Common use of Payment Schedule and Associated ITCC Clause in Contracts

Payment Schedule and Associated ITCC. The payment amounts shown below are based on an estimate of the costs expected to be incurred for the Distribution Upgrades, New Interconnection Facilities, and Network Upgrades. Payment No. Payment Due Date New Interconnection Facilities Cost Distribution Upgrades Cost Reliability Network Upgrades Cost Delivery Network Upgrades Cost One- Time Cost Project Payment Associated ITCC* 1 Within 30 $184,551 $0 $0 $0 $0 184,551 $64,593 Calendar Days after the Effective Date Total $184,551 $0 $0 $0 $0 184,551 $64,593 All amounts shown above are in nominal dollars. Interconnection Facilities Payment = ( New Interconnection Facilities Cost + associated One-Time Cost) = $184,551 Distribution Upgrades Payment = (Distribution Upgrades Cost + associated One-Time Cost) = $0 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) = $0 Transmission credits pursuant to Section 9 of this Appendix A = Reliability Network Upgrades Payment + Delivery Network Upgrades Payment = $0 *ITCC will be provided by Interconnection Customer in accordance with Section 11 of this Appendix A. 1. The Interconnection Customer’s Selected Option: Pursuant to Article 5.1 of the GIA, the Interconnection Customer has selected the Standard Option. 2. Milestone Dates: Item Milestone Responsible Party Due Date (a) Pursuant to Appendix C Section 3(b) provide a complete and updated one line diagram of its facilities identifying any connections to-or-from the Interconnection Facilities to IP. Interconnection Customer Within thirty (30) Calendar Days after the Agreement is fully executed. (b) Pursuant to Appendix C Section 3(b) submit for Distribution Provider’s approval, switching procedures to disconnect IP. Interconnection Customer Within thirty (30) Calendar Days after the Agreement is fully executed (c) Submit proof of insurance coverage in accordance with Article 18.3 of the GIA Interconnection Customer Within ten (10) Calendar Days after the Effective Date (d) Submittal of written authorization to proceed with design and procurement of the New Interconnection Facilities to the Distribution Provider, in accordance with Article 5.5.2 of the GIA Interconnection Customer Within thirty (30) Calendar Days after the Effective Date (e) Submittal of written authorization to proceed with construction to the Distribution Provider, pursuant to Article 5.6.3 of the GIA Interconnection Customer Within thirty (30) Calendar Days after the Effective Date (f) Submittal of security for the estimated tax liability to the Distribution Provider, pursuant to Article 5.17.3 and Section 11 of Appendix A of the GIA Interconnection Customer Within thirty (30) Calendar Days after the Effective Date (g) Completion of the New Interconnection Facilities Distribution Provider Within eighteen (18) months following the Effective Date* (h) Submittal of the steam turbine disconnection plan pursuant to Interconnection Customer Within thirty (30) Calendar Days after the Item Milestone Responsible Party Due Date Article 6.4 and Attachment C Section 3(j) of this GIA Effective Date (i) Submittal of initial specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility, including System Protection Facilities, to the Distribution Provider, pursuant to Article 5.10.1 of the GIA Interconnection Customer Deemed to have been completed under the IFA (j) Submittal of initial information including the Distribution Provider’s Transmission System information necessary to allow the Interconnection Customer to select equipment, in accordance with Article 24.2 of the GIA Distribution Provider Deemed to have been completed under the IFA with respect to the Existing Interconnection Facilities; within thirty (30) Calendar Days after the Effective Date with respect to the New Interconnection Facilities

