Outage Notification. (a) CAISO Approval of Outage(s). Seller is responsible for securing CAISO approvals for Project outages, including securing changes in its outage schedules when CAISO disapproves Seller’s schedules or cancels previously approved outages. Seller shall communicate any CAISO-required changes to Buyer in a timely manner, in accordance with the provisions set forth in Appendix IX.
Appears in 10 contracts
Samples: Power Purchase and Sale Agreement, Power Purchase and Sale Agreement, Power Purchase and Sale Agreement
Outage Notification. (a) CAISO Approval of Outage(s). Seller is responsible for securing CAISO approvals for Project outages, including securing changes in its outage schedules when CAISO disapproves Seller’s schedules or cancels previously approved outages. Seller shall communicate any CAISO-required changes to Buyer in a timely manner, in accordance with the provisions set forth in Appendix IXVIII.
Appears in 2 contracts
Outage Notification. (a) CAISO [CAISO] Approval of Outage(s). Seller is responsible for securing CAISO [CAISO] approvals for Project outages, including securing changes in its outage schedules when CAISO [CAISO] disapproves Seller’s schedules or cancels previously approved outages. Seller shall communicate any CAISO-required [CAISO]-required changes to Buyer in a timely manner, in accordance with the provisions set forth in Appendix IX.VIII. [Short Term Offers Outside California: Revise this Section to reflect Transmission Provider]
Appears in 1 contract
Samples: Consent and Agreement
Outage Notification. (a) CAISO Approval of Outage(s). Seller is responsible for securing CAISO approvals for Project outages, including securing changes in its outage schedules when CAISO disapproves Seller’s schedules or cancels previously approved outages. Seller shall communicate any CAISO-required changes to Buyer in a timely manner, in accordance with the provisions set forth in Appendix IXIV.
Appears in 1 contract
Samples: Power Purchase and Sale Agreement