Common use of OUTCOME OF TESTING Clause in Contracts

OUTCOME OF TESTING. The Customer will issue a Satisfaction Certificate when it is satisfied that a Milestone has been Achieved. If any Milestones (or any relevant part thereof) do not pass the Test in respect thereof then: the Supplier shall rectify the cause of the failure and re-submit the Deliverables (or the relevant part) to Testing, provided that the Parties agree that there is sufficient time for that action prior to the relevant Milestone Date; or the Parties shall treat the failure as a Supplier Default.

Appears in 24 contracts

Samples: Call Off Contract, Contract Order Form, Managed Learning Services Call Off Contract

AutoNDA by SimpleDocs

OUTCOME OF TESTING. The Customer will issue a Satisfaction Certificate when it is satisfied that a Milestone has been Achievedachieved. If any Milestones (or any relevant part thereof) do not pass the Test in respect thereof then: the Supplier shall rectify the cause of the failure and re-submit the Deliverables (or the relevant part) to Testing, provided that the Parties agree that there is sufficient time for that action prior to the relevant Milestone Date; or the Parties shall treat the failure as a Supplier Default.

Appears in 5 contracts

Samples: Call Off Terms for Services, Call Off Contract, Call Off Terms for Services

OUTCOME OF TESTING. The Customer will promptly issue a Satisfaction Certificate when it is satisfied that a Milestone has been Achieved. If any Milestones (or any relevant part thereof) do not pass the Test in respect thereof then: the Supplier shall rectify the cause of the failure and re-submit the Deliverables (or the relevant part) to Testing, provided that the Parties agree that there is sufficient time for that action prior to the relevant Milestone Date; or the Parties shall treat the failure as a Supplier Default.

Appears in 4 contracts

Samples: Call Off Contract, Call Off Contract, Call Off Contract

OUTCOME OF TESTING. The Customer will issue a Satisfaction Certificate when it is satisfied that a Milestone has been Achieved. If any Milestones (or any relevant part thereof) do not pass the Test in respect thereof then: the Supplier shall rectify the cause of the failure and re-submit the Deliverables (or the relevant part) to Testing, provided that the Parties agree that there is sufficient time for that action prior to the relevant Milestone Date; or the Parties parties shall treat the failure as a Supplier Default.

Appears in 3 contracts

Samples: Order Form and Call Off Terms, Call Off Agreement, Services Framework Agreement

AutoNDA by SimpleDocs

OUTCOME OF TESTING. 8.1 The Customer will issue a Satisfaction Certificate when it is satisfied that a Milestone has been Achieved. . 8.2 If any Milestones (or any relevant part thereof) do not pass the Test in respect thereof then: : 8.2.1 the Supplier shall rectify the cause of the failure and re-submit the Deliverables (or the relevant part) to Testing, provided that the Parties agree that there is sufficient time for that action prior to the relevant Milestone Date; or or 8.2.2 the Parties shall treat the failure as a Supplier Default.

Appears in 1 contract

Samples: Call Off Agreement