Performance of Changes. In the event the parties are unable to agree on the adjustments applicable to a Change or acceleration in schedule, then GEC shall, if directed by Owner, nevertheless proceed to perform such Change or accelerate the schedule so long as GEC is paid the costs and charges incurred in performing such Change or accelerating the schedule. GEC shall not pursuant to this Section 6.6, be required to perform any Change to the Work directed by Owner that would impair GEC’s ability to meet the Guaranteed Completion Date, or Performance Guarantees without an agreed upon adjustment to the Project Schedule or Guaranteed Completion Date.
Appears in 4 contracts
Samples: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement (USA Synthetic Fuel Corp), Engineering, Procurement and Construction Agreement (USA Synthetic Fuel Corp)
Performance of Changes. In the event the parties are unable to agree on the adjustments applicable to a Change or acceleration in schedule, then GEC Contractor shall, if directed by OwnerGEC, nevertheless proceed to perform such Change or accelerate the schedule so long as GEC Contractor is paid the costs and charges incurred in performing such Change or accelerating the schedule. GEC Contractor shall not pursuant to this Section 6.6, be required to perform any Change to the Work directed by Owner GEC that would impair GECContractor’s ability to meet the Guaranteed Completion Date, or Performance Guarantees without an agreed upon adjustment to the Project Schedule or Guaranteed Completion Date.
Appears in 2 contracts
Samples: Engineering, Procurement and Construction Agreement, Engineering, Procurement and Construction Agreement (Global Energy, Inc.)