Prior Approval Requirements. Certain items of cost and award revisions require the prior written approval of the awarding agency. The following are the most common situations requiring prior approval. However, this list is not exhaustive, and the recipient is also bound by any other prior approval requirements identified in the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. a. Pre-award costs.—To receive reimbursement for costs incurred prior to the award date, recipients must request written approval before incurring the costs. This restriction also applies to costs intended to meet cost-share requirements. FPAC agencies will not approve expenses incurred more than 90 calendar days before the period of performance start date. All costs incurred before the period of performance start date, even if approved, are at the recipient's risk (i.e., the Federal awarding agency is under no obligation to reimburse such costs if for any reason the recipient does not receive a Federal award or if the Federal award is less than anticipated and inadequate to cover such costs). b. Revisions to scope, objective, or deliverables.—When it is necessary to modify the scope, objective, or deliverables of an award, the recipient authorized signatory must submit a written request and justification for the change along with the revised scope, objective, or deliverables of the award to the administrative contact. The request should contain the following information: 1. Grant or agreement number 2. Narrative explaining the requested modification to the project scope, objectives, or deliverables 3. A description of the revised scope, objectives, or deliverables c. Additions or changes to subawards and contracts.—The subawarding, transferring, or contracting out of any work under a Federal award not identified in the original award budget or any changes to subaward or contracts requires prior written approval. The recipient must submit a justification for the proposed subaward/contract, a statement of work to be performed, and a detailed budget for the subaward/contract to the administrative contact. This provision does not apply to the acquisition of supplies, material, equipment, or general support services. d. Change in a key person specified in the application or award.— When there is a change in key personnel, the recipient must request prior written approval for the substitution or change. The request must identify the replacement personnel and provide his or her qualifications. e. Absence or change in project leadership.—If the approved project director or principal investigator disengages from the project for more than three months or reduces time devoted to the project by 25 percent or more, the recipient must notify the administrative contact in writing, identifying who will be in charge during the project director’s absence. The notification must include the qualifications of the replacement. f. Budget revisions.—Recipients must request prior written approval for deviations from the approved budget in the instances described below. For all budget revisions, the recipient must submit a new SF 424A or 424C and budget narrative to support the request. 1. The inclusion of costs that require prior approval in accordance with Subpart E—Cost Principles of this part or 45 CFR part 75 Appendix IX, “Principles for Determining Costs Applicable to Research and Development under Awards and Contracts with Hospitals,” or 48 CFR part 31, “Contract Cost Principles and Procedures,” as applicable. 2. Where the cumulative amount of transfers of funds among direct cost categories or programs, functions, and activities exceeds or is expected to exceed 10 percent of the total budget as last approved by the Federal awarding agency, and where the Federal share of the project exceeds the simplified acquisition threshold. 3. The transfer of funds budgeted for participant support costs to other categories of expense requires prior written approval. Participant support costs means direct costs for items such as stipends or subsistence allowances, travel allowances, and registration fees paid to or on behalf of participants or trainees (but not employees) in connection with conferences or training projects. 4. Changes in the approved cost-sharing or matching provided by the recipient. 5. Additional Federal funds needed to complete the project. 6. Changes to negotiated indirect cost rates during the award period of performance. 7. Equipment purchases not specifically identified in the approved budget. g. No-Cost Extensions of Time.—When a no-cost extension of time is required, the recipient authorized signatory must submit a written request to the FAPC administrative contact. Except in very limited circumstances, a no-cost extension of time cannot exceed 12 months. FPAC cannot approve requests for no-cost extensions received after the expiration of the award. In addition, time may not allow extension requests submitted less than 30 calendar days before the period of performance end date to be processed, so recipients are encouraged to submit requests as soon as possible. FPAC agencies cannot approve no-cost extensions requested merely to expend remaining funds. The request must contain the following: 1. Amount of additional time requested 2. Explanation for the need for the extension 3. A summary of progress to date and revised milestones
Appears in 4 contracts
Samples: Grants Agreement, Grants Agreement, Grants Agreement
Prior Approval Requirements. Certain items of cost and award revisions require the prior written approval of the awarding agency. The following are the most common situations requiring prior approval. However, this list is not exhaustive, and the recipient is also bound by any other prior approval requirements identified in the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Submit all requests for the approvals described below via e-mail to XXXX.XX.XXX@xxxx.xxx. In any instance where a request for approval modifies the award budget, the recipient must submit a revised SF 424A and budget narrative. All requests for prior approval must reference the applicable agreement number.
