Common use of Price Increases Clause in Contracts

Price Increases. 6.2.1.1. Contractor may request an increase in the prices listed in Exhibit C by submitting its request to the State in writing as described in §17 of the main body of this Contract. Requests for increases in prices are limited as follows: 6.2.1.1.1. Contractor may not request a price increase during the first 12 months of this Contract. 6.2.1.1.2. Contractor may not request a price increase within any 12-month period following the State’s approval of a price increase under this section. 6.2.1.1.3. Contractor may not submit a request for a price increase to the State fewer than 60 days prior to when Contractor intends those increased prices to be effective. 6.2.1.1.4. Contractor may only request a price increase if it can justify that increase based on the Producer Price Index or the Consumer Price Index issued by the US Department of Labor, Bureau of Labor Statistics; or a similar industry pricing guide. 6.2.1.2. The State may approve or deny any request for a price increase based on the information provided by Contractor and other circumstances in its sole discretion. 6.2.1.3. If the State approves a price increase, that price increase shall not take effect unless it is included in this Contract. The State may increase the prices in Exhibit E through the use of an Option Letter. 6.2.1.3.1. Contractor may only begin using the increased prices in Orders that are issued following the effective date of the modification that increases the prices. For Orders placed prior to a price increase that are in effect at the time of the price increase, Contractor shall only charge the Purchasing Entity the prices that were in effect at the time the Order was placed. 6.2.1.4. If the State does not approve a price increase, or Contractor increases its prices without submitting a request to the State, then those increased prices shall be void in any Order in which they are used and Contractor shall fulfill the Order at the existing rates approved by the State under this Contract. Contractor’s use of rates in any Order that exceed those approved by the State under this Contract shall be a material breach of this Contract.

Appears in 10 contracts

Samples: Price Agreement, Price Agreement, Price Agreement

AutoNDA by SimpleDocs

Price Increases. 6.2.1.17.2.1.1. Contractor may request an increase in the prices listed in Exhibit C by submitting its request to the State in writing as described in §17 of the main body of this Contract. Requests for increases in prices are limited as follows: 6.2.1.1.17.2.1.1.1. If a Contractor may not request is requesting a price increase during for the first 12 months extension of this Contractthe Contract the requested increased pricing with justification from the manufacturers must be received by July 31, 2021. 6.2.1.1.2. Contractor may not request a price increase within any 12-month period following the State’s approval of a price increase under this section. 6.2.1.1.3. Contractor may not submit a request for a price increase to the State fewer than 60 days prior to when Contractor intends those increased prices to be effective. 6.2.1.1.47.2.1.1.2. Contractor may only request a price increase if it can provide and justify that increase based on the Original Equipment Manufacturer increase, the Producer Price Index or the Consumer Price Index issued by the US Department of Labor, Bureau of Labor Statistics; or a similar industry pricing guide. 6.2.1.27.2.1.2. The State may approve or deny any request for a price increase based on the information provided by Contractor and other circumstances in its sole discretion. 6.2.1.37.2.1.3. If the State approves a price increase, that price increase shall not take effect unless it is included in this Contract. The State may will increase the prices in Exhibit E through the use of an Option Letteramendment. 6.2.1.3.17.2.1.3.1. Contractor may only begin using the increased prices in Orders that are issued following the effective date of the modification that increases the prices. For Orders placed prior to a price increase that are in effect at the time of the price increase, Contractor shall only charge the Purchasing Entity the prices that were in effect at the time the Order was placed. 6.2.1.47.2.1.4. If the State does not approve a price increase, or Contractor increases its prices without submitting a request to the State, then those increased prices shall be void in any Order in which they are used and Contractor shall fulfill the Order at the existing rates approved by the State under this Contract. Contractor’s use of rates in any Order that exceed those approved by the State under this Contract shall be a material breach of this Contract.

