Construction Cost Budget. The total cost to District of all elements of the Project designed or specified by the Architect, as adjusted during and at the end of the design phase in accordance with this Agreement and the Agreement for Architectural Services. The Construction Cost Budget does not include the compensation of the Project Design Team, the Program Manager (if any), the Construction Manager and any subconsultants, the cost of the land, rights-of-way, or financing which are the responsibility of the District.
Construction Cost Budget. Revise the Construction Cost Budget for the Project. Along with the conditions identified in the preceding Phase, the following conditions apply to the revised Construction Cost Budget:
Construction Cost Budget. 5.1. Architect hereby accepts the District’s established Construction Cost Budget and Project scope. In accordance with Exhibit “A,” the Architect shall have responsibility to further develop, review, and reconcile the Construction Cost Budget for the District at the beginning of the Project and at the completion of each design phase. The District and Construction Manager shall also have responsibility to develop, review, and reconcile the Construction Cost Budget with the Architect.
5.2. Architect shall complete all Services as described in Exhibit “A,” including all plans, designs, drawings, specifications and other Contract Documents, so that the cost to construct the work designed by the Architect will not exceed the Construction Cost Budget, as adjusted subsequently with the District’s written approval. Architect shall maintain cost controls throughout the Project to deliver the Project within the Construction Cost Budget.
5.3. The District may, in its sole discretion, do one, or a combination, of the following if any of the events in Article 5.4 occur:
5.3.1. Give Architect written approval on an agreed adjustment to the Construction Cost Budget.
5.3.2. Authorize Architect to re-negotiate, when appropriate, and/or re-bid the Project within three (3) months’ time of receipt of bids (exclusive of District and other agencies’ review time) at no additional cost to the District.
5.3.3. Terminate this Agreement if the Project is abandoned by the District, without further obligation by either party.
5.3.4. Within three (3) months’ time of receipt of bids, instruct Architect to revise the drawings and specifications (in scope and quality as approved by the District) to bring the Project within the Construction Cost Budget for re-bidding at no additional cost to the District.
5.4. If any of the following events occur, the District may exercise any one, or any combination, of the actions set forth in Article 5.3 above:
5.4.1. The lowest responsive base bid received is in excess of five percent (5%) of the Construction Cost Budget; or
5.4.2. If the combined total of base bid and all additive alternates come in ten percent (10%) or more under the Construction Cost Budget; or
5.4.3. If the Construction Cost Budget increases in phases subsequent to the Schematic Design Phase due to reasonably foreseeable changes in the condition of the construction market in the county in which the District is located, in so far as these have not been caused by Acts of God, earthq...
Construction Cost Budget. (i) Revise the Construction Cost Budget for the Project. Along with the conditions identified in the preceding phases, Architect shall update and refine the Schematic Design Construction Cost Budget.
(ii) The Construction Cost Budget for the Project must at no point exceed the relevant portion of the District’s Project Budget. The accuracy of the Construction Cost Budget shall be the responsibility of the Architect.
(iii) The Architect shall submit its proposed Construction Cost Budget to the District and the Construction Manager for review and approval. At that time, the Architect shall coordinate with the District and the Construction Manager to further develop, review, and reconcile the Construction Cost Budget.
(iv) At this stage of the design, the Construction Cost Budget shall not include any design contingencies in excess of the cost estimates.
Construction Cost Budget. 5.1 The Construction Manager shall have responsibility, along with the Architect, to develop, review, and reconcile the Construction Cost Budget with the Architect and the District throughout the design process and construction.
5.2 The Construction Cost Budget shall be the total cost to District of all elements of the Project designed or specified by the Project design professional(s), as defined in Article 1.
