180) days of submission thereof or eighty five ninety (8590) days from the receipt of the clarifications/additional information from the Contractor. Any clarification/additional information required by the Management Committee shall be asked for within eighty five ninety (8590) days of receipt of the proposal from the Contractor. The Contractor shall provide such additional information within thirty (30) days from the receipt of request by the Management Committee. If the Management Committee fails to convey its decision within one hundred and sixty five eighty (165180) days from the submission of the development plan or eighty five ninety (8590) days from the receipt of the clarifications/additional information, whichever is later, the Contractor may submit the development plan for the approval of the Government. Also, where, the Management Committee rejects the development plan of the Contractor, the Contractor can submit the development plan for the approval of the Government.
21.5.8 Where the development plan is submitted to the Government for approval pursuant to Article 21.5.7, the Government shall convey its decision within one hundred and fifteen twenty (115120) days from the date of receipt of the proposal from the Contractor. Government, where it considers necessary, may ask clarifications/additional information from the Contractor within eighty five ninety (8590) days and shall convey its decision within fifty five (5560) days from the date of receipt of such clarifications/additional information.
21.5.9 If the Government has failed to approve or disapproves the Contractor’s proposed development plan, within one hundred and fifteen twenty (115120) days from receipt or within fifty five sixty (5560) days from the receipt of clarifications/ information from the Contractor as mentioned in the Article 21.5.8, the Government shall advise the Contractor, in writing, of the reasons for such failure or disapproval and the Government and the Contractor shall meet to discuss the said development plan and the reasons for the said failure to approve or disapproval, and use their best efforts to agree on appropriate modifications thereto to meet the Government’s concerns or objections. Thereafter, the Contractor shall have the right to resubmit, within eighty five ninety (8590) days of communication from the Government, the proposed development plan duly amended to meet the Government’s concerns. Such right of resubmission of the proposed development plan shall be exercisable by the Contractor only once. The Government will respond to the re-submitted plan within one hundred and fifteen (115) days. If no such plan is submitted to the Government within the above specified period, the Contractor shall relinquish its right to develop such Gas Discovery and such Discovery shall be excluded from the Contract Area.
21.5.10 In the event that the Management Committee or Government, as may be the case, approves the Contractor’s development plan for the development of such Commercial Discovery, with such modifications and amendments as the Management Committee or Government, as may be the case, may approve, the said Gas Discovery shall be promptly developed by the Contractor in accordance with the approved plan which shall be the Development Plan.
21.5.11 The Contractor will have a two (2) years period, from the date of approval of the Development Plan by the Management Committee or Government, to tie-up the market(s) for sale of Non-associated Natural Gas.
21.5.12 In the event the Contractor does not commence development of such Discovery within ten (10) years from the date of the first Discovery Well, the Contractor shall relinquish its right to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
Appears in 1 contract
Samples: Production Sharing Contract
Non Associated Natural Gas (NANG. 21.5.1 In the event of a Discovery of NANG in the Contract Area, the Contractor shall promptly report such Discovery to the Management Committee and the Government and the provisions of Articles 10.1 and 10.2 shall apply. The remaining provisions of Article 10 would apply to the Discovery and development of NANG only insofar as they are not inconsistent with the provisions of this Article. Notwithstanding the provisions of Article 3, the Contractor shall be entitled to retain the Discovery Area subject to the provisions of this Article 21.
21.5.2 If, pursuant to Article 10.1, the Contractor gives notification that the Discovery is of potential commercial interest, the Contractor shall submit to the Management Committee, within one (1) year from the date of notification of the above said Discovery, the proposed Appraisal Programme, including a Work Programme and Budget to carry out an adequate and effective appraisal of such Discovery, to determine (i) without delay, whether such Discovery is a Commercial Discovery and (ii) with reasonable precision, the boundaries of the area to be delineated as the Development Area. Such proposed Appraisal Programme shall be supported by all relevant data such as Well data, Contractor’s best estimate of reserve range and production potential, and shall indicate the date of commencement of the proposed Appraisal Programme.
