Common use of Payment Schedule and Associated ITCC Clause in Contracts

Payment Schedule and Associated ITCC. The payment amounts shown below are based on an estimate of the costs expected to be incurred for the Distribution Upgrades, Distribution Provider’s Interconnection Facilities, and Network Upgrades. Payment No. Payment Due Date Interconnection Facilities Cost Distribution Upgrades Cost Reliability Network Upgrades Cost Delivery Network Upgrades Cost One- Time Cost Project Payment Associated ITCC* 1 12/09/13 $58,300 $29,150 $0.00 $0.00 $7,250 $94,700.00 $30,607.50 2 02/03/14 $58,300 $29,150 $0.00 $0.00 $7,250 $94,700.00 $30,607.50 Total $116,600 $58,300 $0.00 $0.00 $14,500 $189,400.00 $61,215.00 All amounts shown above are in nominal dollars. Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) = $116,600.00 + $14,500 = $131,100.00 Distribution Upgrades Payment = (Distribution Upgrades Cost + associated One-Time Cost) = $58,300.00 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0.00 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) = $0.00 Transmission credits pursuant to Section 9 of this Attachment 2 = Reliability Network Upgrades Payment + Delivery Network Upgrades Payment = $0.00 *ITCC will be provided by Interconnection Customer in accordance with Section 11 of this Attachment 2. One-line Diagram Depicting the Generating Facility, Interconnection Facilities, Metering Equipment, and Upgrades In-Service Date: October 20, 2014 Critical milestones and responsibility as agreed to by the Parties: Item Milestone Responsible Party Due Date (a) Submit proof of insurance coverage in accordance with Article 8.1 of the GIA Interconnection Customer On or before December 15, 2013 (b) Submittal of Credit Support for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades and Network Upgrades to the Distribution Provider pursuant to Section 10 of Attachment 2 of the GIA Interconnection Customer On or before January 4, 2014 (c) Submittal of security for the estimated tax liability to the Distribution Provider, pursuant to Section 11 of Attachment 2 of the GIA Interconnection Customer On or before January 4, 2014 (d) Provide the following information (“Required Information”) in support of the Distribution Provider’s engineering and design of the Distribution Provider’s Interconnection Facilities and Distribution Upgrades: 1) a completed Distribution Provider provided Interconnection Customer information sheet, 2) a unique address for the project, 3) public right-of-way (street) base maps as required by the interconnection, 4) street improvement plans, 5) site plot plan on a 30:1 scale or digital file, 6) grading plans, 7) sewer and storm plot plans, 8) landscape, sprinkler and pedestal locations, 9) proposed location for the RTU, if applicable, 10) easements/lease agreements, and 11) panel drawings Interconnection Customer On or before January 19, 2014 Item Milestone Responsible Party Due Date (e) Completion of the Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction Distribution Provider Within ninety (90) calendar days of Distribution Provider’s receipt of the Required Information (f) Provide to the Interconnection Customer: 1) an updated scope of work and design for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction; 2) an updated cost estimate and schedule related to the Distribution Provider’s Interconnection Facilities and Distribution Upgrades, as applicable, if there are any material changes resulting from completion of the Distribution Provider’s detailed design of Distribution Provider’s Interconnection Facilities and Distribution Upgrades, and 3) comment on Interconnection Customer’s proposed location for the RTU, if applicable Distribution Provider Within five (5) calendar days following completion of Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and Civil Construction (g) Completion of the Civil Construction, including Distribution Provider’s release, in accordance with Section 1 of Attachment 2 and Section 3 of Attachment 5 of the GIA Interconnection Customer Within sixty (60) calendar days after the Distribution Provider provides the design for the Civil Construction to the Interconnection Customer (h) Submittal of final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility, including system protection facilities, to the Distribution Provider Interconnection Customer At least ninety (90) calendar days prior to completion of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, and Network Upgrades Item Milestone Responsible Party Due Date (i) Review of and comment on the Interconnection Customer’s final specifications Distribution Provider Within forty-five (45) calendar days following the Interconnection Customer’s submittal of the final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility (j) Notification of testing and inspection of Interconnection Customer’s Interconnection Facilities pursuant to Article 2.1.1 of the GIA Interconnection Customer Within five (5) Business Days prior to such testing and inspection (k) Submission of a written test report to the Distribution Provider, in accordance with Article 2.1.1 of the GIA Interconnection Customer Within five (5) Business Days following completion of Interconnection Customer’s testing and inspection (l) Written acknowledgement of Interconnection Customer’s Interconnection Facilities written test report pursuant to Article 2.1.2 of the GIA Distribution Provider Within five (5) Business Days of Interconnection Customer’s submission of the test report (m) Submission of written documentation reflecting Interconnection Customer’s satisfaction of parallel operation requirements pursuant to Article 2.2.2 of the GIA Interconnection Customer At least fifteen (15) calendar days prior to the Initial Synchronization Date (n) Proposed Interconnection Customer’s Interconnection Facilities completion date Interconnection Customer Ten (10) calendar days before completion of SCE’s Interconnection Facilities and Distribution Upgrades Item Milestone Responsible Party Due Date (o) Completion of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, and Network Upgrades Distribution Provider Within (09) months following the Effective Date, assuming Items (d) and (g) of this Attachment 4 have occurred timely* (p) Notification of Interconnection Customer’s intention to begin on-site verification testing of the Generating Facility pursuant to Article 2.3.1 of the GIA Interconnection Customer Ten (10) Business Days prior to Interconnection Customer’s verification testing date (q) Provide the ISO written notice that the required Distribution Provider facilities have been installed and tested, and that initial synchronization of the Generating Facility to the Distribution System is expected to occur on the Initial Synchronization Date Distribution Provider At least five (5) Business Days prior to the Initial Synchronization Date (r) Performance of a complete calibration test and functional trip test of the system protection facilities Interconnection Customer and Distribution Provider During the on-site verification testing of the Generating Facility pursuant to Article 2.3.1 of the GIA, and prior to initial synchronization (s) Proposed Initial Synchronization Date Interconnection Customer October 20, 2014 (t) In-Service Date Interconnection Customer October 20, 2014