Appears in 1 contract

Samples: Generator Interconnection Agreement

AutoNDA by SimpleDocs

Payment Schedule and Associated ITCC. The payment amounts shown below are based on an estimate of the monthly incurred costs expected to be incurred for the Distribution Upgrades, New Distribution Provider’s Interconnection Facilities, and Network Upgrades. Payment No. Payment Due Date New Within 30 calendar days of the Effective Date Interconnection Facilities Cost $143,700 Distribution Upgrades Cost $0 Reliability Network Upgrades Cost $0 Delivery Network Upgrades Cost $0 One- Time Cost $0 Project Payment $143,700 Associated ITCC* 1 Within 30 $184,551 $0 $0 $0 $0 184,551 $64,593 Calendar Days after the Effective Date Total $184,551 $0 $0 $0 $0 184,551 $64,593 50,300 All amounts shown above are in nominal dollars. Interconnection Facilities Payment = ( New Interconnection Facilities Cost + associated One-Time Cost) = $184,551 Distribution Upgrades Payment = (Distribution Upgrades Cost + associated One-Time Cost) = $0 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) =$0 Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) =$143,700 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0 Transmission credits pursuant to Section 9 of this Appendix A Attachment 2 = Reliability Network Upgrades Payment + Delivery Network Upgrades Payment = $0 *ITCC will be provided by Interconnection Customer in accordance with Section 11 of this Appendix A. 1. The Interconnection Customer’s Selected Option: Pursuant to Article 5.1 of the GIA, the Interconnection Customer has selected the Standard Option. Attachment 2. Milestone DatesOne-line Diagram Depicting the Small Generating Facility, Interconnection Facilities, Metering Equipment, and Upgrades In-Service Date: May 31, 2013 Critical milestones and responsibility as agreed to by the Parties: Item Milestone Responsible Party Due Date (a) Pursuant to Appendix C Section 3(b) provide a complete and updated one line diagram of its facilities identifying any connections to-or-from the Interconnection Facilities to IP. Interconnection Customer Within thirty (30) Calendar Days after the Agreement is fully executed. (b) Pursuant to Appendix C Section 3(b) submit for Distribution Provider’s approval, switching procedures to disconnect IP. Interconnection Customer Within thirty (30) Calendar Days after the Agreement is fully executed (c) Submit proof of insurance coverage in accordance with Article 18.3 8.1 of the GIA SGIA Interconnection Customer Within ten (10) Calendar Days after the Effective Date (d) Submittal of written authorization to proceed with design and procurement calendar days of the New Interconnection Facilities to the Distribution Provider, in accordance with Article 5.5.2 execution of the GIA Interconnection Customer Within thirty this SGIA (30) Calendar Days after the Effective Date (e) Submittal of written authorization to proceed with construction to the Distribution Provider, pursuant to Article 5.6.3 of the GIA Interconnection Customer Within thirty (30) Calendar Days after the Effective Date (fb) Submittal of security for the estimated tax liability to the Distribution Provider, pursuant to Article 5.17.3 and Section 11 of Appendix A Attachment 2 of the GIA SGIA Interconnection Customer Within thirty (30) Calendar Days after calendar days of the Effective Date Date (g) Completion of the New Interconnection Facilities Distribution Provider Within eighteen (18) months following the Effective Date* (h) Submittal of the steam turbine disconnection plan pursuant to Interconnection Customer Within thirty (30) Calendar Days after the Item Milestone Responsible Party Due Date Article 6.4 and Attachment C Section 3(j) of this GIA Effective Date (ic) Submittal of initial specifications for the Interconnection Customer’s Interconnection Facilities and Small Generating Facility, including System Protection Facilitiessystem protection facilities, to the Distribution Provider, pursuant to Article 5.10.1 Provider Interconnection Customer Within (30) calendar days of the GIA Interconnection Customer Deemed to have been completed under the IFA Effective Date (jd) Submittal of initial information including payment number 1 pursuant to Section 17 of Attachment 2 of the Distribution Provider’s Transmission System information necessary to allow the SGIA Interconnection Customer to select equipment, in accordance with Article 24.2 of the GIA Distribution Provider Deemed to have been completed under the IFA with respect to the Existing Interconnection Facilities; within Within thirty (30) Calendar Days after calendar days of the Effective Date with respect to (e) Provide panel drawings, easements/lease agreements, grading plans, sewer and storm plot plans, landscape, sprinkler and pedestal locations (“Required Information”) Interconnection Customer Within thirty (30) calendar days of the New Effective Date (f) Review of and comment on the Interconnection FacilitiesCustomer’s initial specifications Distribution Provider Within thirty (30) calendar days of the Interconnection Customer’s submission of initial specifications (g) Design of Distribution Provider’s Interconnection Facilities and Distribution Upgrades Distribution Provider Within sixty (60) business days following the Effective Date assuming Item (e) of this Attachment 4 has occurred timely

