Non-Compensable Delay. CM/GC understands, acknowledges and agrees that delays occasioned by the events and occurrences set forth below are not compensable delays and do not constitute reason for extending the Date for Material Completion. It is CM/GC's responsibility to make adequate provision for the following in scheduling the Work:
Appears in 3 contracts
Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement
Non-Compensable Delay. CM/GC understands, acknowledges and agrees that delays occasioned by the events and occurrences set forth below are not compensable delays and do not constitute reason for extending the Date for Material CompletionCompletion and Occupancy. It is CM/GC's responsibility to make adequate provision for the following in scheduling the Work:
Appears in 3 contracts
Samples: Construction Management Agreement, Construction Management Agreement, Construction Management Agreement