Other Methods of Procurement of Goods and Works. (a) The following table specifies the methods of procurement, other than International and National Competitive Bidding, which may be used for goods and works. The Procurement Plan shall specify the circumstances under which such methods may be used. (a) National Competitive Bidding (b) Force Account (c) Shopping (b) The procedures to be followed for National Competitive Bidding shall be those set forth in the Law on Tendering and Bidding of the People’s Republic of China promulgated by Order No.21 of the President of the People’s Republic of China on August 30, 1999, with the following clarifications required for compliance with the Guidelines: (i) All invitations to prequalify or to bid shall be advertised in a newspaper of national circulation in the Borrower’s country, except for civil works contracts that are estimated cost less than $2,000,000 equivalent each and for goods contracts that are estimated to cost less than $300,000 equivalent each, which may be advertised in a provincial daily newspaper. Such advertisement shall be made in sufficient time for prospective bidders to obtain prequalification or bidding documents and prepare and submit their responses. In any event, a minimum of thirty (30) days shall be given to bidders between the date of advertisement in such newspaper and the deadline for submission of bids, and the advertisement and bidding documents shall specify the deadline for such submission. (ii) Qualification requirements of bidders and the method of evaluating the qualification of each bidder shall be specified in detail in the bidding documents. (iii) All bidders that meet the qualification criteria set out in the pre- qualification document shall be allowed to bid and there shall be no limit on the number of pre-qualified bidders. (iv) All bidders shall be required to provide security in an amount sufficient to protect the Borrower or the Project Implementing Entity, as the case may be, in case of breach of contract by the contractor, and the bidding documents shall specify the required form and amount of such security. (v) Bidders will be allowed to submit bids by mail or by hand. The time for opening of all bids shall be the same as the deadline for receipt of such bids. (vi) All bids shall be opened in public; all bidders shall be offered an opportunity to be present (either in person or through their representatives) at the time of bid opening, but bidders shall not be required to be present at the bid opening. (vii) All bid evaluation criteria shall be disclosed in the bidding documents and quantified in monetary terms or expressed in the form of pass/fail requirements. (viii) No bid may be rejected solely on the basis that the bid price falls outside any standard contract estimate, or margin or bracket of average bids established by the Borrower or the Project Implementing Entity, as the case may be. (ix) Each contract shall be awarded to the lowest evaluated responsive bidder, that is, the bidder who meets the appropriate standards of capability and resources and whose bid has been determined: (A) to be substantially responsive to the bidding documents; and (B) to offer the lowest evaluated cost. The winning bidder shall not be required, as a condition of award, to undertake responsibilities for work not stipulated in the bidding documents or otherwise to modify the bid as originally submitted. (x) Each contract financed with the proceeds of the Loan shall provide that the suppliers and contractors shall permit the Bank, at its request, to inspect their accounts and records relating to the performance of the contract and to have said accounts and records audited by auditors appointed by the Bank. (xi) Government owned enterprises in the Borrower;s country may be permitted to bid or submit a proposal of goods and works if they can establish that they: (i) are legally and financially autonomous; (ii) operate under commercial law; and (iii) are not a dependent agency of the agency conducting the procurement. (xii) Re-bidding should not be allowed solely because the number of bids is less than three (3). (c) Use of force account for civil works shall be permissible only under Part B of the Project when: (i) works are small and scattered or in remote locations for which qualified contractors are unlikely to bid at reasonable price; and (ii) the aggregate value of the works under force account shall not exceed $7,500,000 equivalent.
Appears in 1 contract
Samples: Loan Agreement
Other Methods of Procurement of Goods and Works. (a) The following table specifies the methods of procurement, other than International and National Competitive Bidding, which may be used for goods and works. The Procurement Plan shall specify the circumstances under which such methods may be used.
(a) National Competitive Bidding
(b) Force Account
(c) Shopping
(b) The . In addition, the procedures to be followed for National Competitive Bidding shall be those set forth in the Law on Tendering and Bidding of the People’s Republic of China promulgated by Order No.21 of the President of the People’s Republic of China on August 30, 1999, with the following clarifications required for compliance with the Procurement Guidelines:
(i) All invitations to prequalify or to bid shall be advertised in a newspaper of national circulation in the Borrower’s country, except for civil works contracts that are estimated cost less than $2,000,000 equivalent each and for goods contracts that are estimated to cost less than $300,000 equivalent each, which may be advertised in a provincial daily newspaper. Such advertisement shall be made in sufficient time for prospective bidders to obtain prequalification or bidding documents and prepare and submit their responses. In any event, a minimum of thirty (30) days shall be given to bidders between the date of advertisement in such newspaper and the deadline for submission of bids, and the advertisement and bidding documents shall specify the deadline for such submission.