Appears in 1 contract

Samples: Small Generator Interconnection Agreement (Sgia)

Payment Schedule and Associated ITCC. The payment amounts shown below are based on an estimate of the costs expected to be incurred for the Distribution Upgrades, New Distribution Provider’s Interconnection Facilities, and Network Upgrades. Payment No. Payment Due Date New Interconnection Facilities Cost Distribution Upgrades Cost Reliability Network Upgrades Cost Delivery Network Upgrades Cost One- Time Cost Project Payment Associated ITCC* 1 Within 30 Calendar Days for Effective Date $184,551 190,200 $0 $0 $0 $0 184,551 $64,593 Calendar Days after the Effective Date 190,200 $66,570 Total $184,551 190,200 $0 $0 $0 $0 184,551 $64,593 190,200 $66,570 All amounts shown above are in nominal dollars. Interconnection Facilities Payment = ( New (Interconnection Facilities Cost + associated One-Time Cost) = $184,551 190,200 Distribution Upgrades Payment = (Distribution Upgrades Cost + associated One-Time Cost) = $0 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) = $0 Transmission credits pursuant to Section 9 of this Appendix A Attachment 2 = Reliability Network Upgrades Payment + Delivery Network Upgrades Payment = $0 *ITCC will be provided by Interconnection Customer in accordance with Section 11 of this Appendix A. 1. The Interconnection Customer’s Selected Option: Pursuant to Article 5.1 of the GIA, the Interconnection Customer has selected the Standard Option. Attachment 2. Milestone DatesIn-Service Date: Item Milestone Responsible Party Due DateAugust 31, 2014 Critical milestones and responsibility as agreed to by the Parties: (a) Pursuant to Appendix C Section 3(b) provide a complete and updated one line diagram of its facilities identifying any connections to-or-from the Interconnection Facilities to IP. Interconnection Customer Within thirty (30) Calendar Days after the Agreement is fully executed. (b) Pursuant to Appendix C Section 3(b) submit for Distribution Provider’s approval, switching procedures to disconnect IP. Interconnection Customer Within thirty (30) Calendar Days after the Agreement is fully executed (c) Submit proof of insurance coverage in accordance with Article 18.3 8.1 of the GIA Interconnection Customer Within ten (10) Calendar Days calendar days after the Effective Date (db) Submittal of written authorization to proceed with design Credit Support for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades and procurement of the New Interconnection Facilities Network Upgrades to the Distribution Provider, in accordance with Article 5.5.2 Provider pursuant to Section 10 of Attachment 2 of the GIA Interconnection Customer Within thirty (30) Calendar Days calendar days after the Effective Date (e) Submittal of written authorization to proceed with construction to the Distribution Provider, pursuant to Article 5.6.3 of the GIA Interconnection Customer Within thirty (30) Calendar Days after the Effective Date (fc) Submittal of security for the estimated tax liability to the Distribution Provider, pursuant to Article 5.17.3 and Section 11 of Appendix A Attachment 2 of the GIA Interconnection Customer Within thirty (30) Calendar Days calendar days after the Effective Date (d) Provide the following information (“Required Information”) in support of the Distribution Provider’s engineering and design of the Distribution Provider’s Interconnection Facilities and Distribution Upgrades: 1) a completed