Planned Work. 27.10.1 Where planned work to be performed by a Party may affect the safety of the other Party=s personnel, the Party performing the work shall provide the other Party with all required Work Protection documentation and related notices in writing or by such other means as they may agree in writing. 27.10.2 Where planned work on the facilities of a Party: (a) requires the participation or cooperation of the other Party; or (b) could adversely affect the normal operation of the other Party=s facilities, the other Party shall use commercially reasonable efforts to accommodate the planned work and shall negotiate in good faith the reasonable procedures and cost sharing criteria applicable to the planned work. 27.10.3 The Customer shall take all reasonable steps to ensure that all anticipated and planned outages of its facilities for each calendar year are submitted to the Transmitter by October 1st of the preceding year. 27.10.4 All planned work on the Customer=s facilities that may affect the Transmitter=s transmission facilities shall be scheduled by the Customer with the Transmitter=s Controlling Authority. 27.10.5. Where the Customer plans work on its facilities that: (a) requires a feeder breaker to be opened or operated; (b) requires any disconnection or isolation from any facilities of either Party that are less than 50 kV, such as a feeder breaker; (c) will result in load changes of greater than 5 MW; or (d) will involve a load transfer or a switching operation that directly affects the Transmitter=s transmission facilities, the Customer=s Controlling Authority shall submit a request to the Transmitter=s representative identified in Schedule A, including a request to provide a Supporting Guarantee where applicable. Such request shall be submitted in writing and shall be submitted at least four days in advance of the planned work or within such other period as the Parties may agree.
Appears in 2 contracts
Samples: Connection Agreement for Load Customers, Connection Agreement
Planned Work. 27.10.1 27.10.1. Where planned work to be performed by a Party may affect the safety of the other Party=s ’s personnel, the Party performing the work shall provide the other Party with all required Work Protection documentation and related notices in writing or by such other means as they may agree in writing.
27.10.2 27.10.2. Where planned work on the facilities of a Party:
(a) requires the participation or cooperation of the other Party; or
(b) could adversely affect the normal operation of the other Party=s ’s facilities, the other Party shall use commercially reasonable efforts to accommodate the planned work and shall negotiate in good faith the reasonable procedures and cost sharing criteria applicable to the planned work.
27.10.3 27.10.3. The Customer shall take all reasonable steps to ensure that all anticipated and planned outages of its facilities for each calendar year are submitted to the Transmitter by October 1st of the preceding year.
27.10.4 27.10.4. All planned work on the Customer=s ’s facilities that may affect the Transmitter=s ’s transmission facilities shall be scheduled by the Customer with the Transmitter=s ’s Controlling Authority.
27.10.5. Where the Customer plans work on its facilities that:
(a) requires a feeder breaker to be opened or operated;
(b) requires any disconnection or isolation from any facilities of either Party that are less than 50 kV, such as a feeder breaker;
(c) will result in load power flow changes of greater than 5 MW; or
(d) will involve a load transfer or a switching operation that directly affects the Transmitter=s ’s transmission facilities, the Customer=s ’s Controlling Authority shall submit a request to the Transmitter=s ’s representative identified in Schedule A, including a request to provide a Supporting Guarantee where applicable. Such request shall be submitted in writing and shall be submitted at least four days in advance of the planned work or within such other period as the Parties may agree.
Appears in 2 contracts
Samples: Connection Agreement, Connection Agreement
Planned Work. 27.10.1 Where planned work to be performed by a Party may affect the safety of the other Party=s ’s personnel, the Party performing the work shall provide the other Party with all required Work Protection documentation and related notices in writing or by such other means as they may agree in writing.
27.10.2 Where planned work on the facilities of a Party:
(a) requires the participation or cooperation of the other Party; or
(b) could adversely affect the normal operation of the other Party=s ’s facilities, the other Party shall use commercially reasonable efforts to accommodate the planned work and shall negotiate in good faith the reasonable procedures and cost sharing criteria applicable to the planned work.
27.10.3 The Customer shall take all reasonable steps to ensure that all anticipated and planned outages of its facilities for each calendar year are submitted to the Transmitter by October 1st of the preceding year.