(ii) Qualification requirements of bidders and the method of evaluating the qualification of each bidder shall be specified in detail in the bidding documents.
(iii) All bidders that meet the qualification criteria set out in the pre- pre-qualification document shall be allowed to bid and there shall be no limit on the number of pre-qualified bidders.
(iv) All bidders shall be required to provide security in an amount sufficient to protect the Borrower or the Project Implementing Entity, as the case may be, in case of breach of contract by the contractor, and the bidding documents shall specify the required form and amount of such security.
(v) Bidders will be allowed to submit bids by mail or by hand. The time for opening of all bids shall be the same as the deadline for receipt of such bids.
(vi) All bids shall be opened in public; all bidders shall be offered an opportunity to be present (either in person or through their representatives) at the time of bid opening, but bidders shall not be required to be present at the bid opening.
(vii) All bid evaluation criteria shall be disclosed in the bidding documents and quantified in monetary terms or expressed in the form of pass/fail requirements.
(viii) No bid may be rejected solely on the basis that the bid price falls outside any standard contract estimate, or margin or bracket of average bids established by the Borrower or the Project Implementing Entity, as the case may be.
(ix) Each contract shall be awarded to the lowest evaluated responsive bidder, that is, the bidder who meets the appropriate standards of capability and resources and whose bid has been determined: (A) to be substantially responsive to the bidding documents; and (B) to offer the lowest evaluated cost. The winning bidder shall not be required, as a condition of award, to undertake responsibilities for work not stipulated in the bidding documents or otherwise to modify the bid as originally submitted.
(x) Each contract financed with the proceeds of the Loan shall provide that the suppliers and contractors shall permit the Bank, at its request, to inspect their accounts and records relating to the performance of the contract and to have said accounts and records audited by auditors appointed by the Bank.
(xi) Government owned enterprises in the Borrower;s Borrower’s country may be permitted to bid or submit a proposal of goods and works if they can establish that they: (iA) are legally and financially autonomous; (iiB) operate under commercial law; and (iiiC) are not a dependent agency of the agency conducting the procurement.
(xii) Re-bidding should not be allowed solely because the number of bids is less than three (3).
(cb) Use of force account for civil works shall be permissible only under Part B of the Project when: (i) works are small and scattered or in remote locations for which qualified contractors are unlikely to bid at reasonable price; and (ii) the aggregate value of the works under force account shall not exceed $7,500,000 equivalent.Shopping
Appears in 1 contract
Samples: Loan Agreement
Other Methods of Procurement of Goods and Works. (a) The following table specifies the methods of procurement, other than International and National Competitive Bidding, which may be used for goods and works. The Procurement Plan shall specify the circumstances under which such methods may be used.
(a) National Competitive Bidding
(b) Force Account
(c) Shopping
(b) The . In addition, the procedures to be followed for National Competitive Bidding shall be those set forth in the Law on Tendering and Bidding of the People’s Republic of China promulgated by Order No.21 of the President of the People’s Republic of China on August 30, 1999, with the following clarifications required for compliance with the Procurement Guidelines:
(i) All invitations to prequalify or to bid shall be advertised in a newspaper of national circulation in the Borrower’s country, except for civil works contracts that are estimated cost less than $2,000,000 equivalent each and for goods contracts that are estimated to cost less than $300,000 equivalent each, which may be advertised in a provincial daily newspaper. Such advertisement shall be made in sufficient time for prospective bidders to obtain prequalification or bidding documents and prepare and submit their responses. In any event, a minimum of thirty (30) days shall be given to bidders between the date of advertisement in such newspaper and the deadline for submission of bids, and the advertisement and bidding documents shall specify the deadline for such submission.
(ii) Qualification requirements of bidders and the method of evaluating the qualification of each bidder shall be specified in detail in the bidding documents.
(iii) All bidders that meet the qualification criteria set out in the pre- pre-qualification document shall be allowed to bid and there shall be no limit on the number of pre-qualified bidders.
(iv) All bidders shall be required to provide security in an amount sufficient to protect the Borrower or the Project Implementing Entity, as the case may be, in case of breach of contract by the contractor, and the bidding documents shall specify the required form and amount of such security.