Distribution Provider provided Interconnection Customer information sheet, 2) a unique address for the project, 3) public right-of- way (street) base maps as required by the interconnection, 4) street improvement plans, 5) site plot plan on a 30:1 scale or digital file, 6) grading plans, 7) sewer and storm plot plans, 8) landscape, sprinkler and pedestal locations, 9) proposed location for the RTU, if applicable, 10) easements/lease agreements, and 11) panel drawings Interconnection Customer Within thirty (30) calendar days after the Effective Date (e) Completion of the Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction Distribution Provider Within ninety (90) calendar days of Distribution Provider’s receipt of the Required Information (f) Provide to the Interconnection Customer: 1) an updated scope of work and design for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction; 2) an updated cost estimate and schedule related to the Distribution Provider’s Interconnection Facilities and Distribution Upgrades, as applicable, if there are any material changes resulting from completion of the Distribution Provider’s detailed design of Distribution Provider’s Interconnection Facilities and Distribution Upgrades, and 3) comment on Interconnection Customer’s proposed location for the RTU, if applicable Distribution Provider Within five (5) calendar days following completion of Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and Civil Construction (g) Completion of the New Civil Construction, including Distribution Provider’s release, in accordance with Section 1 of Attachment 2 and Section 3 of Attachment 5 of the GIA Interconnection Facilities Customer Within sixty (60) calendar days after the Distribution Provider Within eighteen (18) months following provides the Effective Date*design for the Civil Construction to the Interconnection Customer (h) Submittal of the steam turbine disconnection plan pursuant to Interconnection Customer Within thirty (30) Calendar Days after the Item Milestone Responsible Party Due Date Article 6.4 and Attachment C Section 3(j) of this GIA Effective Date (i) Submittal of initial final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility, including System Protection Facilitiessystem protection facilities, to the Distribution Provider Interconnection Customer At least ninety (90) calendar days prior to completion of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, and Network Upgrades (i) Review of and comment on the Interconnection Customer’s final specifications Distribution Provider Within forty-five (45) calendar days following the Interconnection Customer’s submittal of the final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility (j) Notification of testing and inspection of Interconnection Customer’s Interconnection Facilities pursuant to Article 5.10.1 2.1.1 of the GIA Interconnection Customer Deemed Within five (5) Business Days prior to have been completed under the IFA (j) Submittal of initial information including the Distribution Provider’s Transmission System information necessary to allow the Interconnection Customer to select equipment, in accordance with Article 24.2 of the GIA Distribution Provider Deemed to have been completed under the IFA with respect to the Existing Interconnection Facilities; within thirty (30) Calendar Days after the Effective Date with respect to the New Interconnection Facilitiessuch testing and inspection

