Progress Chart. (1) The Contractor shall prepare progress charts and submit the same for approval of the Engineer and for his record within twenty-one days of commencement of work. The charts shall indicate the expected date of commencement and completion of each of the items of the work and shall be in a form approved by the Engineer. The chart shall also indicate the scheduling of samples, Shop Drawings and approvals. The Contractor shall, whenever required by the Engineer, also provide in writing for his information a general description of the arrangements and method which the Contractor proposes to adopt for execution of the Works. (2) If at any time it should appear to the Engineer that the actual progress of the Works does not conform to the programme to which consent has been given under sub- clause 14.1, the Contractor shall produce within a week's time at the request of the Engineer, a revised programme showing the modifications to such programmes necessary to ensure completion of the Work within the Time for Completion. (3) The Contractor shall, if required any time by the Engineer, deliver to the Engineer a report in detail, in such form and at such interval as the Engineer may prescribe showing the status of work by the Contractor at site.
Appears in 4 contracts
Samples: Annual Maintenance Contract, Annual Maintenance Contract, Annual Maintenance Contract
Progress Chart. (1) The Contractor shall prepare progress charts and submit the same for approval of the Engineer and for his record within twenty-one days of commencement of work. The charts shall indicate the expected date of commencement and completion of each of the items of the work and shall be in a form approved by the Engineer. The chart shall also indicate the scheduling of samples, Shop Drawings and approvals. The Contractor shall, whenever required by the Engineer, also provide in writing for his information a general description of the arrangements and method which the Contractor proposes to adopt for execution of the Works.
(2) If at any time it should appear to the Engineer that the actual progress of the Works does not conform to the programme to which consent has been given under sub- clause 14.1, the Contractor shall produce within a week's time at the request of the Engineer, a revised programme showing the modifications to such programmes necessary to ensure completion of the Work within the Time for Completion.
(3) The Contractor shall, if required any time by the Engineer, deliver to the Engineer a report in detail, in such form and at such interval as the Engineer may prescribe presc ribe showing the status of work by the Contractor at site.
Appears in 1 contract