Payment to Contractor. 17.1.5.1 If Owner terminates the Contract for Contractor’s breach or default, Contractor shall thereafter only be entitled to reimbursement (subject to Section 17.1.5.3 hereof) only of such amount (if any), by which: (a) the (i) Cost of the Work actually and properly completed by Contractor in accordance with the Contract Documents up to the date of such termination (and not cancelable or refundable), plus (ii) the pro rata portion of Contractor’s Fee thereon (subject to satisfaction of the conditions applicable to progress and Final Payment contained in the Contract Documents as the case may be), but the foregoing amounts shall not exceed the portion of the Guaranteed Maximum Price (including Contractor’s Fee) fairly allocable to the Work so completed, exceeds (b) the total of (i) all payments theretofore made to Contractor under the Contract Documents, and (ii) all damages and other costs and expenses incurred by Owner directly or indirectly, arising out of or as a result of, Contractor’s breach or default, including, without limitation, the cost of any additional consultants’ services, or managerial and administrative services required thereby, any additional costs incurred in retaining another contractor or other Subcontractors, any additional financing, interest or fees and other costs that Owner must pay by reason of a delay in completion of the Work, Owner’s termination of Contractor and the finishing of the Work by another method after such termination, attorneys’ fees and expenses, and any other damages, costs, and expenses Owner may incur in completing the Work as a result of Contractor’s breach or default including if Owner elects to complete the Project after such termination, the amount by which the actual cost of completing the Project (including components of the Project that are not part of the Work) is greater than what such actual cost (including the actual cost of components of the Project that are not part of the Work) would have been if Contractor had fulfilled its obligations under the Contract Documents, and if Owner elects to not complete the Project after such termination Contractor hereby acknowledges that Owner has the right to so elect without Owner waiving Contractor’s liability for damages arising out of the breach by Contractor that led to its termination, all damages suffered by Owner arising out of Contractor’s breach of this Agreement. 17.1.5.2 If the amount referred to in Section 17.1.5.1.(b) hereinabove exceeds the amount referred to in Section 17.1. (a) hereinabove, Contractor shall pay the difference to Owner immediately upon Owner’s demand. 17.1.5.3 Any reimbursements or payments made to Contractor under this Section 17.1.5 are conditioned on (a) Contractor previously having delivered to Owner possession and unfettered access to the Work and Site and all materials, equipment, tools and the like (undamaged and in good condition) which Owner has paid for and/or been billed for, (b) all the applicable items listed in, and performance of all the applicable obligations described in Section 12.2.1 of this Agreement have been satisfied, and (c) Contractor complies with such other obligations under the Contract Documents as Owner or Owner’s Lenders reasonably requires.
Appears in 2 contracts
Sources: Guaranteed Maximum Price Construction Services Agreement (Pinnacle Entertainment Inc), Guaranteed Maximum Price Construction Services Agreement (Pinnacle Entertainment Inc)
Payment to Contractor. 17.1.5.1 If Owner terminates the Contract for Contractor’s 's breach or default, Contractor shall thereafter only be entitled to reimbursement (subject to Section 17.1.5.3 hereof) only of such amount (if any), by which:
(a) the (i) Cost of the Work actually and properly completed by Contractor in accordance with the Contract Documents up to the date of such termination (and not cancelable or refundable), plus (ii) the pro rata portion of Contractor’s 's Fee thereon (subject to satisfaction of the conditions applicable to progress and Final Payment contained in the Contract Documents as the case may be), but the foregoing amounts shall not exceed the portion of the Guaranteed Maximum Price (including Contractor’s 's Fee) fairly allocable to the Work so completed, exceeds
(b) the total of (i) all payments theretofore made to Contractor under the Contract Documents, and (ii) all damages and other costs and expenses incurred by Owner directly or indirectly, arising out of or as a result of, Contractor’s 's breach or default, including, without limitation, the cost of any additional consultants’ ' services, or managerial and administrative services required thereby, any additional costs incurred in retaining another contractor or other Subcontractors, any additional financing, interest or fees and other costs that Owner must pay by reason of a delay in completion of the Work, Owner’s 's termination of Contractor and the finishing of the Work by another method after such termination, attorneys’ ' fees and expenses, and any other damages, costs, and expenses Owner may incur in completing the Work as a result of Contractor’s 's breach or default including if Owner elects to complete the Project after such termination, the amount by which the actual cost of completing the Project (including components of the Project that are not part of the Work) is greater than what such actual cost (including the actual cost of components of the Project that are not part of the Work) would have been if Contractor had fulfilled its obligations under the Contract Documents, and if Owner elects to not complete the Project after such termination Contractor hereby acknowledges that Owner has the right to so elect without Owner waiving Contractor’s 's liability for damages arising out of the breach by Contractor that led to its termination, all damages suffered by Owner arising out of Contractor’s 's breach of this Agreement.