Appears in 1 contract

Samples: Generator Interconnection Agreement

Payment Schedule and Associated ITCC. The payment amounts shown below are based on an estimate of the monthly incurred costs expected to be incurred for the Distribution Upgrades, New Distribution Provider’s Interconnection Facilities, and Network Upgrades. Payment No. Payment Due Date New Interconnection Facilities Cost Distribution Upgrades Cost Reliability Network Upgrades Cost Delivery Network Upgrades Cost One- Time Cost Project Payment Associated ITCC* 1 Within 30 $184,551 $0 $0 $0 $0 184,551 $64,593 Calendar Days after the Effective Date Total $184,551 $0 $0 $0 $0 184,551 $64,593 All amounts shown above are in nominal dollars. Interconnection Facilities Payment = ( New Interconnection Facilities Cost + associated One-Time Cost) = $184,551 Distribution Upgrades Payment = (Distribution Upgrades Cost + associated One-Time Cost) = $1,407,359 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) =$0 Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) =$4,008,336 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) = $0 1,266,201 Transmission credits pursuant to Section 9 of this Appendix A = Reliability Network Upgrades Payment + Delivery Network Upgrades Payment = $0 1,266,201 *ITCC will be provided by Interconnection Customer in accordance with Section 11 of this Appendix A. 1. The Interconnection Customer’s Selected Option: Pursuant to Article 5.1 of the GIACLGIA, the Interconnection Customer has selected the Standard Option. 2. Milestone Dates: Item Milestone Responsible Party Due Date: (a) Pursuant to Appendix C Section 3(b) provide a complete and updated one line diagram of its facilities identifying any connections to-or-from the Interconnection Facilities to IP. Interconnection Customer Within thirty (30) Calendar Days after the Agreement is fully executed. (b) Pursuant to Appendix C Section 3(b) submit for Distribution Provider’s approval, switching procedures to disconnect IP. Interconnection Customer Within thirty (30) Calendar Days after the Agreement is fully executed (c) Submit proof of insurance coverage in accordance with Article 18.3 of the GIA CLGIA Interconnection Customer Within ten (10) Calendar Days after the Effective Date (db) Submittal of written authorization to proceed with design and procurement of the New Distribution Provider’s Interconnection Facilities Facilities, Distribution Upgrades and Network Upgrades to the Distribution Provider, in accordance with Article 5.5.2 of the GIA CLGIA Interconnection Customer Within thirty (30) Calendar Days after the Effective Date (c) Submittal of second posting of Distribution Provider’s Distribution Upgrades to the Distribution Provider, pursuant to Section 8 of the CLGIP and Section 10 of Appendix A of the CLGIA Interconnection Customer June 21, 2013 (d) Submittal of third posting of Credit Support for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades and Network Upgrades to the Distribution Provider, pursuant to Section 8 of the CLGIP and Section 10 of Appendix A of the CLGIA Interconnection Customer On or before the start of construction of Network Upgrades or Distribution Provider’s Interconnection Facilities (whichever is earlier). August 1, 2013 (e) Submittal of written authorization to proceed with construction to the Distribution Provider, pursuant to Article 5.6.3 of the GIA CLGIA Interconnection Customer Within thirty (30) Calendar Days after the Effective Date (f) Submittal of security for the estimated tax liability to the Distribution Provider, pursuant to Article 5.17.3 and Section 11 of Appendix A of the GIA CLGIA Interconnection Customer Within thirty (30) Calendar Days after the Effective Date (g) Completion of the New Distribution Provider’s Interconnection Facilities Facilities, Distribution Upgrades, and Network Upgrades Distribution Provider Within eighteen (1824) months following the Effective Date* (h) Submittal of the steam turbine disconnection plan pursuant to Interconnection Customer Within thirty (30) Calendar Days after the Item Milestone Responsible Party Due Date Article 6.4 and Attachment C Section 3(j) of this GIA Effective Date (i) Submittal of initial specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility, including System Protection Facilities, to the Distribution Provider, pursuant to Article 5.10.1 of the GIA CLGIA Interconnection Customer Deemed At least one hundred eighty (180) Calendar Days prior to have been completed under the IFA Initial Synchronization Date (ji) Submittal of initial information including the Distribution Provider’s Transmission System information necessary to allow the Interconnection Customer to select equipment, in accordance with Article 24.2 of the GIA CLGIA Distribution Provider Deemed At least one hundred eighty (180) Calendar Days prior to have been completed under Trial Operation (j) Submittal of updated information by the IFA Interconnection Customer, including manufacturer information, in accordance with respect Article 24.3 of the CLGIA Interconnection Customer No later than one hundred eighty (180) Calendar Days prior to Trial Operation (k) Review of and comment on the Existing Interconnection Facilities; within Customer’s initial specifications, pursuant to Article 5.10.1 of the CLGIA Distribution Provider Within thirty (30) Calendar Days after the Effective Date with respect to the New Interconnection FacilitiesCustomer’s submission of initial specifications

Appears in 1 contract

Samples: Clustering Large Generator Interconnection Agreement (Clgia)

