Preliminary Project Baseline Schedule. The Proposal shall provide a Preliminary Project Baseline Schedule and narrative for all portions of the Project and include at least the following: (a) Narrative which describes the proposed execution of the work for the term of the Development Agreement. (b) A description of the approach used for preparing, controlling and updating the Baseline Schedule, for calculating progress performance on a monthly basis, and preparing Payment Requests on a quarterly basis;
Appears in 3 contracts
Samples: Development Agreement, Development Agreement, Development Agreement
Preliminary Project Baseline Schedule. The Proposal shall provide a Preliminary Project Baseline Schedule and narrative for all portions of the Project and include at least the following:
(a) Narrative which describes the proposed execution of the work for the term of the Development Agreement.
(b) A description of the approach used for preparing, controlling and updating the Baseline Schedule, for calculating progress performance performance, and preparing Draw Requests on a monthly basis, and preparing Payment Requests on a quarterly basis;
Appears in 3 contracts
Samples: Development Agreement, Development Agreement, Development Agreement