Appears in 1 contract

Samples: Generator Interconnection Agreement

AutoNDA by SimpleDocs

Payment Schedule and Associated ITCC. The payment amounts shown below are based on an estimate of the monthly incurred costs expected to be incurred for the Distribution Upgrades, Distribution Provider’s Interconnection Facilities, and Network Upgrades. Payment No. Payment Due Date Interconnection Facilities Cost Distribution Upgrades Cost Reliability Network Upgrades Cost Delivery Network Upgrades Cost One- One-Time Cost Project Payment Associated ITCC* 1 12/09/13 1/15/2014 $58,300 135,000.00 $29,150 14,500.00 $0.00 149,500.00 $0.00 47,250.00 2 6/1/2014 $7,250 1,057,227.00 $94,700.00 1,057,227.00 $30,607.50 2 02/03/14 $58,300 $29,150 $0.00 $0.00 $7,250 $94,700.00 $30,607.50 232,590.00 Total $116,600 1,192,227.00 $58,300 14,500.00 $0.00 1,206,727.00 $0.00 $14,500 $189,400.00 $61,215.00 279,840.00 All amounts shown above are in nominal dollars. Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) = $116,600.00 + $14,500 = $131,100.00 Distribution Upgrades Payment = (Distribution Upgrades Cost + associated One-Time Cost) = $58,300.00 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0.00 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) = $0.00 Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) = $1,206,727.00 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0.00 Transmission credits pursuant to Section 9 of this Attachment 2 = Reliability Network Upgrades Payment + Delivery Network Upgrades Payment = $0.00 *ITCC will be provided by Interconnection Customer in accordance with Section 11 of this Attachment 2. One-line Diagram Depicting the Generating Facility, Interconnection Facilities, Metering Equipment, and Upgrades In-Service Date: October 20June 1, 2014 Critical milestones and responsibility as agreed to by the Parties: Item Milestone Responsible Party Due Date: (a) Submit proof of insurance coverage in accordance with Article 8.1 of the GIA SGIA Interconnection Customer On or before December 15, 2013Within ten (10) calendar days after the Effective Date (b) Submittal of Credit Support for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades and Network Upgrades to the Distribution Provider pursuant to Section 10 of Attachment 2 of the GIA SGIA Interconnection Customer On or before January 4, 2014Within thirty (30) calendar days after the Effective Date (c) Submittal of security for the estimated tax liability to the Distribution Provider, pursuant to Section 11 of Attachment 2 of the GIA Interconnection Customer On or before January 4, 2014 (d) Provide the following information (“Required Information”) in support of the Distribution Provider’s engineering and design of the Distribution Provider’s Interconnection Facilities and Distribution Upgrades: 1) a completed Distribution Provider provided Interconnection Customer information sheet, 2) a unique address for the project, 3) public right-of-way (street) base maps as required by the interconnection, 4) street improvement plans, 5) site plot plan on a 30:1 scale or digital file, 6) grading plans, 7) sewer and storm plot plans, 8) landscape, sprinkler and pedestal locations, 9) proposed location for the RTU, if applicable, 10) easements/lease agreements, and 11) panel drawings Interconnection Customer On or before January 19, 2014 Item Milestone Responsible Party Due Date (e) Completion of the Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction Distribution Provider Within ninety (90) calendar days of Distribution Provider’s receipt of the Required Information (f) Provide to the Interconnection Customer: 1) an updated scope of work and design for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction; 2) an updated cost estimate and schedule related to the Distribution Provider’s Interconnection Facilities and Distribution Upgrades, as applicable, if there are any material changes resulting from completion of the Distribution