AutoNDA by SimpleDocs

Payment Schedule and Associated ITCC. The payment amounts shown below are based on an estimate of the monthly incurred costs expected to be incurred for the new Distribution Upgrades, New Distribution Provider’s Interconnection Facilities, and Network Upgrades. Payment No. Payment Due Date New Customer- Financed Interconnection Facilities Cost Distribution Upgrades Cost Reliability Network Upgrades Cost Delivery Network Upgrades Cost One- Time Cost Project Payment Associated ITCC* 1 Within 30 calendar days of the Effective Date $184,551 168,000 $0 $0 $0 $0 184,551 $64,593 Calendar Days after the Effective Date 168,000 $58,800 Total $184,551 168,000 $0 $0 $0 $0 184,551 $64,593 168,000 $58,800 All amounts shown above are in nominal dollars. Interconnection Facilities Payment = ( New Interconnection Facilities Cost + associated One-Time Cost) = $184,551 Distribution Upgrades Payment = (Distribution Upgrades Cost + associated One-Time Cost) = $0 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) =$0 Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) =$168,000 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0 Transmission credits pursuant to Section 9 of this Appendix A = Reliability Network Upgrades Payment + Delivery Network Upgrades Payment = $0 Payment for the installation of existing facilities was made by the Interconnection Customer under the IFA. *ITCC will be provided by Interconnection Customer in accordance with Section 11 of this Appendix A. 1A. 18. The Review of Generating Facility and Interconnection Customer’s Selected Option: Interconnection Facilities Design. Pursuant to Article 5.1 5.10 of the this GIA, the Interconnection Customer has selected the Standard Option. 2. Milestone Dates: Item Milestone Responsible Party Due Date (a) Pursuant to Appendix C Section 3(b) provide a complete and updated one line diagram of its facilities identifying any connections to-or-from the Interconnection Facilities to IP. Interconnection Customer Within thirty (30) Calendar Days after the Agreement is fully executed. (b) Pursuant to Appendix C Section 3(b) submit for Distribution Provider’s approval, switching procedures to disconnect IP. Interconnection Customer Within thirty (30) Calendar Days after the Agreement is fully executed (c) Submit proof of insurance coverage in accordance with Article 18.3 of the GIA Interconnection Customer Within ten (10) within 120 Calendar Days after the Effective Date (d) Submittal of written authorization to proceed with design , the Interconnection Customer shall provide all drawings, specifications, information and procurement of the New Interconnection Facilities documents related to the Distribution Provider, in accordance with Article 5.5.2 of the GIA Interconnection Customer Within thirty (30) Calendar Days after the Effective Date (e) Submittal of written authorization to proceed with construction to the Distribution Provider, pursuant to Article 5.6.3 of the GIA Interconnection Customer Within thirty (30) Calendar Days after the Effective Date (f) Submittal of security for the estimated tax liability to the Distribution Provider, pursuant to Article 5.17.3 Generating Facility and Section 11 of Appendix A of the GIA Interconnection Customer Within thirty (30) Calendar Days after the Effective Date (g) Completion of the New Interconnection Facilities Distribution Provider Within eighteen (18) months following the Effective Date* (h) Submittal of the steam turbine disconnection plan pursuant to Interconnection Customer Within thirty (30) Calendar Days after the Item Milestone Responsible Party Due Date Article 6.4 and Attachment C Section 3(j) of this GIA Effective Date (i) Submittal of initial specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility, including System Protection Facilities, to necessary for the Distribution Provider, pursuant Provider to Article 5.10.1 verify the compatibility of the GIA Generating Facility and Interconnection Customer Deemed to have been completed under the IFA (j) Submittal of initial information including Customer’s Interconnection Facilities with the Distribution Provider’s Interconnection Facilities, Distribution System and Transmission System, and compliance with the Interconnection Handbook. Such drawings, specifications, information and documents shall include, but are not limited to: i) an electrical one-line diagram of the Generating Facility and Interconnection Customer’s Interconnection Facilities; ii) an electrical three-line diagram of the Interconnection Customer’s protective relays and devices used for protection of the Distribution Provider’s Interconnection Facilities, Distribution System and Transmission System; iii) electrical elementary or wiring diagrams of the Interconnection Customer’s protective relays and devices used for protection of the Distribution Provider’s Interconnection Facilities, Distribution System and Transmission System; iv) protection settings of the Interconnection Customer’s relays or other protective devices used for protection of the Distribution Provider’s Interconnection Facilities, Distribution System and Transmission System, including a test report for such relays or other protective devices dated within 5 years of the Effective Date; and v) a plot plan of the Generating Facility and Interconnection Customer’s Interconnection Facilities. Such drawings, specifications, information necessary to allow and documents submitted by the Interconnection Customer to select equipmentthe Distribution Provider must be certified in writing by a professional engineer registered in the State of California, in accordance with Article 24.2 or other qualified and authorized representative of the GIA Distribution Provider Deemed to have been completed under Interconnection Customer, as being current and accurate representations of the IFA with respect to the Existing Generating Facility and Interconnection Customer’s Interconnection Facilities; within thirty (30) Calendar Days after the Effective Date with respect to the New Interconnection Facilities.

