Owner’s Duty to Pay. The Owner has no duty to pay the Contractor except on receipt by the ODR of: 1) a complete Invoice certified by the A/E, and 2) the Contractor’s updated Work Progress Schedule, and 3) confirmation that the Contractor’s as-built documentation at the Site is kept current. 10.3.1 Payment for stored materials and/or equipment confirmed by the Owner and A/E to be on-site or otherwise properly stored is limited to 85 percent of the invoice price or 85 percent of the scheduled value for the materials or equipment, whichever is less.
Appears in 41 contracts
Samples: Design Build Contract, Construction Management Agreement, Construction Management Agreement
Owner’s Duty to Pay. The Owner has no duty to pay the Contractor except on receipt by the ODR of: 1) a complete Invoice Application for Payment certified by the A/E, and ; 2) the Contractor’s updated Work Progress Schedule, ; and 3) confirmation that Contractor has maintained and updated the Contractor’s as-built documentation Record Documents kept at the Site is kept currentSite.
10.3.1 Payment for stored materials and/or equipment confirmed by the Owner and A/E to be on-site or otherwise properly stored is limited to 85 eighty-five (85) percent of the invoice price or 85 eighty- five (85) percent of the scheduled value for the materials or equipment, whichever is less.
Appears in 20 contracts
Samples: Construction Services Agreement, Construction Services Agreement, Construction Manager at Risk Agreement
Owner’s Duty to Pay. The Owner has no duty to pay the Contractor except on receipt by the ODR of: 1) a complete Invoice certified by the A/E, and 2) the Contractor’s updated Work Progress Schedule, and 3) confirmation that Contractor has maintained and updated the Contractor’s as-built documentation at the Site is kept currentdigital Record Documents.
10.3.1 Payment for stored materials and/or equipment confirmed by the Owner and A/E to be on-site or otherwise properly stored is limited to 85 percent of the invoice price or 85 percent of the scheduled value for the materials or equipment, whichever is less.
Appears in 7 contracts
Samples: Construction Manager at Risk Agreement, Construction Manager at Risk Agreement, Construction Contract
Owner’s Duty to Pay. The Owner has no duty to pay the Contractor except on receipt by the ODR of: 1) a complete Invoice Application for Payment certified by the A/E, and ; 2) the Contractor’s updated Work Progress Schedule, ; and 3) confirmation that the Contractor’s as-built record documentation at the Site is kept current.
10.3.1 Payment for stored materials and/or equipment confirmed by the Owner and A/E to be on-site or otherwise properly stored is limited to 85 eighty-five (85) percent of the invoice price or 85 eighty-five (85) percent of the scheduled value for the materials or equipment, whichever is less.
Appears in 6 contracts
Samples: General Construction Services Contract, General Construction Services Contract, Construction Manager at Risk Contract
Owner’s Duty to Pay. The Owner has no duty to pay the Contractor except on receipt by the ODR of: 1) a complete Invoice Application for Payment certified by the A/E, and ; 2) the Contractor’s updated Work Progress Schedule, ; and 3) confirmation that Contractor has maintained and updated the Contractor’s as-built documentation Record Documents kept at the Site is kept currentSite.
10.3.1 9.3.1 Payment for stored materials and/or equipment confirmed by the Owner and A/E to be on-site or otherwise properly stored is limited to 85 eighty-five (85) percent of the invoice price or 85 eighty- five (85) percent of the scheduled value for the materials or equipment, whichever is less.
Appears in 1 contract
Samples: Standard Agreement
Owner’s Duty to Pay. The Owner has no duty to pay the Contractor except on receipt by the ODR of: ; 1) a complete Invoice certified by the A/E, AE and 2) the Contractor’s updated Work Progress Schedule, and 3) confirmation that the Contractor’s as-built documentation at the Site site is kept current.
10.3.1 Payment for stored materials and/or equipment confirmed by the Owner and A/E AE to be on-on- site or otherwise properly stored is may be limited to 85 percent of the invoice price or 85 percent of the scheduled value for the materials or equipment, whichever is less.
Appears in 1 contract
Samples: Contract