Provider’s detailed design of Distribution Provider’s Interconnection Facilities and Distribution Upgrades, and 3) comment on Interconnection Customer’s proposed location for the RTU, if applicable Distribution Provider Within five (5) calendar days following completion of Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and Civil Construction (g) Completion of the Civil Construction, including Distribution Provider’s release, in accordance with Section 1 of Attachment 2 and Section 3 of Attachment 5 of the GIA SGIA Interconnection Customer Within sixty thirty (6030) calendar days after the Distribution Provider provides the design for the Civil Construction to the Interconnection Customer Effective Date (hd) Submittal of final initial specifications for the Interconnection Customer’s Interconnection Facilities and Small Generating Facility, including system protection facilities, to the Distribution Provider Interconnection Customer At least ninety one hundred eighty (90) calendar days prior to completion of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, and Network Upgrades Item Milestone Responsible Party Due Date (i) Review of and comment on the Interconnection Customer’s final specifications Distribution Provider Within forty-five (45) calendar days following the Interconnection Customer’s submittal of the final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility (j) Notification of testing and inspection of Interconnection Customer’s Interconnection Facilities pursuant to Article 2.1.1 of the GIA Interconnection Customer Within five (5) Business Days prior to such testing and inspection (k) Submission of a written test report to the Distribution Provider, in accordance with Article 2.1.1 of the GIA Interconnection Customer Within five (5) Business Days following completion of Interconnection Customer’s testing and inspection (l) Written acknowledgement of Interconnection Customer’s Interconnection Facilities written test report pursuant to Article 2.1.2 of the GIA Distribution Provider Within five (5) Business Days of Interconnection Customer’s submission of the test report (m) Submission of written documentation reflecting Interconnection Customer’s satisfaction of parallel operation requirements pursuant to Article 2.2.2 of the GIA Interconnection Customer At least fifteen (15180) calendar days prior to the Initial Synchronization Date (n) Proposed Interconnection Customer’s Interconnection Facilities completion date Interconnection Customer Ten (10) calendar days before completion of SCE’s Interconnection Facilities and Distribution Upgrades Item Milestone Responsible Party Due Date (o) Completion of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, and Network Upgrades Distribution Provider Within (09) months following the Effective Date, assuming Items (d) and (g) of this Attachment 4 have occurred timely* (p) Notification of Interconnection Customer’s intention to begin on-site verification testing of the Generating Facility pursuant to Article 2.3.1 of the GIA Interconnection Customer Ten (10) Business Days prior to Interconnection Customer’s verification testing date (q) Provide the ISO written notice that the required Distribution Provider facilities have been installed and tested, and that initial synchronization of the Generating Facility to the Distribution System is expected to occur on the Initial Synchronization Date Distribution Provider At least five (5) Business Days prior to the Initial Synchronization Date (r) Performance of a complete calibration test and functional trip test of the system protection facilities Interconnection Customer and Distribution Provider During the on-site verification testing of the Generating Facility pursuant to Article 2.3.1 of the GIA, and prior to initial synchronization (s) Proposed Initial Synchronization Date Interconnection Customer October 20, 2014 (t) In-Service Date Interconnection Customer October 20, 2014

