Non-Compensable Delay. Contractor understands, acknowledges and agrees that delays occasioned by the events and occurrences set forth below are not compensable delays and do not constitute reason for extending the Date for Material Completion and Occupancy. It is Contractor's responsibility to make adequate provision for the following in scheduling the Work:
Appears in 42 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Non-Compensable Delay. Contractor understands, acknowledges and agrees that delays occasioned by the events and occurrences set forth below are not compensable delays and do not constitute reason for extending the Date for Material Completion and OccupancyCompletion. It is Contractor's responsibility to make adequate provision for the following in scheduling the Work:
3.3.9.1 Delay in Delivery of Materials or Equipment. Delay in delivery of materials or equipment for any cause other than those specified in Paragraph 3.3.8.
Appears in 35 contracts
Samples: Construction Contract, Construction Contract, Construction Contract
Non-Compensable Delay. Contractor understands, acknowledges and agrees that delays occasioned by the events and occurrences set forth below are not compensable delays and do not constitute reason for extending the Date for Material Completion and OccupancyCompletion. It is Contractor's responsibility to make adequate provision for the following in scheduling the Work:
Appears in 1 contract