21.5.3 The proposed Appraisal Programme together with the Work Programme and Budget referred to in Article 21.5.2 shall be reviewed by the Management Committee within sixty (60) days of its submission by the Contractor. The Management Committee shall offer its comments within the said period. The said Appraisal Programme together with the Work Programme and Budget submitted by the Contractor as revised or modified or amended in light of the Management Committee review and advice, shall be adopted as the Appraisal Programme and the Contractor shall promptly proceed with implementation of the said Programme.
21.5.4 If on the basis of the results of the Appraisal Programme, the Contractor is of the opinion that NANG has been discovered in commercial quantities, it shall submit to the Management Committee as soon as practicable but not later than three (3) years from the date of notification of the aforementioned Discovery, a proposal for the declaration of the Discovery as a Commercial Discovery. Such proposal shall take into account the Government’s policies on Gas utilization and propose alternative options, if any for use or consumption of the NANG and be accompanied by a report on the Discovery supported by, inter alia, technical and economic data, evaluations, interpretations and analyses of such data and feasibility studies relating to the Discovery prepared by or on behalf of the Contractor, and other relevant information. If no proposal is submitted to the Management Committee by the Contractor within three (3) years from the said Discovery, the Contractor shall relinquish its rights to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
21.5.5 Where the Contractor has submitted a proposal for the declaration of a Discovery as a Commercial Discovery, the Management Committee shall consider the proposal of the Contractor with reference to commercial utilization or commercial development of the NANG in the domestic market or elsewhere and in the context of Government’s policy on Gas utilization and the chain of activities required to bring the NANG from the Delivery Point to potential consumers in the domestic market or elsewhere. The Management Committee may, within eighty five (85) days of the submission of the said proposal, request the Contractor to submit any additional information on the Discovery, the anticipated markets or any other related matter, that may reasonably be required to facilitate a review. The Contractor shall submit the required information within thirty (30) days of the request by the Management Committee. The Management Committee will advise the Contractor of its review within one hundred and thirty five (135) days from the submission of proposal or within fifty five (55) days from the receipt of additional information, as the case may be, on the proposal made by the Contractor to declare the Discovery as a Commercial Discovery.
21.5.6 If the Contractor declares the Discovery a Commercial Discovery after taking into account the advice of the Management Committee as referred to in the Article 21.5.5, the Contractor shall, within one (1) year of the declaration of the Discovery as a Commercial Discovery, submit a development plan for the development of the Discovery to the Management Committee for approval. Such plan shall be supported by all relevant information including, inter alia, the information required in Article 10.7.
21.5.7 Unless otherwise agreed by the Management Committee, it shall consider the proposed development plan and give their approval within one hundred and sixty five (165) days of submission thereof or eighty five (85) days from the receipt of the clarifications/additional information from the Contractor. Any clarification/additional information required by the Management Committee shall be asked for within eighty five (85) days of receipt of the proposal from the Contractor. The Contractor shall provide such additional information within thirty (30) days from the receipt of request by the Management Committee. If the Management Committee fails to convey its decision within one hundred and sixty five (165) days from the submission of the development plan or eighty five (85) days from the receipt of the clarifications/additional information, whichever is later, the Contractor may submit the development plan for the approval of the Government. Also, where, the Management Committee rejects the development plan of the Contractor, the Contractor can submit the development plan for the approval of the Government.
21.5.8 Where the development plan is submitted to the Government for approval pursuant to Article 21.5.7, the Government shall convey its decision within one hundred and fifteen (115) days from the date of receipt of the proposal from the Contractor. Government, where it considers necessary, may ask clarifications/additional information from the Contractor within eighty five (85) days and shall convey its decision within fifty five (55) days from the date of receipt of such clarifications/additional information.
21.5.9 If the Government has failed to approve or disapproves the Contractor’s proposed development plan, within one hundred and fifteen (115) days from receipt or within fifty five (55) days from the receipt of clarifications/ information from the Contractor as mentioned in the Article 21.5.8, the Government shall advise the Contractor, in writing, of the reasons for such failure or disapproval and the Government and the Contractor shall meet to discuss the said development plan and the reasons for the said failure to approve or disapproval, and use their best efforts to agree on appropriate modifications thereto to meet the Government’s concerns or objections. Thereafter, the Contractor shall have the right to resubmit, within eighty five (85) days of communication from the Government, the proposed development plan duly amended to meet the Government’s concerns. Such right of resubmission of the proposed development plan shall be exercisable by the Contractor only once. The Government will respond to the re-submitted plan within one hundred and fifteen (115) days. If no such plan is submitted to the Government within the above specified period, the Contractor shall relinquish its right to develop such Gas Discovery and such Discovery shall be excluded from the Contract Area.
