Common use of NOTIFICATION OF CHANGE OF CONTRACT TIME OR CONTRACT PRICE Clause in Contracts

NOTIFICATION OF CHANGE OF CONTRACT TIME OR CONTRACT PRICE. 3.3.1 Any claim for a change in the Contract Time or Contract Price shall be made by written notice and delivered by CONTRACTOR to the PROJECT MANAGER within five (5) calendar days of the commencement of the event giving rise to the claim and stating the general nature of the claim. Notice of the nature and elements of the claim shall be delivered within twenty (20) calendar days after the date of such written notice. Thereafter, within ten (10) calendar days of the termination of the event giving the to the claim, notice of the extent of the claim with supporting data shall be delivered unless the CITY allows an additional period of time to ascertain more accurate data in support of the claim and shall be accompanied by CONTRACTOR’s written statement that the adjustment claimed justified as a result of the occurrence of said event. All claims for adjustment in the Contract Time or contract price shall be determined by the CITY in accordance with Article 4 hereof, if the CITY and CONTRACTOR cannot otherwise agree. NO CLAIM FOR AN ADJUSTMENT IN THE CONTRACT TIME OR CONTRACT PRICE WILL BE VALID IF NOT SUBMITTED IN STRICT ACCORDANCE WITH THE REQUIREMENTS OF THIS SECTION.

Appears in 2 contracts

Samples: Agreement, Risk Agreement

AutoNDA by SimpleDocs

NOTIFICATION OF CHANGE OF CONTRACT TIME OR CONTRACT PRICE. 3.3.1 6.3.1 Any claim for a change in the Contract Time or Contract Price shall be made by written notice and delivered by CONTRACTOR to the PROJECT MANAGER within five (5) calendar days of the commencement of the event giving rise to the claim and stating the general nature of the claim. Notice of the nature and elements of the claim shall be delivered within twenty (20) calendar days after the date of such written notice. Thereafter, within ten (10) calendar days of the termination previous notice of the event giving the rise to the claim, notice of the extent of the claim with supporting data shall be delivered unless the CITY PROJECT MANAGER allows an additional period of time to ascertain more accurate data in support of the claim and shall be accompanied by CONTRACTOR’s written statement that the adjustment claimed justified as a result of the occurrence of said event. All claims for adjustment in the Contract Time or contract price shall be determined by the CITY PROJECT MANAGER in accordance with Article 4 30 hereof, if the CITY PROJECT MANAGER and CONTRACTOR cannot otherwise agree. NO CLAIM FOR AN ADJUSTMENT IN THE CONTRACT TIME OR CONTRACT PRICE WILL BE VALID IF NOT SUBMITTED IN STRICT ACCORDANCE WITH THE REQUIREMENTS OF THIS SECTION.

Appears in 1 contract

Samples: Contract by And

NOTIFICATION OF CHANGE OF CONTRACT TIME OR CONTRACT PRICE. 3.3.1 6.3.1 Any claim for a change in the Contract Time CONTRACT TIME or Contract Price CONTRACT PRICE shall be made by written notice and delivered by CONTRACTOR XXXX to the CONSULTANT with a copy to PROJECT MANAGER within five (5) calendar days of the commencement of the event giving rise to the claim and stating the general nature of the claim. Notice of the nature and elements of the claim shall be delivered within twenty (20) 20 calendar days after the date of such written notice. Thereafter, within ten (10) calendar days of the termination of the event giving the rise to the claim, notice of the extent of the claim with supporting data shall be delivered unless the CITY CONSULTANT allows an additional period of time to ascertain more accurate data in support of the claim and shall be accompanied by CONTRACTOR’s XXXX’x written statement that the adjustment claimed is justified as a result of the occurrence of said event. All claims for adjustment in the Contract Time CONTRACT TIME or contract price CONTRACT PRICE shall be determined by the CITY CONSULTANT in accordance with Article 4 30 hereof, if the CITY CONSULTANT and CONTRACTOR XXXX cannot otherwise agree. NO CLAIM FOR AN ADJUSTMENT IN THE CONTRACT TIME OR CONTRACT PRICE WILL BE VALID IF NOT SUBMITTED IN STRICT ACCORDANCE WITH THE REQUIREMENTS OF THIS SECTION.

Appears in 1 contract

Samples: www.bidnet.com

AutoNDA by SimpleDocs

NOTIFICATION OF CHANGE OF CONTRACT TIME OR CONTRACT PRICE. 3.3.1 Any claim for a change in the Contract Time or Contract Price shall be made by written notice and delivered by CONTRACTOR Construction Manager to the PROJECT MANAGER within five (5) calendar days of the commencement of the event giving rise to the claim and stating the general nature of the claim. Notice of the nature and to the extent reasonably possible elements of the claim shall be delivered within twenty (20) calendar days after the date of such written notice. Thereafter, within ten (10) calendar days of the termination of the event giving the to the claim, notice of the extent of the claim with supporting data shall be delivered unless the CITY allows an additional period of time to ascertain more accurate data in support of the claim and shall be accompanied by CONTRACTORConstruction Manager’s written statement that the adjustment claimed justified as a result of the occurrence of said event. All claims for adjustment in the Contract Time or contract price shall be determined by the CITY in accordance with Article 4 hereof, if the CITY and CONTRACTOR Construction Manager cannot otherwise agree. NO CLAIM FOR AN ADJUSTMENT IN THE CONTRACT TIME OR CONTRACT PRICE WILL BE VALID IF NOT SUBMITTED IN STRICT ACCORDANCE WITH THE REQUIREMENTS OF THIS SECTION.

Appears in 1 contract

Samples: Construction Management at Risk Phase 2 Construction Services Agreement

Time is Money Join Law Insider Premium to draft better contracts faster.