Appears in 1 contract

Samples: Small Generator Interconnection Agreement (Sgia)

Payment Schedule and Associated ITCC. The payment amounts shown below are based on an estimate of the monthly incurred costs expected to be incurred for the Distribution Upgrades, Distribution Provider’s Interconnection Facilities, and Network Upgrades. Payment No. Payment Due Date Interconnection Facilities Cost Distribution Upgrades Cost Reliability Network Upgrades Cost Delivery Network Upgrades Cost One- Time Cost Project Payment Amount Associated ITCC* ITCC 1 12/09/13 12/1/2012 $58,300 21,276 $29,150 20,194 $0.00 41,470 2 1/1/2013 $0.00 35,218 $7,250 33,428 $94,700.00 68,646 3 2/1/2013 $30,607.50 2 02/03/14 51,824 $58,300 49,190 $29,150 101,014 4 3/1/2013 $0.00 66,921 $0.00 63,519 $7,250 130,440 5 4/1/2013 $94,700.00 73,221 $30,607.50 Total 69,499 $116,600 142,720 6 5/1/2013 $58,300 66,921 $0.00 63,519 $0.00 130,440 7 6/1/2013 $14,500 51,824 $189,400.00 49,190 $61,215.00 101,014 8 7/1/2013 $35,218 $33,428 $68,646 9 8/1/2013 $21,859 $20,749 $42,608 10 9/1/2013 $12,816 $12,163 $24,979 Totals $437,098 $414,879 $851,977 $298,192 All amounts shown above are in nominal dollars. Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) = $116,600.00 + $14,500 = $131,100.00 Distribution Upgrades Payment = (Distribution Upgrades Cost + associated One-Time Cost) = $58,300.00 414,879 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) =$0 Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) =$437,098 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0.00 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) = $0.00 0 Transmission credits pursuant to Section 9 of this Attachment 2 = Reliability Network Upgrades Payment + Delivery Network Upgrades Payment = $0.00 0 *ITCC will be provided by Interconnection Customer in accordance with Section 11 of this Attachment 2. One-line Diagram Depicting the Generating Facility, Interconnection Facilities, Metering Equipment, and Upgrades In-Service Date: October 20September 15, 2014 2013 Critical milestones and responsibility as agreed to by the Parties: Item Milestone Responsible Party Due Date Date (a) Provide a list of applicable parallel operation requirements in Attachment 5 of this Agreement. Additionally, notify the Interconnection Customer of any changes to these requirements as soon as they are known. Distribution Provider Within twenty (20) business days after request by the Interconnection Customer (a1) Submit proof of insurance coverage in accordance with Article 8.1 of the GIA SGIA Interconnection Customer On or before December 15, 2013 Within ten (10) calendar days of the execution of this SGIA (b) Submittal of Credit Support for the Distribution Provider’s Interconnection Facilities, Distribution Network Upgrades and Network Distribution Upgrades to the Distribution Provider pursuant to Section 10 of Attachment 2 of the GIA SGIA Interconnection Customer On or before January 4, 2014 Within thirty (30) calendar days of the Effective Date (c) Submittal of security for the estimated tax liability to the Distribution Provider, pursuant to Section 11 of Attachment 2 of the GIA SGIA Interconnection Customer On or before January 4, 2014 Within thirty (30) calendar days of the Effective Date (d) Provide the following information (“Required Information”) in support of the Distribution Provider’s engineering and design of the Distribution Provider’s Interconnection Facilities and Distribution Upgrades: 1) a completed Distribution Provider provided Interconnection Customer information sheetpanel drawings, 2) a unique address for the projecteasements/lease agreements, 3) public right-of-way (street) base maps as required by the interconnection, 4) street improvement plans, 5) site plot plan on a 30:1 scale or digital file, 6) grading plans, 7) sewer and storm plot plans, 8) landscape, sprinkler and pedestal locations, 9) proposed location for the RTU, if applicable, 10) easements/lease agreements, and 11) panel drawings . (“Required Information”). Interconnection Customer On or before January 19, 2014 Within 30 calendar days of the Effective Date* (e) Complete design of Civil Construction necessary to support the Distribution Provider’s Interconnection Distribution Provider Sixty (60) business days from the completion of (d) Item Milestone Responsible Party Due Date Date Facilities (e1) Complete the construction of the Civil Construction Interconnection Customer One hundred and eighty (180) business days from the completion of (e) Completion of the Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction Distribution Provider Within ninety (90) calendar days of Distribution Provider’s receipt of the Required Information (f) Provide to the Interconnection Customer: 1) an updated scope of work and design for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction; 2) an updated cost estimate and schedule related to the Distribution Provider’s Interconnection Facilities and Distribution Upgrades, as applicable, if there are any material changes resulting from completion of the Distribution Provider’s detailed design of Distribution Provider’s Interconnection Facilities and Distribution Upgrades, and 3) comment on Interconnection Customer’s proposed location for the RTU, if applicable Distribution Provider Within five (5) calendar days following completion of Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and Civil Construction (g) Completion