Obligations relating to transmission losses. 5.6.1 The Supplier shall be liable for the transmission losses in all inter-state and intra- state transmission of electricity from the Point of Grid Connection to the Delivery Point. For the avoidance of doubt, the Parties expressly agree that transmission of electricity shall be undertaken solely at the risk and cost of the Supplier and all liabilities arising out of any transmission losses on inter-state and intra-state transmission lines shall be borne by the Supplier. The Parties further agree that the obligation of the Supplier to bear the transmission losses shall be restricted to the level of losses determined by the Central Commission as on the Bid Date for this Project and any differential (higher or lower) arising from revision in the level of losses thereafter by the Central Commission shall be borne by the Utility.