(v) Bidders will be allowed to submit bids by mail or by hand. The time for opening of all bids shall be the same as the deadline for receipt of such bids.
(vi) All bids shall be opened in public; all bidders shall be offered an opportunity to be present (either in person or through their representatives) at the time of bid opening, but bidders shall not be required to be present at the bid opening.
(vii) All bid evaluation criteria shall be disclosed in the bidding documents and quantified in monetary terms or expressed in the form of pass/fail requirements.
(viii) No bid may be rejected solely on the basis that the bid price falls outside any standard contract estimate, or margin or bracket of average bids established by the Borrower or the Project Implementing Entity, as the case may be.
(ix) Each contract shall be awarded to the lowest evaluated responsive bidder, that is, the bidder who meets the appropriate standards of capability and resources and whose bid has been determined: (A) to be substantially responsive to the bidding documents; and (B) to offer the lowest evaluated cost. The winning bidder shall not be required, as a condition of award, to undertake responsibilities for work not stipulated in the bidding documents or otherwise to modify the bid as originally submitted.
(x) Each contract financed with the proceeds of the Loan shall provide that the suppliers and contractors shall permit the Bank, at its request, to inspect their accounts and records relating to the performance of the contract and to have said accounts and records audited by auditors appointed by the Bank.
(xi) Government owned enterprises in the Borrower;s Borrower’s country may be permitted to bid or submit a proposal of goods and works if they can establish that they: (iA) are legally and financially autonomous; (iiB) operate under commercial law; and (iiiC) are not a dependent agency Shopping for the procurement of the agency conducting the procurement.
(xii) Re-bidding should not be allowed solely because the number of bids is less than three (3).
(c) Use of force account for civil works shall be permissible only under Part B of the Project when: (i) works are small and scattered or in remote locations for which qualified contractors are unlikely to bid at reasonable price; and (ii) the aggregate value of the works under force account shall not exceed $7,500,000 equivalent.goods
Appears in 1 contract
Samples: Loan Agreement
Other Methods of Procurement of Goods and Works. (a) The following table specifies the methods of procurement, other than International and National Competitive Bidding, which may be used for goods and works. The Procurement Plan shall specify the circumstances under which such methods may be used.
(a) National Competitive Bidding
(ba) Force Account
(c) ShoppingWorks estimated to cost less than
(b) The procedures to be followed for National Competitive Bidding shall be those set forth in the Law on Tendering and Bidding of the People’s Republic of China promulgated by Order No.21 of the President of the People’s Republic of China on August 30, 1999, with the following clarifications required for compliance with the Guidelines:
(i) All invitations to prequalify or to bid shall be advertised in a newspaper of national circulation in the Borrower’s country, except for civil works contracts that are estimated to cost less than $2,000,000 equivalent each and for goods contracts that are estimated to cost less than $300,000 equivalent each, which may be advertised in a provincial daily newspaper. Such advertisement shall be made in sufficient time for prospective bidders to obtain prequalification or bidding documents and prepare and submit their responses. In any event, a minimum of thirty (30) days shall be given to bidders between the date of advertisement in such newspaper and the deadline for submission of bids, and the advertisement and bidding documents shall specify the deadline for such submission.
(ii) Qualification requirements of bidders and the method of evaluating the qualification of each bidder shall be specified in detail in the bidding documents.
(iii) All bidders that meet the qualification criteria set out in the pre- qualification document shall be allowed to bid and there shall be no limit on the number of pre-qualified bidders.
(iv) All bidders shall be required to provide security in an amount sufficient to protect the Borrower or the Project Implementing Entity, as the case may be, in case of breach of contract by the contractor, and the bidding documents shall specify the required form and amount of such security.
(v) Bidders will be allowed to submit bids by mail or by hand. The time for opening of all bids shall be the same as the deadline for receipt of such bids.
(vi) All bids shall be opened in public; all bidders shall be offered an opportunity to be present (either in person or through their representatives) at the time of bid opening, but bidders shall not be required to be present at the bid opening.
(vii) All bid evaluation criteria shall be disclosed in the bidding documents and quantified in monetary terms or expressed in the form of pass/fail requirements.
(viii) No bid may be rejected solely on the basis that the bid price falls outside any standard contract estimate, or margin or bracket of average bids established by the Borrower or the Project Implementing Entity, as the case may beBorrower.
