Programming constraints. Read clause 31.2 first then state what additional information (if any) is to go in the programme per the last bullet of clause 31.
Programming constraints. The Supplier should include in his programme how to manage availability of the ordered material as per task order requirement.
Programming constraints. Describe the programming system (application) to be used if it is necessary to dictate this for project coordination purposes. Read clause 31.2 first then state the work of the Employer and Others to be shown on the programme per 4th bullet of clause 31.2 and what additional information (if any) is to go in the programme per the last bullet of clause 31.2. Describe any particular constraints on the order and timing of the work which the Contractor must take into account in his programme.
Programming constraints. The Contractor submits a programme within 1 week of the Contract Award. The program shall be in Microsoft Excel/MSProjects or MicrosoftWord format The programme indicates The hour duration of each activity, The working calendar (number of work hours per day, days per week), The exact quantity of people per day All phases and interfaces
Programming constraints. The Contractor submits a bar chart programme in MS Project format, detailing how the works are executed within the stipulated dates. The programme indicates the starting date, completion date and duration of each activity.
Programming constraints. 2.6.1 A detailed program with all the relevant Completion date will be discussed with the Contractor and approved by Eskom at the Inaugural meeting. The Contractor shall submit a comprehensive and fully detailed program within 1 week but before the Starting date after the program has been discussed with the contractor. The program shall be revised fortnightly and submitted to the PM for approval. If changes take place which affect the Completion date then a revised program must be submitted within 2 days. The Employer’s key and milestone dates shall be indicated. Note: Only MS Project format will be accepted.
2.6.2 The following dates shall be clearly reflected on the programme:
2.6.3 Updated programmes must be available at all site meetings reflecting progress to date.
2.6.4 The contractor’s trucks must have a valid and current crane test certificate with the truck driver and crane operator’s certificate. All slings, shackles and crimping tools must have valid and current test certificate, which must be produced two weeks before site establishment.
2.6.5 The contractor is to have an Eskom certified and authorised ORHVS person available in each area where work is being performed at all times in accordance with Eskom transmission standard 32-136 for contractor safety in a high voltage environment.
Programming constraints. 2.8.1 Programme constraints and requirements
Programming constraints. Not applicable. The Supplier shall address the tax invoice to Purchaser and include on each invoice the following information: Name and address of the Supplier and the Supply Manager; The contract number and title; The Purchaser’s VAT registration number. Description of goods and services provided for each item invoiced based on the Price Schedule; Total amount invoiced excluding VAT, the VAT and the invoiced amount including VAT; (add other as required) Add procedures for invoice submission and payment (e. g. electronic payment instructions) Not applicable. The form in which a bond or guarantee required by the conditions of contract (if any) is to be provided by the
Programming constraints a) The Contractor submits a first programme to the Project Manager for acceptance within the period stated in the Contract Data.
b) This programme complies with CLAUSE 31.
Programming constraints. The contractor shall submit his construction program in terms of the conditions of contract. This program shall be submitted according to Part one – Data provided by the Employer (Time). • This Site Establishment • Xxxx clearing • Survey • Foundations • Pole layout • Dressing of structures • Planting poles & stays • Stringing of conductors • Stringing of shieldwire • Outage Program & Requirements • Commissioning Every activity on the programme will be clearly linked to a labour resources and equipment required to perform the specific activity. The Contract Program will be on display in the Contractors Site Offices and will be updated weekly. In addition to the maintaining of this programme, the Contractor will report progress to the Project Manager on a weekly basis. Should any deviations to the program be found, the Contractor shall submit a revised program to the Project Manager within one week. The Project Manager retains the right to alter the Accepted Program should circumstances on site necessitate such a change. The following Statutory non-working days are included within the contract period: • All Public Holidays for the duration of the contract. • The programme must clearly indicate the working days for the entire construction period or alternatively all the non-working days within the construction period.