Ordering - Virtual Collocation. 8.4.2.1 Application -- Upon receipt of a complete Collocation Application as described in the above Section, Qwest will perform a feasibility study to determine if adequate space, power and HVAC can be found for the placement of CLEC's equipment within the Premises. The feasibility study will be provided within ten (10) calendar days of receipt of a complete Application. 8.4.2.1.1 If Qwest determines that the Application is not complete, Qwest shall notify CLEC of any deficiencies within ten (10) calendar days of the Application. Qwest shall provide sufficient detail so that CLEC has a reasonable opportunity to cure each deficiency. To retain its place in the Collocation queue for the requested Premises, CLEC must cure any deficiencies in its Application and resubmit the Application within ten (10) calendar days after being advised of the deficiencies. 8.4.2.2 Quotation – If Collocation entrance facilities and space are available, Qwest will develop a price quotation within twenty-five (25) calendar days of completion of the feasibility study. Subsequent requests to augment an existing Collocation also require receipt of an Application. Adding plug-ins, e.g., DS1 or DS3 cards to existing Virtually Collocated equipment, will be processed and provisioned within ten (10) business days. Virtual Collocation price quotes will be honored for thirty (30) calendar days from the date the quote is provided. During this period the Collocation entrance facility and space are reserved pending CLEC's Acceptance of the quoted charges.
Appears in 3 contracts
Samples: Telecommunications, Telecommunications, Telecommunications
Ordering - Virtual Collocation. 8.4.2.1 Application -- Upon receipt of a complete Collocation Application as described in the above SectionSection 8.4.1.5, Qwest will perform a feasibility study to determine if adequate space, power and HVAC can be found for the placement of CLEC's equipment within the Premises. The feasibility study will be provided within ten (10) calendar days of receipt of a complete Application.
8.4.2.1.1 If Qwest determines that the Application is not complete, Qwest shall notify CLEC of any deficiencies within ten (10) calendar days of the Application. Qwest shall provide sufficient detail so that CLEC has a reasonable opportunity to cure each deficiency. To retain its place in the Collocation queue for the requested Premises, CLEC must cure any deficiencies in its Application and resubmit the Application within ten (10) calendar days after being advised of the deficiencies.
8.4.2.2 Quotation – If Collocation entrance facilities and space are available, Qwest will develop a price quotation within twenty-five (25) calendar days of completion of the feasibility study. Subsequent requests to augment an existing Collocation also require receipt of an Application. Adding plug-ins, e.g., DS1 or DS3 cards to existing Virtually Collocated virtually collocated equipment, will be processed and provisioned within ten (10) business days. Virtual Collocation price quotes will be honored for thirty (30) calendar days from the date the quote is provided. During this period the Collocation entrance facility and space are reserved pending CLEC's Acceptance of the quoted charges.
8.4.2.3 Acceptance -- Upon receipt of complete Collocation Acceptance, as described in 8.4.1.6, space will be reserved and construction by Qwest will begin.
8.4.2.4 Interval -- The interval for Virtual Collocation shall vary depending upon four factors – 1) whether the request was forecasted in accordance with Section 8.4.1.4 or the space was reserved, in accordance with Section 8.4.1.7; 2) whether CLEC provides its Acceptance within seven (7) calendar days receipt of the quotation; 3) whether CLEC delivers its collocated equipment to Qwest in a timely manner, which shall mean within fifty-three (53) calendar days of the receipt of the complete Collocation Application; and 4) whether the Application requires major infrastructure additions or modifications. The installation of line cards and other minor modifications shall be performed by Qwest on shorter intervals and in no instance shall any such interval exceed thirty (30) calendar days. When Qwest is permitted to complete a Collocation installation in an interval that is longer than the standard intervals set forth below, Qwest shall use its best efforts to minimize the extension of the intervals beyond such standard intervals. In all cases, where CLEC finds during a walk-through inspection that any requirements for use of the space previously identified, on the Collocation Application, to Qwest have not been completed by Qwest, Qwest will remedy such defects within a reasonable period of time at its own expense.
Appears in 1 contract
Samples: Telecommunications
Ordering - Virtual Collocation. 8.4.2.1 Application -- Upon receipt of a complete Collocation Application as described in the above SectionSection 8.4.1.5, Qwest will perform a feasibility study to determine if adequate space, power and HVAC can be found for the placement of CLEC's equipment within the Premises. The feasibility study will be provided within ten (10) calendar days of receipt of a complete Application.