27.10.4 All planned work on the Customer=s ’s facilities that may affect the Transmitter=s ’s transmission facilities shall be scheduled by the Customer with the Transmitter=s ’s Controlling Authority.
27.10.5. Where the Customer plans work on its facilities that:
(a) requires a feeder breaker to be opened or operated;
(b) requires any disconnection or isolation from any facilities of either Party that are less than 50 kV, such as a feeder breaker;
(c) will result in load changes of greater than 5 MW; or
(d) will involve a load transfer or a switching operation that directly affects the Transmitter=s ’s transmission facilities, the Customer=s ’s Controlling Authority shall submit a request to the Transmitter=s ’s representative identified in Schedule A, including a request to provide a Supporting Guarantee where applicable. Such request shall be submitted in writing and shall be submitted at least four days in advance of the planned work or within such other period as the Parties may agree.
Appears in 2 contracts
Samples: Connection Agreement, Connection Agreement
Planned Work. 27.10.1 27.10.1. Where planned work to be performed by a Party may affect the safety of the other Party=s personnel, the Party performing the work shall provide the other Party with all required Work Protection documentation and related notices in writing or by such other means as they may agree in writing.
27.10.2 27.10.2. Where planned work on the facilities of a Party:
(a) requires the participation or cooperation of the other Party; or
(b) could adversely affect the normal operation of the other Party=s facilities, the other Party shall use commercially reasonable efforts to accommodate the planned work and shall negotiate in good faith the reasonable procedures and cost sharing criteria applicable to the planned work.
27.10.3 27.10.3. The Customer shall take all reasonable steps to ensure that all anticipated and planned outages of its facilities for each calendar year are submitted to the Transmitter by October 1st of the preceding year.
27.10.4 27.10.4. All planned work on the Customer=s facilities that may affect the Transmitter=s transmission facilities shall be scheduled by the Customer with the Transmitter=s Controlling Authority.
27.10.5. Where the Customer plans work on its facilities that:
(a) requires a feeder breaker to be opened or operated;
(b) requires any disconnection or isolation from any facilities of either Party that are less than 50 kV, such as a feeder breaker;
(c) will result in load power flow changes of greater than 5 MW; or
(d) will involve a load transfer or a switching operation that directly affects the Transmitter=s transmission facilities, the Customer=s Controlling Authority shall submit a request to the Transmitter=s representative identified in Schedule A, including a request to provide a Supporting Guarantee where applicable. Such request shall be submitted in Deleted: Proposed Revised Transmission System Code, Appendix 1 (version B) 43 writing and shall be submitted at least four days in advance of the planned work or within such other period as the Parties may agree.
Appears in 1 contract
Samples: Connection Agreement
Planned Work. 27.10.1 27.10.1. Where planned work to be performed by a Party may affect the safety of the other Party=s ’s personnel, the Party performing the work shall provide the other Party with all required Work Protection documentation and related notices in writing or by such other means as they may agree in writing.
27.10.2 27.10.2. Where planned work on the facilities of a Party:
(a) requires the participation or cooperation of the other Party; or
(b) could adversely affect the normal operation of the other Party=s ’s facilities, the other Party shall use commercially reasonable efforts to accommodate the planned work and shall negotiate be undertaken in good faith the reasonable accordance with such procedures and cost sharing criteria applicable to as the planned workParties may agree.
27.10.3 27.10.3. The Customer shall take all reasonable steps to ensure that all anticipated and planned outages of its facilities for each calendar year are submitted to the Transmitter by October 1st of the preceding year.
27.10.4 27.10.4. All planned work on the Customer=s ’s facilities that may affect the Transmitter=s ’s transmission facilities shall be scheduled by the Customer with the Transmitter=s ’s Controlling Authority.