21.5.10 In the event that the Management Committee or Government, as may be the case, approves the Contractor’s development plan for the development of such Commercial Discovery, with such modifications and amendments as the Management Committee or Government, as may be the case, may approve, the said Gas Discovery shall be promptly developed by the Contractor in accordance with the approved plan which shall be the Development Plan.
21.5.11 The Contractor will have a two (2) years period, from the date of approval of the Development Plan by the Management Committee or Government, to tie-up the market(s) for sale of Non-associated Natural Gas.
21.5.12 In the event the Contractor does not commence development of such Discovery within ten (10) years from the date of the first Discovery Well, the Contractor shall relinquish its right to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.three
Appears in 1 contract
Samples: Production Sharing Agreement
Non Associated Natural Gas (NANG. 21.5.1 a) In the event of a Discovery of NANG in the Contract Agreement Area, the Contractor shall promptly report such Discovery to the Management Advisory Committee and the Government PRDS and the provisions of Articles 10.1 Articles
28.1 and 10.2 28.2 shall apply. The remaining provisions of Article 10 28 would apply to the Discovery and development of NANG only insofar as they are not inconsistent with the provisions of this Article. Notwithstanding the provisions of Article 3, the Contractor shall be entitled to retain the Discovery Area subject to the provisions of this Article 2131.
21.5.2 b) If, pursuant to Article 10.128.1, the Contractor gives notification that the Discovery is of potential commercial interest, the Contractor shall submit to the Management CommitteeAdvisory Committee and the PRDS, within one hundred and eighty (1180) year days from the date of notification of the above said Discovery, the proposed Appraisal Programme, including a Work Programme and Budget to carry out an adequate and effective appraisal of such Discovery, to determine determine:
(i) without delay, whether such Discovery is a Commercial Discovery and Discovery; and
(ii) with reasonable precision, the boundaries of the area to be delineated as the Development Area. .
c) Such proposed Appraisal Programme shall be supported by all relevant data such as Well data, the Contractor’s best estimate of reserve range and production potential, and shall indicate the date of commencement of the proposed Appraisal Programme.
21.5.3 The proposed Appraisal Programme together with d) Up to six (6) months before the Work Programme and Budget referred to in Article 21.5.2 shall be reviewed by the Management Committee within sixty (60) days of its submission by the Contractor. The Management Committee shall offer its comments within the said period. The said Appraisal Programme together with the Work Programme and Budget submitted by the Contractor as revised or modified or amended in light end of the Management Committee review and advice, shall be adopted as the Appraisal Programme and the Contractor shall promptly proceed with implementation of the said Programme.
21.5.4 If on the basis of the results of the Appraisal Programme, the Contractor is of the opinion that NANG has been discovered in commercial quantities, it shall submit to the Management Committee as soon as practicable but not later than three (3) years from the date of notification of the aforementioned Discovery, a proposal for the declaration of the Discovery as a Commercial Discovery. Such proposal shall take into account the Government’s policies on Gas utilization and propose alternative options, if any for use or consumption of the NANG and be accompanied by a report on the Discovery supported by, inter alia, technical and economic data, evaluations, interpretations and analyses of such data and feasibility studies relating to the Discovery prepared by or on behalf of the Contractor, and other relevant information. If no proposal is submitted to the Management Committee by the Contractor within three (3) years from the said Discovery, the Contractor shall relinquish its rights to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Area.
21.5.5 Where the Contractor has submitted a proposal for the declaration of a Discovery as a Commercial Discovery, the Management Committee shall consider the proposal of the Contractor with reference to commercial utilization or commercial development of the NANG in the domestic market or elsewhere and in the context of Government’s policy on Gas utilization and the chain of activities required to bring the NANG from the Delivery Point to potential consumers in the domestic market or elsewhere. The Management Committee may, within eighty five (85) days of the submission of the said proposal, request the Contractor to submit any additional information on the Discovery, the anticipated markets or any other related matter, that may reasonably be required to facilitate a review. The Contractor shall submit the required information within thirty (30) days of the request by the Management Committee. The Management Committee will advise the Contractor of its review within one hundred and thirty five (135) days from the submission of proposal or within fifty five (55) days from the receipt of additional information, as the case may be, on the proposal made by the Contractor to declare the Discovery as a Commercial Discovery.
