Common use of Payment of Damages Clause in Contracts

Payment of Damages. 19.8.1 The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.1, after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.

Appears in 26 contracts

Samples: Draft Contract Agreement, Contract Agreement, Epc Agreement

AutoNDA by SimpleDocs

Payment of Damages. 19.8.1 17.6.1 The Contractor as well as the Authority may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 17.6.2 The Authority’s Authority Engineer shall verify and check the claim and issue the IPC within 15 20 (fifteentwenty) days of the receipt of the claim under Clause 19.8.117.6.1, after making adjustments adjustments, in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC suchIPC within a period of 30 (thirty30(thirty) days from the date of the submission of the claim under this Clause 19.817.6. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 17.7 shall apply mutatis mutandis thereto.

Appears in 7 contracts

Samples: Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement, Standard Engineering, Procurement and Construction (Epc) Agreement

Payment of Damages. 19.8.1 The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 The Authority’s Authority‟s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.1, after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.

Appears in 6 contracts

Samples: Epc Agreement, Construction Contract, Epc Agreement

Payment of Damages. 19.8.1 17.6.1 The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 17.6.2 The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.117.6.1, after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any such IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.817.6. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 17.7 shall apply mutatis mutandis thereto.

Appears in 4 contracts

Samples: Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects, Standard Engineering, Procurement and Construction (Epc) Agreement for Railway Projects

Payment of Damages. 19.8.1 The Contractor as well as the Authority may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 . The Authority’s Authority Engineer shall verify and check the claim and issue the IPC within 15 20 (fifteentwenty) days of the receipt of the claim under Clause 19.8.117.6.1, after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any such IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.817.6. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 17.7 shall apply mutatis mutandis thereto.

Appears in 4 contracts

Samples: Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement, Engineering, Procurement and Construction (Epc) Agreement

Payment of Damages. 19.8.1 The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 The AuthorityEmployer’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.1, after making adjustments in accordance with the provisions of this Agreement. The Authority Employer shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority Employer to make payment to the Contractor within the specified time, the Authority Employer shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.

Appears in 3 contracts

Samples: Demonstration Agreement, Epc Agreement, Contract Agreement for Design and Construction

Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.apply

Appears in 3 contracts

Samples: Engineering Procurement and Construction (Epc) Agreement, Engineering Procurement and Construction (Epc) Agreement, Engineering Procurement and Construction (Epc) Agreement

Payment of Damages. 19.8.1 17.6.1 The Contractor as well as the Authority may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 17.6.2 The Authority’s Authority Engineer shall verify and check the claim and issue the IPC within 15 20 (fifteentwenty) days of the receipt of the claim under Clause 19.8.117.6.1, after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any such IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.817.6. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 17.7 shall apply mutatis mutandis thereto.

Appears in 3 contracts

Samples: Epc Agreement, Epc Agreement, Engineering, Procurement and Construction (Epc) Agreement

Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days thirty)days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.

Appears in 2 contracts

Samples: Construction Contract, Construction Contract

Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 (ii) The Authority’s 's Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.

Appears in 2 contracts

Samples: Construction Contract, Construction Contract

Payment of Damages. 19.8.1 The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.1, after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.apply

Appears in 2 contracts

Samples: Draft Contract Agreement, Draft Contract Agreement

Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.

Appears in 2 contracts

Samples: Engineering Procurement and Construction (Epc) Agreement, Engineering Procurement and Construction Agreement

AutoNDA by SimpleDocs

Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this AgreementthisAgreement. 19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay liabletopay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.

Appears in 2 contracts

Samples: Construction Contract, Engineering Procurement and Construction (Epc) Agreement

Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay topay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.

Appears in 1 contract

Samples: Engineering Procurement and Construction Agreement

Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of submissionof the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon there on and the provisions of Clause 19.9 shall apply mutatis mutandis mutatismut and is thereto.

Appears in 1 contract

Samples: Construction Contract

Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with under the provisions of this Agreement. 19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with under the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.

Appears in 1 contract

Samples: Engineering Procurement and Construction (Epc) Agreement

Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.to

Appears in 1 contract

Samples: Engineering Procurement and Construction (Epc) Contract

Payment of Damages. 19.8.1 (i) The Contractor may claim Damages due and payable to it in accordance with the provisions provi- sions of this Agreement. 19.8.2 (ii) The Authority’s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.119.8 (i), after making adjustments in accordance with the provisions of this Agreement. The Authority shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under un- der this Clause 19.8. In the event of the failure of the Authority to make payment to the Contractor within the specified time, the Authority shall be liable to pay to the Contractor Contrac- tor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.

Appears in 1 contract

Samples: Construction Contract

Payment of Damages. 19.8.1 The Contractor may claim Damages due and payable to it in accordance with the provisions of this Agreement. 19.8.2 The Authority’s Employer‟s Engineer shall issue the IPC within 15 (fifteen) days of the receipt of the claim under Clause 19.8.1, after making adjustments in accordance with the provisions of this Agreement. The Authority Employer shall pay to the Contractor the amount due under any IPC within a period of 30 (thirty) days from the date of the submission of the claim under this Clause 19.8. In the event of the failure of the Authority Employer to make payment to the Contractor within the specified time, the Authority Employer shall be liable to pay to the Contractor interest thereon and the provisions of Clause 19.9 shall apply mutatis mutandis thereto.

Appears in 1 contract

Samples: Epc Agreement