Notification of Force Majeure Event. 11.4.4.1. The Affected Party shall give notice to the other Party of any event of Force Majeure as soon as reasonably practicable, but not later than seven (7) days after the date on which such Party knew or should reasonably have known of the commencement of the event of Force Majeure. If an event of Force Majeure results in a breakdown of communications rendering it unreasonable to give notice within the applicable time limit specified herein, then the Party claiming Force Majeure shall give such notice as soon as reasonably practicable after reinstatement of communications, but not later than one (1) Day after such reinstatement. 11.4.4.2. Provided that such notice shall be a pre-condition to the Affected Party’s entitlement to claim relief under the PPA. Such notice shall include full particulars of the event of Force Majeure, its effects on the Party claiming relief and the remedial measures proposed. The Affected Party shall give the other Party regular (and not less than weekly) reports on the progress of those remedial measures and such
Appears in 2 contracts
Samples: Power Purchase Agreement (Ppa), Power Purchase Agreement
Notification of Force Majeure Event. 11.4.4.1. The Affected Party shall give notice to the other Party of any event of Force Majeure as soon as reasonably practicable, but not later than seven (7) days after the date on which such Party knew or should reasonably have known of the commencement of the event of Force Majeure. If an event of Force Majeure results in a breakdown of communications rendering it unreasonable to give notice within the applicable time limit specified herein, then the Party claiming Force Majeure shall give such notice as soon as reasonably practicable after reinstatement of communications, but not later than one (1) Day day after such reinstatement.
11.4.4.2. Provided that such notice shall be a pre-condition to the Affected Party’s entitlement to claim relief under the PPAthis Agreement. Such notice shall include full particulars of the event of Force Majeure, its effects on the Party claiming relief and the remedial measures proposed. The Affected Party shall give the other Party regular (and not less than weeklymonthly) reports on the progress of those remedial measures and suchsuch other information as the other Party may reasonably request about the Force Majeure Event.
Appears in 2 contracts
Notification of Force Majeure Event. 11.4.4.1. The Affected Party shall give notice to the other Party of any event of Force Majeure as soon as reasonably practicable, but not later than seven (7) days after the date on which such Party knew or should reasonably have known of the commencement of the event of Force Majeure. If an event of Force Majeure results in a breakdown of communications rendering it unreasonable to give notice within the applicable time limit specified herein, then the Party claiming Force Majeure shall give such notice as soon as reasonably practicable after reinstatement of communications, but not later than one (1) Day after such reinstatement.
11.4.4.2. Provided that such notice shall be a pre-condition to the Affected Party’s Party‟s entitlement to claim relief under the PPA. Such notice shall include full particulars of the event of Force Majeure, its effects on the Party claiming relief and the remedial measures proposed. The Affected Party shall give the other Party regular (and not less than weekly) reports on the progress of those remedial measures and such
Appears in 1 contract
Samples: Power Purchase Agreement
Notification of Force Majeure Event. 11.4.4.1. 8.4.1 The Affected Party shall give notice to the other Party of any event of Force Majeure as soon as reasonably practicable, but not later than seven (7) days after the date on which such Party knew or should reasonably have known of the commencement of the event of Force Majeure. If an event of Force Majeure results in a breakdown of communications rendering it unreasonable to give notice within the applicable time limit specified herein, then the Party claiming Force Majeure shall give such notice as soon as reasonably practicable after reinstatement of communications, but not later than one (1) Day after such reinstatement.
11.4.4.2. 8.4.2 Provided that such notice shall be a pre-condition to the Affected Party’s entitlement to claim relief under the PPA. Such notice shall include full particulars of the event of Force Majeure, its effects on the Party claiming relief and the remedial measures proposed. The Affected Party shall give the other Party regular (and not less than weekly) reports on the progress of those remedial measures and suchsuch other information as the other Party may reasonably request about the Force Majeure Event.
8.4.3 The Affected Party shall give notice to the other Party of (i) the cessation of the relevant event of Force Majeure; and (ii) the cessation of the effects of such event of Force Majeure on the performance of its rights or obligations under the PPA, as soon as practicable after becoming aware of each of these cessations.
Appears in 1 contract
Samples: Power Purchase Agreement