Non-Excusable Delays. THE FOLLOWING IS ADDED: For work performed by Utilities, delays up to 30 percent of the estimated duration specified in 105.07.02 are considered non-excusable. The duration includes both the advance notice and the completion of the work by the Utility. For delays caused by Railroads, delays up to 30 percent of the estimated availability specified in 105.07 are considered non-excusable.
Appears in 6 contracts
Samples: Construction Contract, Construction Contract, Long Life Pavement Markings Contract