Other Change Orders. For Change Orders involving the following situations that would materially affect the completion of the Work by lengthening the critical path of the Overall Project Schedule, the Design Professional shall determine the appropriate number of days and thereby extend the Material Completion and Occupancy Date. (a) Changes due to Subsurface or Other Unforeseen Conditions, Article 3.2.12. (b) Changes for Compensable Rock, Article 3.2.13. (c) Changes deleting work, Paragraph 3.2.3.2.2.
Appears in 35 contracts
Samples: Construction Contract, Construction Contract, Construction Contract