Common use of Period of Performance and Liquidated Damages Clause in Contracts

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar days, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of ($500.00) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 3 contracts

Samples: Cosumnes Community Services District Construction Contract, Cosumnes Community Services, Cosumnes Community Services District Construction Contract

AutoNDA by SimpleDocs

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 30 Calendar days, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of ($500.00) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 2 contracts

Samples: Cosumnes Community Services District Construction Contract, Cosumnes Community Services District Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar daysbefore December 15, 2022, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the DistrictCity. Such schedules or milestones may be included as part of Exhibits Attachment “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District City will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District City as fixed and liquidated damages the sum of ($500.00) 3,000 per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: City of Coachella Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar daysby February 15, 2020, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of five hundred dollars a day ($500.00) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Cosumnes Community Services District Construction Contract

Period of Performance and Liquidated Damages. 3.5.1 Contractor shall perform and complete all Work under this Contract within 45 Calendar 30 working days, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the DistrictTown. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District Town will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District Town as fixed and liquidated damages the sum of ($500.00) 100 per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Form Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar daysby May 31, 2019, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of Five Hundred dollars ($500.00) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Cosumnes Community Services District Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar 20 working days, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of five hundred dollars ($500.00) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Cosumnes Community Services District Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 75 Calendar days, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of ($500.00) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Cosumnes Community Services District Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar 30 days, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the DistrictCity. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, hereto or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District City will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District City as fixed and liquidated damages the sum of Two Hundred and Fifty Dollars ($500.00250) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule schedule, or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Form Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar working days, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of ($500.00) 500.00 per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.. 82187.00211\30316178.1

Appears in 1 contract

Samples: Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 60 Calendar days, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of ($500.00) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Cosumnes Community Services District Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar daysby February 15, 2020, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of five hundred dollars ($500.00) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Cosumnes Community Services District Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar working days, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of ($500.00) N/A per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.. 82187.00211\30316178.1

Appears in 1 contract

Samples: Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar daysby May 31, 2021, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of five hundred dollars a day ($500.00n/a) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Cosumnes Community Services District Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar daysby , beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of ($500.00) five hundred dollars per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Cosumnes Community Services District Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar daysbefore December 15, 2022, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the DistrictCity. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District City will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District City as fixed and liquidated damages the sum of ($500.00) 3,000 per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Coachella Construction Contract

AutoNDA by SimpleDocs

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar 140 calendar days, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of one thousand dollars ($500.001,000.00) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: District Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar daysby , beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of five hundred dollars a day ($500.00n/a) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Cosumnes Community Services District Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar 90 calendar days, beginning the effective date of the Notice to Proceed ("Contract Time"). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “Exhibit "A” or “B” " attached hereto, or may be provided separately in writing to the Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District Distrct will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of One Hundred Dollars ($500.00100) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Crescent City Harbor District

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar daysby October 31, 2019, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of five hundred dollars a day ($500.00) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Cosumnes Community Services District Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar daysby October 31, 2019, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of Five Hundred dollars ($500.00) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Cosumnes Community Services District Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar daysby May 31, 2019, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the District. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District as fixed and liquidated damages the sum of five hundred dollars a day ($500.00) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Cosumnes Community Services District Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar days30 Working Days, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the DistrictCity. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, hereto or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District City will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District City as fixed and liquidated damages the sum of Five Hundred Dollars ($500.00) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule schedule, or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Form Construction Contract

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar 90 days, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the DistrictCity. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District City will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District City as fixed and liquidated damages the sum of FIVE HUNDRED DOLLARS ($500.00500) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Rack Power

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar 30 days, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the DistrictAuthority. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, hereto or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District Authority will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District Authority as fixed and liquidated damages the sum of Five Hundred Dollars ($500.00) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule schedule, or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: pub-palmdesert.escribemeetings.com

Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 45 Calendar days20 Working Days, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the DistrictCity. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto, or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the District City will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the District City as fixed and liquidated damages the sum of ($500.00) 450.00 per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule or Project milestones established pursuant to the Contract.

Appears in 1 contract

Samples: Davis Construction Contract