PRE-CONSTRUCTION PHASE SERVICES. The Pre-Construction Phase shall be deemed to commence upon the date specified in a written Notice to Proceed with Pre-Construction Phase Services issued by Owner and shall continue through completion of the Construction Documents and procurement of all major Subcontractor agreements. Contractor is not entitled to reimbursement for any costs incurred for Pre-Construction Phase Services performed before issuance of the written Notice to Proceed. Pre-Construction Phase Services may overlap Construction Phase Services. Contractor shall perform the following Pre-Construction Phase Services:
PRE-CONSTRUCTION PHASE SERVICES. Construction Contractor shall provide the following review and commentary services, in addition to any other Pre-Construction Phase Services required by the terms of the Contract:
PRE-CONSTRUCTION PHASE SERVICES. Construction Contractor shall review and comment upon the Construction Documents being developed by Design Professional. The scope of that review shall include reviewing those various documents for value engineering and constructability. As the Construction Documents are developed by Design Professional through the various design phases set forth in the Design Professional Services Agreement between Design Professional and Owner (“Design Agreement”), Construction Contractor shall provide Owner with detailed construction cost estimates with respect to those documents. Construction Contractor agrees to attend any and all design and preconstruction conferences and to otherwise assist and cooperate with Design Professional with respect to the design of the Project. Construction Contractor shall provide all other services during the conducted during the Pre-Construction Phase of the Project as set forth in the Contract Documents (collectively, the “Pre-Construction Phase Services”). The duration of the “Pre-Construction Phase” shall be defined in Section 7 of this Agreement.
PRE-CONSTRUCTION PHASE SERVICES. For all Pre-Construction Phase Services, including providing value engineering services, reviewing Construction Documents for constructability, assisting and meeting with Design Professional during the various design phases, and preparing cost estimates, Construction Contractor shall receive the fixed amount of ($ ) as the total lump sum compensation for its services. Additionally, Construction Contractor shall receive reimbursement, without xxxx-up, for actual amounts incurred by Construction Contractor for the reimbursable expense items specified in the Pre-Construction Phase Services Reimbursable Expense Proposal attached hereto and incorporated herein as Exhibit , , up to the “not to exceed amounts” specified for such items in Exhibit .. Monthly installment payments of the total lump sum compensation and reimbursement for reimbursable expense items specified on Exhibit (subject, however, to the “not to exceed” caps on such items)] shall be based upon the percent completion of the designated portion of the Pre-Construction Phase Services for each particular month as determined by Owner and an itemized statement of reimbursable expenses incurred for such month, respectively, and Owner’s receipt of Construction Contractor’s written invoice for such payment. Construction Contractor’s invoices shall be in a form reasonably acceptable to Owner and be accompanied by such other information, documentation, and materials as Owner may reasonably require. The final invoice shall not be submitted until either (i) the GMP Amendment is executed for the entire Work, or (ii) the parties fail to reach agreement on the GMP Amendment and Owner elects to terminate the Contract as provided in Section 4.B hereafter, whichever occurs first.
PRE-CONSTRUCTION PHASE SERVICES. Services which the Construction Manager shall provide include, but are not limited to, those described or specified herein:
PRE-CONSTRUCTION PHASE SERVICES. The Pre-Construction Phase shall commence on the date specified in a Notice to Proceed issued by Owner and shall continue through completion of the Construction Documents and procurement of all major Subcontractor agreements. CM is not entitled to reimbursement for any costs incurred for Pre- Construction Phase Services performed before issuance of the Notice to Proceed. Pre-Construction Phase Services may overlap with Construction Phase Services. The CM shall perform the following tasks as a part of the Pre-Construction Phase Services:
PRE-CONSTRUCTION PHASE SERVICES. For all Pre-Construction Phase Services, including, but not limited to, providing value engineering services, reviewing Construction Documents for constructability, assisting and meeting with Design Professional during the various design phases, and preparing cost estimates, Construction Contractor shall receive the fixed amount of $ as the total lump sum compensation for its services. Monthly installment payment of the total lump sum compensation shall be based upon the percent completion of the designated portion of the Pre-Construction Services for each particular month and Owner’s receipt of Construction Contractor’s written invoice for such payment, said invoice to be in a form reasonably acceptable to Owner. The final invoice shall not be submitted until either (i) the GMP Amendment is executed for the entire Work, or (ii) the parties fail to reach agreement on the GMP Amendment and Owner elects to terminate this Contract as provided in section 4.B hereafter, whichever occurs first.
PRE-CONSTRUCTION PHASE SERVICES. 3.1 OBLIGATIONS OF THE CONSTRUCTION MANAGER WITH RESPECT TO THE DESIGN PROFESSIONAL.
PRE-CONSTRUCTION PHASE SERVICES. All services described in the CM/GC Contract, Article 3.1, including any similar services as are described in the CM/GC’s Proposal to the extent they are accepted by the Department, but excluding any Early Work. Early Work shall be considered part of the Construction Phase Services.
PRE-CONSTRUCTION PHASE SERVICES. (a) Design Coordination: Assist the District in administrating and monitoring the design phase for the Project by providing the following services: