Non-Compensable Delay. Design-Builder understands, acknowledges and agrees that delays occasioned by the events and occurrences set forth below are not compensable delays and do not constitute reason for extending the Date for Material Completion and Occupancy. It is Design-Builder's responsibility to make adequate provision for the following in scheduling the Work:
Appears in 17 contracts
Samples: Design Build Contract, Design Build Contract, Design Build Contract