Outage Authority and Coordination. Con Edison may, in accordance with NYISO procedures and Good Utility Practice, remove from service any of its Attachment Facilities or System Upgrade Facilities and System Deliverability Upgrades as necessary to perform maintenance or testing or to install or replace
Appears in 8 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement
Outage Authority and Coordination. Con Edison may, in accordance with NYISO procedures and Good Utility Practice, remove from service any of its Attachment Facilities or System Upgrade Facilities and System Deliverability Upgrades as necessary to perform maintenance or testing or to install or replacereplace equipment. In all circumstances, Con Edison shall use Reasonable Efforts to minimize the effect of such removal.
Appears in 6 contracts
Samples: Interconnection Agreement, Interconnection Agreement, Interconnection Agreement