of the Civil Construction, including Distribution Provider’s release, in accordance with Section 1 of Attachment 2 and Section 3 of Attachment 5 of the GIA Interconnection Customer Within sixty (60) calendar days after the Distribution Provider provides the design for the Civil Construction to the Interconnection Customer (h) Submittal of final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility, including system protection facilities, to the Distribution Provider Interconnection Customer At least ninety (90) calendar days prior to completion of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, and Network Upgrades Item Milestone Responsible Party Due Date (i) Review of and comment on the Interconnection Customer’s final specifications Distribution Provider Within forty-five (45) calendar days following the Interconnection Customer’s submittal of the final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility (j) Notification of testing and inspection of Interconnection Customer’s Interconnection Facilities pursuant to Article 2.1.1 of the GIA Interconnection Customer Within five (5) Business Days prior to such testing and inspection (k) Submission of a written test report to the Distribution Provider, in accordance with Article 2.1.1 of the GIA Interconnection Customer Within five (5) Business Days following completion of Interconnection Customer’s testing and inspection (l) Written acknowledgement of Interconnection Customer’s Interconnection Facilities written test report pursuant to Article 2.1.2 of the GIA Distribution Provider Within five (5) Business Days of Interconnection Customer’s submission of the test report (m) Submission of written documentation reflecting Interconnection Customer’s satisfaction of parallel operation requirements pursuant to Article 2.2.2 of the GIA Interconnection Customer At least fifteen (15) calendar days prior to the Initial Synchronization Date (n) Proposed Interconnection Customer’s Interconnection Facilities completion date Interconnection Customer Ten (10) calendar days before completion of SCE’s Interconnection Facilities and Distribution Upgrades Item Milestone Responsible Party Due Date (o) Completion of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, and Network Upgrades Distribution Provider Within The later of (09i) months following the Effective DateSeptember 15, 2013 assuming Items that (d) and has been provided by the due date, or (ii) the date on which sufficient completion of EKWRA has occurred in order to enable interconnection of the project, which date shall be determined by the Distribution Provider in its sole discretion (g) Submittal of this Attachment 4 have occurred timely* (p) Notification of initial specifications for the Interconnection Customer’s intention to begin on-site verification testing of the Interconnection Facilities and Small Generating Facility pursuant to Article 2.3.1 of the GIA Interconnection Customer Ten (10) Business Days prior to Interconnection Customer’s verification testing date (q) Provide the ISO written notice that the required Distribution Provider facilities have been installed and testedFacility, and that initial synchronization of the Generating Facility including system protection facilities, to the Distribution System is expected Provider Interconnection Customer At least one hundred eighty (180) calendar days prior to occur on the Initial Synchronization Date (h) Submittal of initial information including the Distribution System information necessary to allow the Interconnection Customer to select equipment Distribution Provider At least five one hundred eighty (5180) Business Days calendar days prior to Trial Operation (i) Submittal of updated information by the Interconnection Customer, including manufacturer information Interconnection Customer No later than one hundred eighty (180) calendar days prior to Trial Operation (j) Review of and comment on the Interconnection Customer’s initial specifications Distribution Provider Within thirty (30) calendar days of the Interconnection Customer’s submission of initial specifications (k) Submittal of final specifications for the Interconnection Customer’s Interconnection Facilities and Small Generating Facility, including System Interconnection Customer At least ninety (90) calendar days prior to the Initial Synchronization Date . Item Milestone Responsible Party Due Date Protection Facilities, to the Distribution Provider (rl) Review of and comment on the Interconnection Customer’s final specifications Distribution Provider Within thirty (30) calendar days of the Interconnection Customer’s submission of final specifications (m) Notification of Balancing Authority Area to the Distribution Provider Interconnection Customer At least three (3) months prior to the Initial Synchronization Date (n) Performance of a complete calibration test and functional trip test of the system protection facilities Interconnection Customer and Distribution Provider During the on-site verification testing of the Generating Facility pursuant to Article 2.3.1 of the GIA, and At least sixty (60) calendar days prior to initial synchronization the In-Service Date (s) Proposed Initial Synchronization Date Interconnection Customer October 20, 2014 (to) In-Service Date Interconnection Customer October 20September 15, 20142013 with the completion of sufficient EKWRA Project Scope necessary to bring the Generating Facility in-service