17.1.5.2 If the amount referred to in Section 17.1.5.1.(b) hereinabove exceeds the amount referred to in Section 17.117.1.5.1.
(a) hereinabove, Contractor shall pay the difference to Owner immediately upon Owner’s 's demand.
17.1.5.3 Any reimbursements or payments made to Contractor under this Section 17.1.5 are conditioned on (a) Contractor previously having delivered to Owner possession and unfettered access to the Work and Site and all materials, equipment, tools and the like (undamaged and in good condition) which Owner has paid for and/or been billed for, (b) all the applicable items listed in, and performance of all the applicable obligations described in Section 12.2.1 of this Agreement have been satisfied, and (c) Contractor complies with such other obligations under the Contract Documents as Owner or Owner’s 's Lenders reasonably requires.
Appears in 1 contract
Sources: Guaranteed Maximum Price Construction Services Agreement (Wynn Resorts LTD)
Payment to Contractor. 17.1.5.1 If Owner terminates the Contract for Contractor’s breach or default, Contractor shall thereafter only be entitled to reimbursement (subject to Section 17.1.5.3 hereof) only of such amount (if any), by which:
(a) the (i) Cost of the Work actually and properly completed by Contractor in accordance with the Contract Documents up to the date of such termination (and not cancelable or refundable), plus (ii) the pro rata portion of Contractor’s Fee thereon (subject to satisfaction of the conditions applicable to progress and Final Payment contained in the Contract Documents as the case may be), but the foregoing amounts shall not exceed the portion of the Guaranteed Maximum Price (including Contractor’s Fee) fairly allocable to the Work so completed, exceeds
(b) the total of (i) all payments theretofore made to Contractor under the Contract Documents, and (ii) all damages and other costs and expenses incurred by Owner directly or indirectly, arising out of or as a result of, Contractor’s breach or default, including, without limitationbut not limited to, the cost of any additional consultants’ services, or managerial and administrative services required thereby, any additional costs incurred in retaining another contractor or other Subcontractorssubcontractors, any additional financing, interest or fees and other costs that Owner must pay by reason of a delay in completion of the Work, Owner’s termination of Contractor and the finishing of the Work by another method after such termination, attorneys’ fees and expenses, and any other damages, costs, and expenses Owner may incur in completing the Work as a result of Contractor’s breach or default including if Owner elects to complete the Project after such termination, the amount by which the actual cost of completing the Project (including components of the Project that are not part of the Work) is greater than what such actual cost (including the actual cost of components of the Project that are not part of the Work) would have been if Contractor had fulfilled its obligations under the Contract Documents, and if Owner elects to not complete the Project after such termination (Contractor hereby acknowledges acknowledging that Owner has the right to so elect without Owner waiving Contractor’s liability for damages arising out of the breach by Contractor that led to its termination), all damages suffered by Owner arising out of Contractor’s breach of this Agreement; provided that the amount specified in this clause (b) shall be reduced by any amounts received by Owner under the On-Demand Bond referred to in Section 7.18.
17.1.5.2 If the amount referred to in Section 17.1.5.1.(b) hereinabove exceeds the amount referred to in Section 17.1.
(a17.1.5.1.(a) hereinabove, Contractor shall pay the difference to Owner immediately upon Owner’s demandrequest, subject to the provisions of Section 14.7.
