Common use of OWNER’S RIGHT TO CARRY OUT THE WORK Clause in Contracts

OWNER’S RIGHT TO CARRY OUT THE WORK. If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within a seven day period after receipt of written notice from the Owner to commence and continue correction of such default or neglect with diligence and promptness, the Owner may, without prejudice to other remedies, correct such deficiencies. In such case, the Contract Sum shall be adjusted to deduct the cost of correction from payments due the Contractor. If payments then or thereafter due the Contractor are not sufficient to cover such amounts, the Contractor shall pay the difference to the Owner immediately upon Owner’s written demand.

Appears in 15 contracts

Samples: www.unlv.edu, www.unlv.edu, www.unlv.edu

AutoNDA by SimpleDocs
Time is Money Join Law Insider Premium to draft better contracts faster.