Appears in 1 contract

Samples: Small Generator Interconnection Agreement (Sgia)

AutoNDA by SimpleDocs

Payment Schedule and Associated ITCC. The payment amounts shown below are based on an estimate of the monthly incurred costs expected to be incurred for the new Distribution Upgrades, Distribution Provider’s Interconnection Facilities, and Network Upgrades. Payment No. Payment Due Date Customer- Financed Interconnection Facilities Cost Distribution Upgrades Cost Reliability Network Upgrades Cost Delivery Network Upgrades Cost One- Time Cost Project Payment Associated ITCC* 1 12/09/13 Within 30 calendar days of the Effective Date $58,300 168,000 $29,150 168,000 $0.00 $0.00 $7,250 $94,700.00 $30,607.50 2 02/03/14 $58,300 $29,150 $0.00 $0.00 $7,250 $94,700.00 $30,607.50 Total $116,600 $58,300 $0.00 $0.00 $14,500 $189,400.00 $61,215.00 58,800 All amounts shown above are in nominal dollars. Interconnection Facilities Payment = (Interconnection Facilities Cost + associated One-Time Cost) = $116,600.00 + $14,500 = $131,100.00 Distribution Upgrades Payment = (Distribution Upgrades Cost + associated One-Time Cost) = $58,300.00 0 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) =$0 Interconnection Facilities Payment = (Customer-Financed Interconnection Facilities Cost + associated One-Time Cost) =$168,800 Reliability Network Upgrades Payment = (Reliability Network Upgrades Cost + associated One-Time Cost) = $0.00 Delivery Network Upgrades Payment = (Delivery Network Upgrades Cost + associated One-Time Cost) = $0.00 0 Transmission credits pursuant to Section 9 of this Attachment 2 Appendix A = Reliability Network Upgrades Payment + Delivery Network Upgrades Payment = $0.00 0 *ITCC will be provided by Interconnection Customer in accordance with Section 11 of this Attachment 2. One-line Diagram Depicting the Generating Facility, Interconnection Facilities, Metering Equipment, and Upgrades In-Service Date: October 20, 2014 Critical milestones and responsibility as agreed to by the Parties: Item Milestone Responsible Party Due Date (a) Submit proof of insurance coverage in accordance with Article 8.1 of the GIA Interconnection Customer On or before December 15, 2013 (b) Submittal of Credit Support for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades and Network Upgrades to the Distribution Provider pursuant to Section 10 of Attachment 2 of the GIA Interconnection Customer On or before January 4, 2014 (c) Submittal of security for the estimated tax liability to the Distribution Provider, pursuant to Section 11 of Attachment 2 of the GIA Interconnection Customer On or before January 4, 2014 (d) Provide the following information (“Required Information”) in support of the Distribution Provider’s engineering and design of the Distribution Provider’s Interconnection Facilities and Distribution Upgrades: 1) a completed Distribution Provider provided Interconnection Customer information sheet, 2) a unique address for the project, 3) public right-of-way (street) base maps as required by the interconnection, 4) street improvement plans, 5) site plot plan on a 30:1 scale or digital file, 6) grading plans, 7) sewer and storm plot plans, 8) landscape, sprinkler and pedestal locations, 9) proposed location for the RTU, if applicable, 10) easements/lease agreements, and 11) panel drawings Interconnection Customer On or before January 19, 2014 Item Milestone Responsible Party Due Date (e) Completion of the Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction Distribution Provider Within ninety (90) calendar days of Distribution Provider’s receipt of the Required Information (f) Provide to the Interconnection Customer: 1) an updated scope of work and design for the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and the Civil Construction; 2) an updated cost estimate and schedule related to the Distribution Provider’s Interconnection Facilities and Distribution Upgrades, as applicable, if there are any material changes resulting from completion of the Distribution Provider’s detailed design of Distribution