17.1.5.3 Any reimbursements or payments made to Contractor under this Section 17.1.5 are conditioned on (a) Contractor previously having delivered to Owner possession and unfettered access to the Work and Site and all materials, equipment, tools and the like (undamaged and in good condition) which Owner has paid for and/or been billed or will pay for, (b) all the applicable items listed in, and performance of all the applicable obligations described in Section 12.2.1 of this Agreement have been satisfied, and (c) Contractor complies with such other obligations under the Contract Documents accruing prior to termination or that by their nature survive the termination of this Agreement as Owner or Owner’s Lenders reasonably requires.
Appears in 1 contract
Payment to Contractor. 17.1.5.1 If Owner terminates The Contractor shall submit semi-monthly, or at longer intervals, if he so desires, an invoice covering work previously performed for which he believes payment, under the Contract terms, is due, and shall deliver said invoice to the Owner. Each request for Contractor’s breach or defaultpayment shall be accompanied by a statement certifying that all bills for labor and materials have been paid up for all previous pay requests. Each progress payment request shall be paid within one of the following time periods, Contractor shall thereafter only be entitled to reimbursement (subject to Section 17.1.5.3 hereof) only of such amount (if any), by whichwhichever is later:
A. Thirty (a30) days after the (i) Cost Owner has certified that the work is in place in the portion of the Work actually and properly completed facility covered by Contractor the applicable request for payment in accordance with the documents.
▇. ▇▇▇▇▇▇▇ (15) days after the Owner has received the funds with which to make the progress payment from a department or agency of the federal or state government, if any funds for the facility are to come from either of these sources. To assure proper performance of the Contract Documents by the Contractor, the Owner shall retain ten percent (10%) of the dollar value of all work in place until the work is fifty percent (50%) in place. After the work is fifty percent (50%) in place, additional retainage shall not be withheld unless the Owner determines that the Contractor is not making satisfactory progress, or for other specific cause relating to the Contractor's performance under the Contract. In the event of such a determination the Owner may retain up to the date of such termination but not to exceed ten percent (and not cancelable or refundable), plus (ii10%) the pro rata portion of Contractor’s Fee thereon (subject to satisfaction of the conditions applicable to progress and Final Payment contained dollar value of the work more than fifty percent (50%) in place. Any funds retained by the Contract Documents as the case may be), but the foregoing amounts Owner shall not exceed the portion prorated share of the Guaranteed Maximum Price Owner's matching requirement if the project is funded, in part, with federal or state funds. Any retained funds shall not be commingled with other funds of the Owner and shall be deposited in an interest-bearing account in a regulated financial institution. At any time after ninety-four percent (including Contractor’s Fee94%) fairly allocable to of the Work so completed, exceeds
(b) the total of (i) all payments theretofore made to Contractor work under the Contract Documents, is in place and (ii) all damages and other costs and expenses incurred by Owner directly or indirectly, arising out at the request of or as a result of, the Contractor’s breach or default, including, without limitation, the cost Owner shall release the retainage plus interest, only if the Contractor provides to the Owner an irrevocable letter of any additional consultants’ services, or managerial and administrative services required thereby, any additional costs incurred credit in retaining another contractor or other Subcontractors, any additional financing, interest or fees and other costs that Owner must pay by reason of a delay in completion the amount of the Workretainage plus interest, Owner’s termination issued by a bank authorized to do business in the State of Michigan, containing terms mutually acceptable to the Contractor and the finishing of the Work by another method after such termination, attorneys’ fees and expenses, and any other damages, costs, and expenses Owner may incur in completing the Work as a result of Contractor’s breach or default including if Owner elects to complete the Project after such termination, the amount by which the actual cost of completing the Project (including components of the Project that are not part of the Work) is greater than what such actual cost (including the actual cost of components of the Project that are not part of the Work) would have been if Contractor had fulfilled its obligations under the Contract Documents, and if Owner elects to not complete the Project after such termination Contractor hereby acknowledges that Owner has the right to so elect without Owner waiving Contractor’s liability for damages arising out of the breach by Contractor that led to its termination, all damages suffered by Owner arising out of Contractor’s breach of this Agreement.