Appears in 5 contracts

Samples: Price Agreement, Price Agreement, Price Agreement

Price Increases. 6.2.1.1. Contractor may request an increase in the prices listed in Exhibit C by submitting its request to the State in writing as described in §17 of the main body of this Contract. Requests for increases in prices are limited as follows: 6.2.1.1.1. Contractor may not request a price increase during the first 12 months of this Contract. 6.2.1.1.2. Contractor may not request a price increase within any 12-month period following follow ing the State’s approval of a price increase under this section. 6.2.1.1.3. Contractor may not submit a request for a price increase to the State fewer than 60 days prior to when Contractor intends those increased prices to be effective. 6.2.1.1.4. Contractor may only request a price increase if it can justify that increase based on the Producer Price Index or the Consumer Price Index issued by the US Department of Labor, Bureau of Labor Statistics; or a similar industry pricing guide. 6.2.1.2. The State may approve or deny any request for a price increase based on the information informat ion provided by Contractor and other circumstances in its sole discretion. 6.2.1.3. If the State approves a price increase, that price increase shall not take effect unless it is included in this Contract. The State may increase the prices in Exhibit E through the use of an Option Letter. 6.2.1.3.1. Contractor may only begin using the increased prices in Orders that are issued following the effective date of the modification that increases the prices. For Orders placed prior to a price increase that are in effect at the time of the price increase, Contractor shall only charge the Purchasing Entity the prices that were in effect at the time the Order was placed. 6.2.1.4. If the State does not approve a price increase, or Contractor increases its prices without submitting a request to the State, then those increased prices shall be void in any Order in which they are used and Contractor shall fulfill the Order at the existing rates approved by the State under this Contract. Contractor’s use of rates in any Order that exceed those approved by the State under this Contract shall be a material breach of this Contract.

Appears in 3 contracts

Samples: Price Agreement, Price Agreement, Price Agreement

Price Increases. 6.2.1.1. Contractor may request an increase in the prices listed in Exhibit C by submitting its request to the State in writing as described in §17 of the main body of this Contract. Requests for increases in prices are limited as follows: 6.2.1.1.1. Contractor may not request adjustments to pricing to be made either as increases or decreases provided that Contractor can provide documentation to the State demonstrating the price change is a price increase during the first 12 months result of this Contractincreases from suppliers. 6.2.1.1.2. Contractor may not request a price increase within any 12-month period following the State’s approval of a price increase under this section. 6.2.1.1.3. Contractor may not submit a request for a price increase to the State fewer than 60 30 days prior to when Contractor intends those increased prices to be effective. 6.2.1.1.46.2.1.1.3. Contractor may only request a price increase if it can justify that increase based on the Producer Price Index or the Consumer Price Index issued by the US Department of Labor, Bureau of Labor Statistics; or a similar industry pricing guideincreases in costs from suppliers. 6.2.1.2. The State may approve or deny any request for a price increase based on the information provided by Contractor and other circumstances in its sole discretion. 6.2.1.3. If the State approves a price increase, that price increase shall not take effect unless it is included in this Contract. The State may increase as of the prices in Exhibit E through effective date of the use of an Option Letterfully executed amendment. 6.2.1.3.1. Contractor may only begin using the increased prices in Orders that are issued following the effective date of the modification that increases the prices. For Orders placed prior to a price increase that are in effect at the time of the price increase, Contractor shall only charge the Purchasing Entity the prices that were in effect at the time the Order was placed. 6.2.1.4. If the State does not approve a price increase, or Contractor increases its prices without submitting a request to the State, then those increased prices shall be void in any Order in which they are used and Contractor shall fulfill the Order at the existing rates approved by the State under this Contract. Contractor’s use of rates in any Order that exceed those approved by the State under this Contract shall be a material breach of this Contract.

Appears in 1 contract

Samples: Price Agreement

Price Increases. 6.2.1.1. Contractor may request an increase in the prices listed in Exhibit C by submitting its request to the State in writing as described in §17 18 of the main body of this Contract. Requests for increases in prices are limited as follows: 6.2.1.1.1. Contractor may not request a price increase during the first 12 months of this Contract. 6.2.1.1.2. Contractor may not request a price increase within any 12-month period following the State’s approval of a price increase under this section. 6.2.1.1.3. Contractor may not submit a request for a price increase to the State fewer than 60 days prior to when Contractor intends those increased prices to be effective. 6.2.1.1.4. Contractor may only request a price increase if it can justify that increase based on the Producer Price Index or the Consumer Price Index issued by the US Department of Labor, Bureau of Labor Statistics; or a similar industry pricing guide. 6.2.1.2. The State may approve or deny any request for a price increase based on the information provided by Contractor and other circumstances in its sole discretion. 6.2.1.3. If the State approves a price increase, that price increase shall not take effect unless it is included in this Contract. The State may increase the prices in Exhibit E through the use of an Option Letter. 6.2.1.3.16.2.1.2.1. Contractor may only begin using the increased prices in Orders that are issued following the effective date of the modification that increases the prices. For Orders placed prior to a price increase that are in effect at the time of the price increase, Contractor shall only charge the Purchasing Entity the prices that were in effect at the time the Order was placed. 6.2.1.46.2.1.3. If the State does not approve a price increase, or Contractor increases its prices without submitting a request to the State, then those increased prices shall be void in any Order in which they are used and Contractor shall fulfill the Order at the existing rates approved by the State under this Contract. Contractor’s use of rates in any Order that exceed those approved by the State under this Contract shall be a material breach of this Contract.