Provider’s Interconnection Facilities and Distribution Upgrades, and 3) comment on Interconnection Customer’s proposed location for the RTU, if applicable Distribution Provider Within five (5) calendar days following completion of Distribution Provider’s design and engineering of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, if applicable, and Civil Construction (g) Completion of the Civil Construction, including Distribution Provider’s release, in accordance with Section 1 of Attachment 2 and Section 3 of Attachment 5 of the GIA Interconnection Customer Within sixty (60) calendar days after the Distribution Provider provides the design for the Civil Construction to the Interconnection Customer (h) Submittal of final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility, including system protection facilities, to the Distribution Provider Interconnection Customer At least ninety (90) calendar days prior to completion of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, and Network Upgrades Item Milestone Responsible Party Due Date (i) Review of and comment on the Interconnection Customer’s final specifications Distribution Provider Within forty-five (45) calendar days following the Interconnection Customer’s submittal of the final specifications for the Interconnection Customer’s Interconnection Facilities and Generating Facility (j) Notification of testing and inspection of Interconnection Customer’s Interconnection Facilities pursuant to Article 2.1.1 of the GIA Interconnection Customer Within five (5) Business Days prior to such testing and inspection (k) Submission of a written test report to the Distribution Provider, in accordance with Article 2.1.1 of the GIA Interconnection Customer Within five (5) Business Days following completion of Interconnection Customer’s testing and inspection (l) Written acknowledgement of Interconnection Customer’s Interconnection Facilities written test report pursuant to Article 2.1.2 of the GIA Distribution Provider Within five (5) Business Days of Interconnection Customer’s submission of the test report (m) Submission of written documentation reflecting Interconnection Customer’s satisfaction of parallel operation requirements pursuant to Article 2.2.2 of the GIA Interconnection Customer At least fifteen (15) calendar days prior to the Initial Synchronization Date (n) Proposed Interconnection Customer’s Interconnection Facilities completion date Interconnection Customer Ten (10) calendar days before completion of SCE’s Interconnection Facilities and Distribution Upgrades Item Milestone Responsible Party Due Date (o) Completion of the Distribution Provider’s Interconnection Facilities, Distribution Upgrades, and Network Upgrades Distribution Provider Within (09) months following the Effective Date, assuming Items (d) and (g) of this Attachment 4 have occurred timely* (p) Notification of Interconnection Customer’s intention to begin on-site verification testing of the Generating Facility pursuant to Article 2.3.1 of the GIA Interconnection Customer Ten (10) Business Days prior to Interconnection Customer’s verification testing date (q) Provide the ISO written notice that the required Distribution Provider facilities have been installed and tested, and that initial synchronization of the Generating Facility to the Distribution System is expected to occur on the Initial Synchronization Date Distribution Provider At least five (5) Business Days prior to the Initial Synchronization Date (r) Performance of a complete calibration test and functional trip test of the system protection facilities Interconnection Customer and Distribution Provider During the on-site verification testing of the Generating Facility pursuant to Article 2.3.1 of the GIA, and prior to initial synchronization (s) Proposed Initial Synchronization Date Interconnection Customer October 20, 2014 (t) In-Service Date Interconnection Customer October 20, 2014Appendix A.

Appears in 1 contract

Samples: Generator Interconnection Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!