5.3 Construction Manager shall work cooperatively with the Project Design Team throughout the Project, including but not limited to, the Schematic Design Phase, Design Development Phase, and Construction Documents Phase, as described in Exhibit “A,” so that the construction cost of the work designed by the Project Design Team will not exceed the Construction Cost Budget, as may be adjusted subsequently with the District’s written approval. The Construction Manager shall notify the District if it believes the construction cost of the work by the Project Design Team will exceed the Construction Cost Budget, and/or if it believes the construction cost of the Project will exceed the Construction Cost Budget for the Project. The Construction Manager, however, shall not perform or be responsible for any design or architectural services.
5.4 Evaluations of the District’s Construction Budget, and preliminary and detailed cost estimates prepared by the Construction Manager, represent the Construction Manager’s best judgment as a professional familiar with the construction industry.
5.5 If the Bidding Phase has not commenced within ninety (90) days after DSA approval, the Construction Cost Budget may be adjusted at District’s request to reflect changes in the general level of prices in the construction industry between the date of submission of the Construction Documents to the District and the date on which proposals are sought.
5.6 The District may, in its sole discretion, do one, or a combination, of the following if any of the events in Article 5.7 occur:
5.6.1 Give Construction Manager written approval of an agreed adjustment to the Construction Cost Budget.
5.6.2 Authorize Construction Manager to re-negotiate, when appropriate, and/or re-bid the Project within three (3) months time of receipt of bids (exclusive of District and other agencies’ review time) at no additional cost to the District.
5.6.3 Terminate this Agreement if the Project is abandoned by the District, without further obligation by either party.
5.6.4 Within three (3) months of receipt o...
Construction Cost Budget. 5.1.8.1. Revise the Construction Cost Budget for the Project. Along with the conditions identified in the preceding phases, Architect shall update and refine the Design Development Phase revisions to the Construction Cost Budget. Architect shall provide a Construction Cost Budget sorted by the Project Bid Packages.
5.1.8.2. The Construction Cost Budget for the Project must at no point exceed the District’s Project Budget allocation for construction. The accuracy of the Construction Cost Budget shall be the responsibility of the Architect.
5.1.8.3. The Architect shall submit its proposed Construction Cost Budget to the District and the Construction Manager for review and approval. At that time, the Architect shall coordinate with the District and the Construction Manager to further develop, review, and reconcile the Construction Cost Budget.
5.1.8.4. At this stage of the design, the Construction Cost Budget may include design contingencies of no more than 5% in the cost estimates.
Construction Cost Budget. Revise the Construction Cost Budget for the Project. Along with the conditions identified in the preceding Phase, the following conditions apply to the revised Construction Cost Budget:
a. Schematic Estimates: This estimate consists of unit cost applied to the major items and quantities of work. The unit cost shall reflect the complete direct current cost of work. Complete cost includes labor, material, waste allowance, sales tax and subcontractor's mark-up.
(i) General conditions shall be applied separately. This estimate shall be prepared by specification section and summarized by the CSI categories.
b. The estimate shall separate the Project's building cost from site and utilities cost. Architect shall submit to the District the cost estimating format for prior review and approval.
Construction Cost Budget. 2.2.6.1. Architect shall have responsibility to further develop review, and reconcile the Construction Cost Budget within the parameters of the Project Budget established in the District’s implementation plan. The estimates forming the basis of the Construction Cost Budget are to be based on the developed functional architectural programs as approved by the District. The following conditions apply to the Construction Cost Budget prepared by the Architect:
2.2.6.1.1. All costs are to be based on current bid prices, with escalation rate and duration clearly identified as a separate line item; rate of cost escalation and projected bid and construction dates are to be as approved by the District and its representatives.
2.2.6.1.2. Format shall be in a building systems format (e.g., foundations, substructure, structural system, exterior wall enclosure, window systems, etc.) for new buildings, and summarized by the Construction Specification Institute (CSI) category for buildings being modernized.
2.2.6.1.3. Contingencies for design, bidding, and construction are to be included as individual line items, with the percentage and base of calculation clearly identified.