8.4.2.1.1 If Qwest determines that the Application is not complete, Qwest shall notify CLEC of any deficiencies within ten (10) calendar days of the Application. Qwest shall provide sufficient detail so that CLEC has a reasonable opportunity to cure each deficiency. To retain its place in the Collocation queue for the requested Premises, CLEC must cure any deficiencies in its Application and resubmit the Application within ten (10) calendar days after being advised of the deficiencies.
8.4.2.2 Quotation – If Collocation entrance facilities and space are available, Qwest will develop a price quotation within twenty-five (25) calendar days of completion of the feasibility study. Subsequent requests to augment an existing Collocation also require receipt of an Application. Adding plug-ins, e.g., DS1 or DS3 cards to existing Virtually Collocated virtually collocated equipment, will be processed and provisioned within ten (10) business days. Virtual Collocation price quotes will be honored for thirty (30) calendar days from the date the quote is provided. During this period the Collocation entrance facility and space are reserved pending CLEC's Acceptance of the quoted charges.
8.4.2.3 Acceptance -- Upon receipt of complete Collocation Acceptance, as described in 8.4.1.6, space will be reserved and construction by Qwest will begin.
8.4.2.4 Interval -- The interval for Virtual Collocation shall vary depending upon four factors
– 1) whether the request was forecasted in accordance with Section 8.4.1.4 or the space was reserved, in accordance with Section 8.4.1.7; 2) whether CLEC provides its Acceptance within seven (7) calendar days receipt of the quotation; 3) whether CLEC delivers its collocated equipment to Qwest in a timely manner, which shall mean within fifty-three (53) calendar days of the receipt of the complete Collocation Application; and 4) whether the Application requires major infrastructure additions or modifications. The installation of line cards and other minor modifications shall be performed by Qwest on shorter intervals and in no instance shall any such interval exceed thirty (30) calendar days. When Qwest is permitted to complete a Collocation installation in an interval that is longer than the standard intervals set forth below, Qwest shall use its best efforts to minimize the extension of the intervals beyond such standard intervals.
Appears in 1 contract
Samples: Telecommunications
Ordering - Virtual Collocation. 8.4.2.1 Application -- Upon receipt of a complete Collocation Application as described in the above SectionSection 8.4.1.5, Qwest will perform a feasibility study to determine if adequate space, power and HVAC can be found for the placement of CLEC's equipment within the Premises. The feasibility study will be provided within ten (10) calendar days of receipt of a complete Application.
8.4.2.1.1 If Qwest determines that the Application is not complete, Qwest shall notify CLEC of any deficiencies within ten (10) calendar days of the Application. Qwest shall provide sufficient detail so that CLEC has a reasonable opportunity to cure each deficiency. To retain its place in the Collocation queue for the requested Premises, CLEC must cure any deficiencies in its Application and resubmit the Application within ten (10) calendar days after being advised of the deficiencies.
8.4.2.2 Quotation – If Collocation entrance facilities and space are available, Qwest will develop a price quotation within twenty-five (25) calendar days of completion of the feasibility study. Subsequent requests to augment an existing Collocation also require receipt of an Application. Adding plug-ins, e.g., DS1 or DS3 cards to existing Virtually Collocated virtually collocated equipment, will be processed and provisioned within ten (10) business days. Virtual Collocation price quotes will be honored for thirty (30) calendar days from the date the quote is provided. During this period the Collocation entrance facility and space are reserved pending CLEC's Acceptance of the quoted charges.
8.4.2.3 Acceptance -- Upon receipt of complete Collocation Acceptance, as described in 8.4.1.6, space will be reserved and construction by Qwest will begin.
8.4.2.4 Interval -- The interval for Virtual Collocation shall vary depending upon four factors – 1) whether the request was forecasted in accordance with Section 8.4.1.4 or the space was reserved, in accordance with Section 8.4.1.7; 2) whether CLEC provides its Acceptance within seven (7) calendar days receipt of the quotation; 3) whether CLEC delivers its collocated equipment to Qwest in a timely manner, which shall mean within fifty-three (53) calendar days of the receipt of the complete Collocation Application; and 4) whether the Application requires major infrastructure additions or modifications. The installation of line cards and other minor modifications shall be performed by Qwest on shorter intervals and in no instance shall any such interval exceed thirty (30) calendar days. When Qwest is permitted to complete a Collocation installation in an interval that is longer than the standard intervals set forth below, Qwest shall use its best efforts to minimize the extension of the intervals beyond such standard intervals.
Appears in 1 contract
Samples: Interconnection Agreement