21.5.6 If the Contractor declares the Discovery a Commercial Discovery after taking into account the advice of the Management Committee as referred to in the Article 21.5.5, the Contractor shall, within one (1) year of the declaration of the Discovery as a Commercial Discovery, submit a development plan for the development of the Discovery to the Management Committee for approval. Such plan shall be supported by all relevant information including, inter alia, the information required in Article 10.7.
21.5.7 Unless otherwise agreed by the Management Committee, it shall consider the proposed development plan and give their approval within one hundred and sixty five (165) days of submission thereof or eighty five (85) days from the receipt of the clarifications/additional information from the Contractor. Any clarification/additional information required by the Management Committee shall be asked for within eighty five (85) days of receipt of the proposal from the Contractor. The Contractor shall provide such additional information within thirty (30) days from the receipt of request by the Management Committee. If the Management Committee fails to convey its decision within one hundred and sixty five (165) days from the submission of the development plan or eighty five (85) days from the receipt of the clarifications/additional information, whichever is laterExploration Period, the Contractor may submit Appraisal Programmes for Discoveries encountered in its Agreement Area but not considered commercial at the development plan for the approval time of the Government. Also, where, the Management Committee rejects the development plan of the Contractor, the Contractor can submit the development plan for the approval of the Governmentdiscovery.
21.5.8 Where the development plan is submitted to the Government for approval e) If, pursuant to Article 21.5.728.1, the Government shall convey its decision within one hundred and fifteen (115) days from the date of receipt of the proposal from the Contractor. Government, where it considers necessary, may ask clarifications/additional information from the Contractor within eighty five (85) days and shall convey its decision within fifty five (55) days from the date of receipt of such clarifications/additional information.
21.5.9 If the Government has failed to approve or disapproves the Contractor’s proposed development plan, within one hundred and fifteen (115) days from receipt or within fifty five (55) days from the receipt of clarifications/ information from the Contractor as mentioned in the Article 21.5.8, the Government shall advise the Contractor, in writing, of the reasons for such failure or disapproval and the Government and the Contractor shall meet to discuss the said development plan and the reasons for the said failure to approve or disapproval, and use their best efforts to agree on appropriate modifications thereto to meet the Government’s concerns or objections. Thereafter, the Contractor shall have the right to resubmit, within eighty five (85) days of communication from the Government, the proposed development plan duly amended to meet the Government’s concerns. Such right of resubmission of the proposed development plan shall be exercisable by the Contractor only once. The Government will respond to the re-submitted plan within one hundred and fifteen (115) days. If no such plan is submitted to the Government within the above specified period, the Contractor shall relinquish its right to develop such Gas Discovery and such Discovery shall be excluded from the Contract Area.
21.5.10 In the event that the Management Committee or Government, as may be the case, approves the Contractor’s development plan for the development of such Commercial Discovery, with such modifications and amendments as the Management Committee or Government, as may be the case, may approve, the said Gas Discovery shall be promptly developed by the Contractor in accordance with the approved plan which shall be the Development Plan.
21.5.11 The Contractor will have a two (2) years period, from the date of approval of the Development Plan by the Management Committee or Government, to tie-up the market(s) for sale of Non-associated Natural Gas.
21.5.12 In the event the Contractor does not commence development notify the Advisory Committee and the PRDS that the Discovery is of potential commercial interest and the Advisory Committee and the PRDS are reasonably of the view that the Discovery merits appraisal the Contractor may be required to produce an Appraisal Programme with a Work Programme and Budget to carry out an adequate and effective appraisal of such Discovery within ten designed to achieve the objectives set out in sub-paragraphs (10i) years from the date and (ii) of the first Discovery Well, the Contractor shall relinquish its right to develop such Discovery and the area relating to such Discovery shall be excluded from the Contract Areaparagraph b).
Appears in 1 contract
Samples: Model Petroleum Resources Agreement