Appears in 1 contract

Samples: Price Agreement

AutoNDA by SimpleDocs

Price Increases. 6.2.1.1. Contractor may request an increase in the prices listed in Exhibit C B by submitting its request to the State in writing as described in §17 16 of the main body of this Contract. Requests for increases in prices are limited as follows: 6.2.1.1.1. Contractor may not request a price increase during the first 12 months of this Contract. 6.2.1.1.2. Contractor may not request a price increase within any 12-month period following the State’s approval of a price increase under this section. 6.2.1.1.3. Contractor may not submit a request for a price increase to the State fewer than 60 days prior to when Contractor intends those increased prices to be effective. 6.2.1.1.4. Contractor may only request a price increase if it can justify that increase based on the Producer Price Index or the Consumer Price Index issued by the US Department of Labor, Bureau of Labor Statistics; or a similar industry pricing guide. 6.2.1.2. The State may approve or deny any request for a price increase based on the information provided by Contractor and other circumstances in its sole discretion. 6.2.1.3. If the State approves a price increase, that price increase shall not take effect unless it is included in this Contract. The State may increase the prices in Exhibit E D through the use of an Option Letter. 6.2.1.3.1. Contractor may only begin using the increased prices in Orders that are issued following the effective date of the modification that increases the prices. For Orders placed prior to a price increase that are in effect at the time of the price increase, Contractor shall only charge the Purchasing Entity the prices that were in effect at the time the Order was placed. 6.2.1.4. If the State does not approve a price increase, or Contractor increases its prices without submitting a request to the State, then those increased prices shall be void in any Order in which they are used and Contractor shall fulfill the Order at the existing rates approved by the State under this Contract. Contractor’s use of rates in any Order that exceed those approved by the State under this Contract shall be a material breach of this Contract.

Appears in 1 contract

Samples: Price Agreement

Price Increases. 6.2.1.1. Contractor may request an increase in the prices listed in Exhibit C B by submitting its request to the State in writing as described in §17 of the main body of this Contract. Requests for increases in prices are limited as follows: 6.2.1.1.1. Contractor may not request a price increase during the first 12 months of this Contract. 6.2.1.1.2. Contractor may not request a price increase within any 12-month period following the State’s approval of a price increase under this section. 6.2.1.1.3. Contractor may not submit a request for a price increase to the State fewer than 60 days prior to when Contractor intends those increased prices to be effective. 6.2.1.1.4. Contractor may only request a price increase if it can justify that increase based on the Producer Price Index or the Consumer Price Index issued by the US Department of Labor, Bureau of Labor Statistics; or a similar industry pricing guide. 6.2.1.2. The State may approve or deny any request for a price increase based on the information provided by Contractor and other circumstances in its sole discretion. 6.2.1.3. If the State approves a price increase, that price increase shall not take effect unless it is included in this Contract. The State may increase the prices in Exhibit E D through the use of an Option Letter. 6.2.1.3.1. Contractor may only begin using the increased prices in Orders that are issued following the effective date of the modification that increases the prices. For Orders placed prior to a price increase that are in effect at the time of the price increase, Contractor shall only charge the Purchasing Entity the prices that were in effect at the time the Order was placed. 6.2.1.4. If the State does not approve a price increase, or Contractor increases its prices without submitting a request to the State, then those increased prices shall be void in any Order in which they are used and Contractor shall fulfill the Order at the existing rates approved by the State under this Contract. Contractor’s use of rates in any Order that exceed those approved by the State under this Contract shall be a material breach of this Contract.

Appears in 1 contract

Samples: Price Agreement

Draft better contracts in just 5 minutes Get the weekly Law Insider newsletter packed with expert videos, webinars, ebooks, and more!