17.1.5.2 If the amount referred to in Section 17.1.5.1.(b) hereinabove exceeds the amount referred to in Section 17.1.
(a) hereinabove, Contractor Owner. Retainage shall pay the difference to Owner immediately upon Owner’s demand.
17.1.5.3 Any reimbursements or payments made to Contractor under this Section 17.1.5 are conditioned on (a) Contractor previously having delivered to Owner possession and unfettered access be released to the Work and Site and all materials, equipment, tools and Contractor together with the like (undamaged and in good condition) which Owner has paid for and/or been billed for, (b) all the applicable items listed in, and performance of all the applicable obligations described in Section 12.2.1 of this Agreement have been satisfied, and (c) Contractor complies with such other obligations under the Contract Documents as Owner or Owner’s Lenders reasonably requires.final progress payment. GENERAL CONDITIONS
Appears in 1 contract
Sources: Water Tower Contract
Payment to Contractor. 17.1.5.1 If Owner terminates the Contract for Contractor’s breach or default, Contractor shall thereafter only be entitled to reimbursement (subject to Section 17.1.5.3 hereof) only of such amount (if any), by which:
(a) the (i) Cost of the Work actually and properly completed by Contractor in accordance with the Contract Documents up to the date of such termination (and not cancelable or refundable), plus (ii) the pro rata portion of the Original Project Contractor’s Fee or Expansion Project Contractor’s Fee thereon (subject to satisfaction of the conditions applicable to progress and the Original Project Final Payment or Expansion Project Final Payment contained in the Contract Documents as the case may be), but the foregoing amounts shall not exceed the portion of the Original Project Guaranteed Maximum Price or Expansion Project Guaranteed Maximum Price (including the Original Project Contractor’s FeeFee or Expansion Project Contractor’s Fee , respectively) fairly allocable to the Work so completed, exceeds
(b) the total of (i) all payments theretofore made to Contractor under the Contract Documents, and (ii) all damages and other costs and expenses incurred by Owner directly or indirectly, arising out of or as a result of, Contractor’s breach or default, including, without limitationbut not limited to, the cost of any additional consultants’ services, or managerial and administrative services required thereby, any additional costs incurred in retaining another contractor or other Subcontractorssubcontractors, any additional financing, interest or fees and other costs that Owner must pay by reason of a delay in completion of the Work, Owner’s termination of Contractor and the finishing of the Work by another method after such termination, attorneys’ fees and expenses, and any other damages, costs, and expenses Owner may incur in completing the Work as a result of Contractor’s breach or default including if Owner elects to complete the Project after such termination, the amount by which the actual cost of completing the Project (including components of the Project that are not part of the Work) is greater than what such actual cost (including the actual cost of components of the Project that are not part of the Work) would have been if Contractor had fulfilled its obligations under the Contract Documents, and if Owner elects to not complete the Project after such termination (Contractor hereby acknowledges acknowledging that Owner has the right to so elect without Owner waiving Contractor’s liability for damages arising out of the breach by Contractor that led to its termination), all damages suffered by Owner arising out of Contractor’s breach of this Agreement; provided that the amount specified in this clause (b) shall be reduced by any amounts received by Owner under the On-Demand Bond referred to in Section 7.18.
17.1.5.2 If the amount referred to in Section 17.1.5.1.(b) hereinabove exceeds the amount referred to in Section 17.1.
(a17.1.5.1.(a) hereinabove, Contractor shall pay the difference to Owner immediately upon Owner’s demandrequest, subject to the provisions of Section 14.7.
17.1.5.3 Any reimbursements or payments made to Contractor under this Section 17.1.5 are conditioned on (a) Contractor previously having delivered to Owner possession and unfettered access to the Work and Site and all materials, equipment, tools and the like (undamaged and in good condition) which Owner has paid for and/or been billed or will pay for, (b) all the applicable items listed in, and performance of all the applicable obligations described in Section 12.2.1 of this Agreement have been satisfied, and (c) Contractor complies with such other obligations under the Contract Documents accruing prior to termination or that by their nature survive the termination of this Agreement as Owner or Owner’s Lenders reasonably requires.
Appears in 1 contract