27.10.5. Where the Customer plans The Customer’s Controlling Authority shall, at least four days in advance of planned work on its facilities that:
(a) requires a feeder breaker to be opened or operated;
(b) requires any disconnection or isolation from any facilities of either Party that are less than 50 kV, such as a feeder breaker;
(c) will result in load changes of greater than 5 MW; or
(d) will involve a load transfer or a switching operation that directly affects the Transmitter=s ’s transmission facilities, the Customer=s Controlling Authority shall submit a request to the Transmitter=s ’s representative identified in Schedule A, including a request A to provide a Supporting Guarantee where applicableCondition Guarantee. Such request shall be submitted in writing and shall be submitted at least four days in advance of the planned work or within such other period as the Parties may agreewriting.
Appears in 1 contract
Samples: Connection Agreement
Planned Work. 27.10.1 27.10.1. Where planned work to be performed by a Party may affect the safety of the other Party=s personnel, the Party performing the work shall provide the other Party with all required Work Protection documentation and related notices in writing or by such other means as they may agree in writing.
27.10.2 27.10.2. Where planned work on the facilities of a Party:
(a) requires the participation or cooperation of the other Party; or
(b) could adversely affect the normal operation of the other Party=s facilities, the other Party shall use commercially reasonable efforts to accommodate the planned work and shall negotiate in good faith the reasonable procedures and cost sharing criteria applicable to the planned work.
27.10.3 27.10.3. The Customer shall take all reasonable steps to ensure that all anticipated and planned outages of its facilities for each calendar year are submitted to the Transmitter by October 1st of the preceding year.
27.10.4 27.10.4. All planned work on the Customer=s facilities that may affect the Transmitter=s transmission facilities shall be scheduled by the Customer with the Transmitter=s Controlling Authority.
27.10.5. Where the Customer plans work on its facilities that:
(a) requires a feeder breaker to be opened or operated;
(b) requires any disconnection or isolation from any facilities of either Party that are less than 50 kV, such as a feeder breaker;
(c) will result in load power flow changes of greater than 5 MW; or
(d) will involve a load transfer or a switching operation that directly affects the Transmitter=s transmission facilities, the Customer=s Controlling Authority shall submit a request to the Transmitter=s representative identified in Schedule A, including a request to provide a Supporting Guarantee where applicable. Such request shall be submitted in writing and shall be submitted at least four days in advance of the planned work or within such other period as the Parties may agree.
Appears in 1 contract
Samples: Connection Agreement
Planned Work. 27.10.1 27.10.1. Where planned work to be performed by a Party may affect the safety of the other Party=s ’s personnel, the Party performing the work shall provide the other Party with all required Work Protection documentation and related notices in writing or by such other means as they may agree in writing.
27.10.2 27.10.2. Where planned work on the facilities of a Party:
(a) requires the participation or cooperation of the other Party; or
(b) could adversely affect the normal operation of the other Party=s ’s facilities, the other Party shall use commercially reasonable efforts to accommodate the planned work and shall negotiate in good faith the reasonable procedures and cost sharing criteria applicable to the planned work.,
27.10.3 27.10.3. The Customer shall take all reasonable steps to ensure that all anticipated and planned outages of its facilities for each calendar year are submitted to the Transmitter by October 1st of the preceding year.
27.10.4 27.10.4. All planned work on the Customer=s ’s facilities that may affect the Transmitter=s ’s transmission facilities shall be scheduled by the Customer with the Transmitter=s ’s Controlling Authority.
27.10.5. The Customer’s Controlling Authority shall, at least four days in advance of planned Where the Customer plans work on its facilities that:
(a) requires a feeder breaker to be opened or operated;
(b) requires any disconnection or isolation from any facilities of either Party that are less than 50 kV, such as a feeder breaker;
(c) will result in load changes of greater than 5 MW; or
(d) will involve a load transfer or a switching operation that directly affects the Transmitter=s ’s transmission facilities, the Customer=s ’s Controlling Authority shall submit a request to the Transmitter=s ’s representative identified in Schedule A, including a request to provide a Supporting ConditionSupporting Guarantee where applicable. Such request shall be submitted in writing and shall be submitted at least four days in advance of the planned work or within such other period as the Parties may agreewriting.
Appears in 1 contract
Samples: Connection Agreement