Appears in 1 contract

Samples: Generator Interconnection Agreement (Gia)

Payment Schedule and Associated ITCC. The payment amounts shown below are based on an estimate of the costs expected to be incurred for the Distribution Upgrades, New Distribution Provider’s Interconnection Facilities, and Network Upgrades. Payment No. Payment Due Date New Interconnection Facilities Cost Distribution Upgrades Cost Reliability Network Upgrades Cost Delivery Network Upgrades Cost One- Time Cost Project Payment Associated ITCC* 1 Within 30 thirty (30) Calendar Days after the Effective Date $184,551 86,900 $0 $0 $0 $0 184,551 $64,593 Calendar Days after the Effective Date 86,900 $30,415 Total $184,551 86,900 $0 $0 $0 $0 184,551 $64,593 86,900 $30,415 All amounts shown above are in nominal dollars. Interconnection Facilities Payment = ( New (Interconnection Facilities Cost + associated One-Time Cost) = $184,551 86,900 Distribution Upgrades Payment = (Distribution Upgrades Cost + associated One-Time Cost) = $0 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) = $0 Transmission credits pursuant to Section 9 of this Appendix A Attachment 2 = Reliability Network Upgrades Payment + Delivery Network Upgrades Payment = $0 *ITCC will be provided by Interconnection Customer in accordance with Section 11 of this Appendix A. 1. The Interconnection Customer’s Selected Option: Pursuant to Article 5.1 of the GIA, the Interconnection Customer has selected the Standard Option. Attachment 2. Milestone DatesIn-Service Date: Item Milestone Responsible Party Due DateMay 1, 2016 Critical milestones and responsibility as agreed to by the Parties: (a) Pursuant to Appendix C Section 3(b) provide a complete and updated one line diagram of its facilities identifying any connections to-or-from the Interconnection Facilities to IP. Interconnection Customer Within thirty (30) Calendar Days after the Agreement is fully executed. (b) Pursuant to Appendix C Section 3(b) submit for Distribution Provider’s approval, switching procedures to disconnect IP. Interconnection Customer Within thirty (30) Calendar Days after the Agreement is fully executed (c) Submit proof of insurance coverage in accordance with Article 18.3 8.1 of the GIA Interconnection Customer Within ten (10) Calendar Days calendar days after the Effective Date (db) Submittal of written authorization to proceed with design Credit Support for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades and procurement of the New Interconnection Facilities Network Upgrades to the Distribution Provider, in accordance with Article 5.5.2 Provider pursuant to Section 10 of Attachment 2 of the GIA Interconnection Customer Within thirty (30) Calendar Days after the Effective DateN/A (e) Submittal of written authorization to proceed with construction to the Distribution Provider, pursuant to Article 5.6.3 of the GIA Interconnection Customer Within thirty (30) Calendar Days after the Effective Date (fc) Submittal of security for the estimated tax liability to the Distribution Provider, pursuant to Article 5.17.3 and Section 11 of Appendix A Attachment 2 of the GIA Interconnection Customer Within thirty (30) Calendar Days calendar days after the Effective Date (d) Provide the following information (“Required Information”) in support of the Distribution Provider’s engineering and design of the Distribution Provider’s Interconnection Facilities and Distribution Upgrades: 1) a completed Distribution Provider provided Interconnection Customer information sheet, 2) a unique address for the project, 3) public right-of- way (street) base maps as required by the interconnection, 4) street improvement plans, 5) site plot plan on a 30:1 scale or digital file, 6) grading plans, 7) sewer and storm plot plans, 8) landscape, sprinkler and pedestal locations, 9) proposed location for the RTU, if applicable, 10) easements/lease agreements, and 11) panel drawings Interconnection Customer Within thirty (30) calendar days after the Effective Date (e) Completion of the Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction Distribution Provider Within ninety (90) calendar days of Distribution Provider’s receipt of the Required Information (f) Provide to the Interconnection Customer: 1) an updated scope of work and design for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction; 2) an updated cost estimate and schedule related to the Distribution Provider’s Interconnection Facilities and Distribution Upgrades, as applicable, if there are any material changes resulting from completion of the Distribution Provider’s detailed design of Distribution Provider’s Interconnection Facilities and Distribution Upgrades, and 3) comment on Interconnection Customer’s proposed location for the RTU, if applicable Distribution Provider Within five (5) calendar days following completion of Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and