(ixviii) Each contract shall be awarded to the lowest evaluated responsive bidder, that is, the bidder who meets the appropriate standards of capability and resources and whose bid has been determined: (A) to be substantially responsive to the bidding documents; and (B) to offer the lowest evaluated cost. The winning bidder shall not be required, as a condition of award, to undertake responsibilities for work not stipulated in the bidding documents or otherwise to modify the bid as originally submitted.
(xix) Each contract financed with the proceeds of the Loan shall provide that the suppliers and contractors shall permit the Bank, at its request, to inspect their accounts and records relating to the performance of the contract and to have said accounts and records audited by auditors appointed by the Bank.
(xi) Government owned enterprises in the Borrower;s country may be permitted to bid or submit a proposal of goods and works if they can establish that they: (i) are legally and financially autonomous; (ii) operate under commercial law; and (iii) are not a dependent agency of the agency conducting the procurement.
(xiix) Re-bidding should not be allowed solely because the number of bids is less than three (3).
(c) Use of force account for civil works shall be permissible only under Part B of the Project when: (i) works are small and scattered or in remote locations for which qualified contractors are unlikely to bid at reasonable price; and (ii) the aggregate value of the works under force account shall not exceed $7,500,000 equivalent.
Appears in 1 contract
Samples: Loan Agreement
Other Methods of Procurement of Goods and Works. (a) The following table specifies the methods of procurement, other than International and National Competitive Bidding, which may be used for goods and works. The Procurement Plan shall specify the circumstances under which such methods may be used.
(a) National Competitive Bidding
(b) Force Account
(c) Shopping
(b) The . In addition, the procedures to be followed for National Competitive Bidding shall be those set forth in the Law on Tendering and Bidding of the People’s Republic of China promulgated by Order No.21 of the President of the People’s Republic of China on August 30, 1999, with the following clarifications required for compliance with the Procurement Guidelines:
(i) All invitations to prequalify or to bid shall be advertised in a newspaper of national circulation in the Borrower’s country, except for civil works contracts that are estimated cost less than $2,000,000 equivalent each and for goods contracts that are estimated to cost less than $300,000 equivalent each, which may be advertised in a provincial daily newspaper. Such advertisement shall be made in sufficient time for prospective bidders to obtain prequalification or bidding documents and prepare and submit their responses. In any event, a minimum of thirty (30) days shall be given to bidders between the date of advertisement in such newspaper and the deadline for submission of bids, and the advertisement and bidding documents shall specify the deadline for such submission.
(ii) Qualification requirements of bidders and the method of evaluating the qualification of each bidder shall be specified in detail in the bidding documents.
(iii) All bidders that meet the qualification criteria set out in the pre- qualification document shall be allowed to bid and there shall be no limit on the number of pre-qualified bidders.
(iv) All bidders shall be required to provide security in an amount sufficient to protect the Borrower or the Project Implementing Entity, as the case may be, in case of breach of contract by the contractor, and the bidding documents shall specify the required form and amount of such security.
(v) Bidders will be allowed to submit bids by mail or by hand. The time for opening of all bids shall be the same as the deadline for receipt of such bids.
(vi) All bids shall be opened in public; all bidders shall be offered an opportunity to be present (either in person or through their representatives) at the time of bid opening, but bidders shall not be required to be present at the bid opening.
(vii) All bid evaluation criteria shall be disclosed in the bidding documents and quantified in monetary terms or expressed in the form of pass/fail requirements.
(viii) No bid may be rejected solely on the basis that the bid price falls outside any standard contract estimate, or margin or bracket of average bids established by the Borrower or the Project Implementing Entity, as the case may be.
(ix) Each contract shall be awarded to the lowest evaluated responsive bidder, that is, the bidder who meets the appropriate standards of capability and resources and whose bid has been determined: (A) to be substantially responsive to the bidding documents; and (B) to offer the lowest evaluated cost. The winning bidder shall not be required, as a condition of award, to undertake responsibilities for work not stipulated in the bidding documents or otherwise to modify the bid as originally submitted.
(x) Each contract financed with the proceeds of the Loan shall provide that the suppliers and contractors shall permit the Bank, at its request, to inspect their accounts and records relating to the performance of the contract and to have said accounts and records audited by auditors appointed by the Bank.
(xi) Government owned enterprises in the Borrower;s Borrower’s country may be permitted to bid or submit a proposal of goods and works if they can establish that they: (i) are legally and financially autonomous; (ii) operate under commercial law; and (iii) are not a dependent agency of the agency conducting the procurement.