2.2.6.1.4. The Architect shall include all information and estimates from the District and/or the Construction Manager that are intended to be part of the Construction Cost Budget.
2.2.6.1.5. One week prior to submittal of documents, the Architect shall submit its proposed Construction Cost Budget to the District and the Construction Manager for review and approval. At that time, the Architect shall coordinate with the District and the Construction Manager to further develop, review, and reconcile the Construction Cost Budget.
2.2.6.1.6. Mechanical, electrical, civil, landscape and estimating consultant(s) shall participate in the progress meeting as appropriate and shall provide input and feedback into the development of the Construction Cost Budget.
2.2.6.2. The Construction Cost Budget for the Project must at no point exceed the District’s Project Budget allocation for construction. The accuracy of the Construction Cost Budget shall be the responsibility of the Architect.
Construction Cost Budget a. Architect shall have responsibility to further develop, review, and reconcile the Construction Cost Budget within the parameters of the Construction Budget established by District for the Project. The estimates forming the basis of the Construction Cost Budget are to be based on the developed functional architectural program as approved by District. The following conditions apply to the Construction Cost Budget prepared by Architect:
(i) All costs are to be based on current bid prices, with escalation rate and duration clearly identified as a separate line item; rate of cost escalation and projected bid and construction dates are to be approved by District and its representatives.
(ii) Format shall be in a building systems format (e.g., foundations, substructure, structural system, exterior wall enclosure, window systems, etc.) for new buildings, and summarized by the Construction Specification Institute (“CSI”) categories for buildings being modernized.
(iii) Contingencies for design, bidding, and construction are to be included as individual line items, with the percentage and base of calculation clearly identified.
(iv) Architect shall include all information and estimates from District and/or the Construction Manager that are intended to be part of the Construction Cost Budget.
(v) One week prior to submittal of documents, Architect shall submit its proposed Construction Cost Budget to District and the Construction Manager for review and approval. At that time, Architect shall coordinate with District and the Construction Manager to further develop, review, and reconcile the Construction Cost Budget.
Construction Cost Budget. 5.1. The Construction Manager shall have responsibility to develop, review, and reconcile the Construction Cost Budget with the Architect and the District throughout the design process and construction.
5.2. The Construction Cost Budget shall be the total cost to District of all elements of the Project designed or specified by the Project design professional(s). The Construction Cost Budget does not include the compensation of the Construction Manager, the Project design professional(s), sub-consultants, the cost of the land, rights-of-way, financing or other costs which are the responsibility of the District.
5.3. Construction Manager shall work cooperatively with the Project design professional(s) during the Schematic Design Phase, Design Development Phase, and Construction Documents Phase, as described in Exhibit “A,” so that the construction cost of the work designed by the Project design professional(s) will not exceed the Construction Cost Budget, as may be adjusted subsequently with the District’s written approval. The Construction Manager shall notify the District if it believes the construction cost of the work by the Project design profession(s) will exceed the Construction Cost Budget. The Construction Manager, however, shall not perform or be responsible for any design or architectural services.
5.4. Evaluations of the District’s Construction Budget, and preliminary and detailed cost estimates prepared by the Construction Manager, represent the Construction Manager’s best judgment as a professional familiar with the construction industry.
5.5. If the Bidding Phase has not commenced within ninety (90) days after DSA approval, the Construction Cost Budget shall be adjusted to reflect changes in the general level of prices in the construction industry between the date of submission of the Construction Documents to the District and the date on which proposals are sought.
5.6. If any of the following events occur:
5.6.1. If the lowest responsive base bid received is in excess of ten percent (10%) of the Construction Cost Budget, or
5.6.2. If the combined total of base bid and all additive alternates come in fifteen percent (15%) or more under the Construction Cost Budget, or
5.6.3. If the Construction Cost Budget increases in phases subsequent to the Schematic Design Phase due to reasonably foreseeable changes in the condition of the construction market in the county in which the District is located, in so far as these have not been caused by Acts o...