Civil Construction (g) Completion of the New Civil Construction, including Distribution Provider’s release, in accordance with Section 1 of Attachment 2 and Section 3 of Attachment 5 of the GIA Interconnection Facilities Customer Within sixty (60) calendar days after the Distribution Provider Within eighteen provides the design for the Civil Construction to the Interconnection Customer. Construction of SCE’s facilities does not commence until this milestone is completed; if the Customer can complete it earlier, then SCE’s completion under milestone (18o) months following the Effective Date*can also be earlier (h) Submittal of the steam turbine disconnection plan pursuant to Interconnection Customer Within thirty (30) Calendar Days after the Item Milestone Responsible Party Due Date Article 6.4 and Attachment C Section 3(j) of this GIA Effective Date (i) Submittal of initial final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility, including System Protection system protection facilities, to the Distribution Provider Interconnection Customer At least ninety (90) calendar days prior to completion of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, and Network Upgrades (i) Review of and comment on the Interconnection Customer’s final specifications Distribution Provider Within forty-five (45) calendar days following the Interconnection Customer’s submittal of the final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility (j) Notification of testing and inspection of Interconnection Customer’s Interconnection Facilities pursuant to Article 2.1.1 of the GIA Interconnection Customer Within five (5) Business Days prior to such testing and inspection (k) Submission of a written test report to the Distribution Provider, pursuant to in accordance with Article 5.10.1 2.1.1 of the GIA Interconnection Customer Deemed Within five (5) Business Days following completion of Interconnection Customer’s testing and inspection (l) Written acknowledgement of Interconnection Customer’s Interconnection Facilities written test report pursuant to have been completed under the IFA (j) Submittal of initial information including the Distribution Provider’s Transmission System information necessary to allow the Interconnection Customer to select equipment, in accordance with Article 24.2 2.1.2 of the GIA Distribution Provider Deemed Within five (5) Business Days of Interconnection Customer’s submission of the test report (m) Submission of written documentation reflecting Interconnection Customer’s satisfaction of parallel operation requirements pursuant to Article 2.2.2 of the GIA Interconnection Customer At least fifteen (15) calendar days prior to the Initial Synchronization Date (n) Proposed Interconnection Customer’s Interconnection Facilities completion date Interconnection Customer April 20, 2016 (o) Completion of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, and Network Upgrades Distribution Provider Within (9) months following the Effective Date, assuming Items (d) and (g) of this Attachment 4 have occurred timely* (p) Notification of Interconnection Customer’s intention to begin on-site verification testing of the Generating Facility pursuant to Article 2.3.1 of the GIA Interconnection Customer Ten (10) Business Days prior to Interconnection Customer’s verification testing date (q) Provide the ISO written notice that the required Distribution Provider facilities have been completed under installed and tested, and that initial synchronization of the IFA with respect Generating Facility to the Existing Distribution System is expected to occur on the Initial Synchronization Date Distribution Provider At least ten (10) calendar days prior to the Initial Synchronization Date (r) Performance of a complete calibration test and functional trip test of the system protection facilities Interconnection FacilitiesCustomer and Distribution Provider During the on-site verification testing of the Generating Facility pursuant to Article 2.3.1 of the GIA, and prior to initial synchronization; within thirty for Fast Track Projects this milestone is completed during the commissioning test (30s) Calendar Days In-Service Date Interconnection Customer May 1, 2016 (t) Proposed Initial Synchronization Date Interconnection Customer May 10, 2016 (u) Distribution Provider’s written authorization authorizing Interconnection Customer to operate its Generating Facility in parallel with the Distribution Provider’s Distribution System, pursuant to Article 2.2.2 of the GIA Distribution Provider Within five (5) calendar days after the Effective Initial Synchronization Date with respect and the Interconnection Customer’s satisfaction of parallel operation requirements pursuant to the New Interconnection FacilitiesArticle 2.2.2

Appears in 1 contract

Samples: Generator Interconnection Agreement