(xii) Re-bidding should not be allowed solely because the number of bids is less than three (3), and rejection of all bids or rebidding shall not take place without the Bank’s prior written concurrence. Shopping
(xiii) The results of bid evaluation and contract award shall be published in the national press or provincial press (as provided under sub-paragraph (i) above) or official gazette or a free and open access website and shall identify the name and offered price of the winning bidder, as well as the duration and summary scope of the awarded contract.
(cxiv) Use of force account Shanxi shall have in place provisions for civil works shall be permissible only under Part B of the Project when: (i) works are small and scattered or in remote locations for which qualified contractors are unlikely bidders to bid at reasonable price; and (ii) the aggregate value of the works under force account shall not exceed $7,500,000 equivalentprotest.
Appears in 1 contract
Samples: Loan Agreement
Other Methods of Procurement of Goods and Works. (a) The following table specifies the methods of procurement, other than International and National Competitive Bidding, which may be used for goods and worksgoods. The Procurement Plan shall specify the circumstances under which such methods may be used.
(a) National Competitive Bidding
(b) Force Account
(c) Shopping
(b) , subject to the following additional procedures: The procedures to be followed for National Competitive Bidding shall be those set forth in the Law on Tendering and Bidding of the People’s Republic of China promulgated by Order No.21 No. 21 of the President of the People’s Republic of China on August 30, 1999, with the following clarifications required for compliance with the Guidelines:
(i) All invitations to prequalify or to bid shall be advertised in a newspaper of national circulation in the BorrowerRecipient’s country, except contracts for civil works contracts that are estimated to cost less than $US$2,000,000 equivalent each and for or goods contracts that are estimated to cost less than $300,000 equivalent each, which may be advertised in a provincial daily newspaper. Such advertisement shall be made in sufficient time for prospective bidders to obtain prequalification or bidding documents and prepare and submit their responses. In any event, a minimum of thirty (30) days shall be given to bidders between the date of advertisement in such newspaper and the deadline for submission of bids, and the advertisement and bidding documents shall specify the deadline for such submission.
(ii) Qualification requirements of bidders and the method of evaluating the qualification of each bidder shall be specified in detail in the bidding documents.
(iii) All bidders that meet the qualification criteria set out in the pre- qualification document shall be allowed to bid and there shall be no limit on the number of pre-qualified bidders.
(iv) All bidders shall be required to provide security in an amount sufficient to protect the Borrower or the Project Implementing Entity, as the case may be, Participants in case of breach of contract by the contractor, and the bidding documents shall specify the required form and amount of such security.
(v) Bidders will be allowed to submit bids by mail or by hand. The time for opening of all bids shall be the same as the deadline for receipt of such bids.
(vi) All bids shall be opened in public; all bidders shall be offered afforded an opportunity to be present (either in person or through their representatives) at the time of bid opening, but bidders shall not be required to be present at the bid opening.
(vii) All bid evaluation criteria shall be disclosed in the bidding documents and quantified in monetary terms or expressed in the form of pass/fail requirements.
(viii) No bid may be rejected solely on the basis that the bid price falls outside any standard contract estimate, or margin or bracket of average bids established by the Borrower or the Project Implementing Entity, as the case may be.
Participants. (ix) Each contract shall be awarded to the lowest evaluated responsive bidder, that is, the bidder who meets the appropriate standards of capability and resources and whose bid has been determined: (A) to be substantially responsive to the bidding documents; and (B) to offer the lowest evaluated cost. The winning bidder shall not be required, as a condition of award, to undertake responsibilities for work not stipulated in the bidding documents or otherwise to modify the bid as originally submitted.
(x) Each contract financed with the proceeds of the Loan shall provide that the suppliers and contractors shall permit the Bank, at its request, to inspect their accounts and records relating to the performance of the contract and to have said accounts and records audited by auditors appointed by the Bank.
(xi) Government owned enterprises in the Borrower;s country may be permitted to bid or submit a proposal of goods and works if they can establish that they: (i) are legally and financially autonomous; (ii) operate under commercial law; and (iii) are not a dependent agency of the agency conducting the procurement.
(xii) Re-bidding should not be allowed solely because the number of bids is less than three (3).
(c) Use of force account for civil works shall be permissible only under Part B of the Project when: (i) works are small and scattered or in remote locations for which qualified contractors are unlikely to bid at reasonable price; and (ii) the aggregate value of the works under force account shall not exceed $7,500,000 equivalent.be
Appears in 1 contract