Payment of Damages. 19.8.1 The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.1, after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.
Appears in 26 contracts
Samples: Draft Contract Agreement, Contract Agreement, Epc Agreement
Payment of Damages. 19.8.1 17.6.1 The Contractor as well as the Authority may claim Damages due and payable to it in accordance with the provisions of this Agreement.
19.8.2 17.6.2 The Authority’s Authority Engineer shall verify and check the claim and issue the IPC within 15 20 (fifteentwenty) days of the receipt of the claim under Clause 19.8.117.6.1, after making adjustments adjustments, in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC suchIPC within a period of 30 (thirty30(thirty) days from the date of the submission of the claim under this Clause 19.817.6. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 17.7 shall apply mutatis mutandis thereto.
Appears in 7 contracts
Samples: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement
Payment of Damages. 19.8.1 The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement.
19.8.2 The Authority’s Authority‟s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.1, after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.
Appears in 6 contracts
Samples: Epc Agreement, Construction Contract, Epc Agreement
Payment of Damages. 19.8.1 17.6.1 The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement.
19.8.2 17.6.2 The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.117.6.1, after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any such IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.817.6. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 17.7 shall apply mutatis mutandis thereto.
Appears in 4 contracts
Samples: Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects
Payment of Damages. 19.8.1 The Contractor as well as the Authority may claim Damages due and payable to it in accordance with the provisions of this Agreement.
19.8.2 . The Authority’s Authority Engineer shall verify and check the claim and issue the IPC within 15 20 (fifteentwenty) days of the receipt of the claim under Clause 19.8.117.6.1, after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any such IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.817.6. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 17.7 shall apply mutatis mutandis thereto.
Appears in 4 contracts
Samples: Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement
Payment of Damages. 19.8.1 The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement.
19.8.2 The AuthorityEmployer’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.1, after making adjustments in accordance with the provisions of this Agreement. The Authority Employer shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority Employer to make payment to the Contractor within the specified time, the Authority Employer shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.
Appears in 3 contracts
Samples: Demonstration Agreement, Epc Agreement, Contract Agreement for Design and Construction
Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement.
19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.apply
Appears in 3 contracts
Samples: Engineering Procurement and Construction (Epc) Agreement, Engineering Procurement and Construction (Epc) Agreement, Engineering Procurement and Construction (Epc) Agreement
Payment of Damages. 19.8.1 17.6.1 The Contractor as well as the Authority may claim Damages due and payable to it in accordance with the provisions of this Agreement.
19.8.2 17.6.2 The Authority’s Authority Engineer shall verify and check the claim and issue the IPC within 15 20 (fifteentwenty) days of the receipt of the claim under Clause 19.8.117.6.1, after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any such IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.817.6. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 17.7 shall apply mutatis mutandis thereto.
Appears in 3 contracts
Samples: Epc Agreement, Epc Agreement, Engineering, Procurement and Construction (Epc) Agreement
Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement.
19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days thirty)days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.
Appears in 2 contracts
Samples: Construction Contract, Construction Contract
Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement.
19.8.2 (ii) The Authority’s 's Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.
Appears in 2 contracts
Samples: Construction Contract, Construction Contract
Payment of Damages. 19.8.1 The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement.
19.8.2 The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.1, after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.apply
Appears in 2 contracts
Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement.
19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.
Appears in 2 contracts
Samples: Engineering Procurement and Construction (Epc) Agreement, Engineering Procurement and Construction Agreement
Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this AgreementthisAgreement.
19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay liabletopay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.
Appears in 2 contracts
Samples: Construction Contract, Engineering Procurement and Construction (Epc) Agreement
Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement.
19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay topay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.
Appears in 1 contract
Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement.
19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of submissionof the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon there on and the provisions of Clause 19.9 shall apply mutatis mutandis mutatismut and is thereto.
Appears in 1 contract
Samples: Construction Contract
Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with under the provisions of this Agreement.
19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with under the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.
Appears in 1 contract
Samples: Engineering Procurement and Construction (Epc) Agreement
Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement.
19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.to
Appears in 1 contract
Samples: Engineering Procurement and Construction (Epc) Contract
Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions provi- sions of this Agreement.
19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under un- der this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor Contrac- tor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.
Appears in 1 contract
Samples: Construction Contract
Payment of Damages. 19.8.1 The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement.
19.8.2 The Authority’s Employer‟s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.1, after making adjustments in accordance with the provisions of this Agreement. The Authority Employer shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority Employer to make payment to the Contractor within the specified time, the Authority Employer shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.
Appears in 1 contract