Other Records. (A) The Generator must prepare and maintain, for the life of each relevant item of Facility Metering Equipment, including each Meter and Measurement Transformer, complete, up-to-date and accurate records as required by the CfD Counterparty from time to time. (B) Such records must include details of the following (including relevant dates and time periods, where applicable): (i) Facility name; (ii) Facility address; (iii) Generator Unique Reference Number; (iv) Meter Serial Number; (v) name of commissioning body (even if the Generator is the commissioning body); (vi) date of commissioning; (vii) name of persons responsible for organising and undertaking commissioning; (viii) reason for commissioning; (ix) Key Meter Technical Details (including any certificate identity); (x) current transformers details (including any certificate identity); (xi) voltage transformers details (including any certificate identity); (xii) circuit name (where more than one); (xiii) calibration results (including individual test errors for each Meter); and (xiv) results of inspections, tests and observations.
Appears in 3 contracts
Samples: Private Network CFD Agreement, Private Network CFD Agreement, Private Network CFD Agreement
Other Records. (A) The Generator must prepare and maintain, for the life of each relevant item of Facility Metering Equipment, including each Meter and Measurement Transformer, complete, up-to-date and accurate records as required by the CfD Counterparty from time to time.
(B) Such records must include details of the following (including relevant dates and time periods, where applicable):
(i) Facility name;
(ii) Facility address;
(iii) Generator Unique Reference Number;
(iv) Meter Serial Number;
(v) name of commissioning body (even if the Generator is the commissioning body);
(vi) date of commissioning;
(vii) name of persons responsible for organising and undertaking commissioning;
(viii) reason for commissioning;
(ix) Key Meter Technical Details (including any certificate identity);
(x) current transformers details (including any certificate identity);
(xi) voltage transformers details (including any certificate identity);
(xii) circuit name (where more than one);
(xiii) calibration results (including individual test errors for each Meter); and
(xiv) results of inspections, tests and observations.
Appendix 1 Metering Records and Forms
Appears in 2 contracts
Samples: Private Network CFD Agreement, Private Network CFD Agreement
Other Records. (A) The Generator must prepare and maintain, for the life of each relevant item of Facility Metering Equipment, including each Meter and Measurement Transformer, complete, up-to-date and accurate records as required by the CfD Counterparty from time to time.
(B) Such records must include details of the following (including relevant dates and time periods, where applicable):
(i) Facility name;
(ii) Facility address;
(iii) Generator Unique Reference Number;
(iv) Meter Serial Number;
(v) name of commissioning body (even if the Generator is the commissioning body);
(vi) date of commissioning;
(vii) name of persons responsible for organising and undertaking commissioning;
(viii) reason for commissioning;
(ix) Key Meter Technical Details (including any certificate identity);
(x) current transformers details (including any certificate identity);
(xi) voltage transformers details (including any certificate identity);
(xii) circuit name (where more than one);
(xiii) calibration results (including individual test errors for each Meter); and
(xiv) results of inspections, tests and observations.
Appendix 1 Metering Records and Forms
1. DETAILS Current Transformer L1 L2 L3 Voltage Transformer L1 L2 L3
2. Ratio Verification