a. Pre-award costs.—To receive reimbursement for costs incurred prior to the award date, recipients must request written approval before incurring the costsapproval. This restriction also applies to costs intended to meet cost-share requirements. FPAC agencies will not approve expenses incurred more than 90 calendar days before the period of performance start dateEven with approval, recipients incur pre- award costs at their own risk. All costs incurred before the period of performance start date, even if approved, are at the recipient's risk (i.e., the The Federal awarding agency is under no obligation to reimburse such costs if for any reason the recipient does not receive a Federal award or if the Federal award is less than anticipated and inadequate to cover such the costs).
b. Revisions to scope, objective, or deliverables.—When it is necessary to modify the scope, objective, or deliverables of an award, the recipient authorized signatory must submit a written request and justification for the change along with the revised scope, objective, or deliverables of the award to the administrative contact. The request should contain the following information:
1. Grant or agreement number
2. Narrative explaining the requested modification to the project scope, objectives, or deliverables
3. A description of the revised scope, objectives, or deliverablesaward.
c. Additions or changes to subawards and contracts.—The subawarding, transferring, or contracting out of any work (i.e., services) under a Federal award not identified in the original award budget or any changes to subaward or contracts requires prior written approval. The recipient must submit a justification for the proposed subaward/contract, a statement of work to be performed, and a detailed budget for the subaward/contract to the administrative contactcontract. This provision does not apply to the acquisition of supplies, material, equipment, or general support services.
d. Change in a key person specified in the application or award.— When award.—When there is a change in key personnel, the recipient must request prior written approval for the substitution or change. The request must identify the replacement personnel and provide his or her qualifications.
e. Absence or change in project leadership.—If the approved project director or principal investigator disengages from the project for more than three months or reduces time devoted to the project by 25 percent or more, the recipient must notify the administrative contact request prior approval in writing, identifying who will be in charge during the project director’s absence. The notification must include the qualifications of the replacement.
f. Budget revisions.—Recipients must request prior written approval for deviations from the approved budget in the instances described below. For all budget revisions, the recipient must submit a new SF 424A or 424C and budget narrative to support the request.narrative, even those that do not require prior approval..
1. The inclusion of costs that require prior approval in accordance with Subpart E—— Cost Principles of this part or 45 CFR part 75 Appendix IX, “Principles for Determining Costs Applicable to Research and Development under Awards and Contracts with Hospitals,” or 48 CFR part 31, “Contract Cost Principles and Procedures,” as applicable.
2. Where the cumulative amount of transfers of funds among direct cost categories or programs, functions, and activities exceeds or is expected to exceed 10 percent of the total budget as last approved by the Federal awarding agency, and where the Federal share of the project exceeds the simplified acquisition threshold. Recipients must notify the Government of budget changes that do not meet the threshold described above and provide a revised SF 424A and budget narrative.
3. The transfer of funds budgeted for participant support costs to other categories of expense requires prior written approval. Participant support costs means direct costs for items such as stipends or subsistence allowances, travel allowances, and registration fees paid to or on behalf of participants or trainees (but not employees) in connection with conferences or training projects.
4. Changes in the approved cost-sharing or matching provided by the recipient, including to amount, source, or type.
5. Additional Federal funds needed to complete the project. This change also requires a formal agreement amendment.
6. Changes to negotiated indirect cost rates during the award period of performance.
7. Equipment purchases not specifically identified in If the approved budgetchange is due to receipt of a new negotiated indirect costs rate agreement (NICRA) must include a copy of the new agreement.
g. No-Cost Extensions of Time.—When a no-cost extension of time is requirednecessary, the recipient authorized signatory must submit a written request via e-mail to the FAPC administrative contactXXXX.XX.XXX@xxxx.xxx. Except in very limited circumstances, a no-cost extension of time cannot exceed 12 months. FPAC cannot approve requests for no-cost extensions received after the expiration of the award. In addition, time may not allow extension requests submitted less than 30 calendar days before the period of performance end date to be processed, so recipients are encouraged to submit requests as soon as possible. FPAC agencies cannot approve no-cost extensions requested merely to expend remaining funds. The request must contain the following:
1. Amount of additional time requested
2. Explanation for the need for the extension 3. A summary of progress to date and revised milestones
Appears in 1 contract
Samples: General Terms and Conditions for Grants and Cooperative Agreements