Progress of the Works. 19.1.1. Immediately after the date of this Contract, and before possession of site, the Contractor must prepare and submit to the Principal‟s Representative for the Principal Representative‟s approval a construction program for the carrying out of the Works in accordance with this Contract. 19.1.2. None of the Principal‟s Representative or the Project Manager shall be liable for any errors in the Construction Program. 19.1.3. A copy of the Construction Program shall be retained at the Site and the Contractor must note on it the actual progress of the Works and inform the Principal‟s Representative or the Project Manager of any circumstances that might affect the Construction Program or delay completion of the Works by the Date for Practical Completion. 19.1.4. The Contractor must submit regular progress reports to the Principal‟s Representative or the Project Manager containing information on the progress of the Works, labour and materials on Site and details of any information required by the Principal‟s Representative or the Project Manager. 19.1.5. Site meetings must be held by the Contractor as requested by the Principal‟s Representative or the Project Manager. 19.1.6. The Contractor must arrange for a senior member of its staff and the Supervisor to attend all Site meetings. 19.1.7. The Contractor must maintain a complete copy of the drawings and specifications and Construction Program at the Site at all times during all phases of the Works. 19.1.8. The Principal‟s Representative or the Project Manager will produce minutes of all Site meetings and distribute copies to the Principal, the Contractor and other interested parties as soon as possible after the meeting. 19.1.9. Where appropriate, the minutes of Site meetings shall be regarded as written instructions by the Principal‟s Representative and/or the Project Manager to the Contractor and the provisions of clause 17.1.2 shall apply.
Appears in 2 contracts
Progress of the Works. 19.1.120.1.1. Immediately after the date of this Contract, and before possession of site, the Contractor must prepare and submit to the Principal‟s Representative for the Principal Representative‟s approval a construction program for the carrying out of the Works in accordance with this Contract.
19.1.220.1.2. The program will need to take into account Court sitting days and public opening hours.
20.1.3. None of the Principal‟s Representative or the Project Manager shall be liable for any errors in the Construction Program.
19.1.320.1.4. A copy of the Construction Program shall be retained at the Site and the Contractor must note on it the actual progress of the Works and inform the Principal‟s Representative or the Project Manager of any circumstances that might affect the Construction Program or delay completion of the Works by the Date for Practical Completion.
19.1.420.1.5. The Contractor must submit regular progress reports to the Principal‟s Representative or Representative, as nominated by the Project Manager Principal‟s Representative, containing information on the progress of the Works, labour and materials on Site and details of any information required by the Principal‟s Representative or the Project ManagerRepresentative.
19.1.520.1.6. Site meetings must be held by the Contractor as requested by the Principal‟s Representative or the Project ManagerRepresentative.
19.1.620.1.7. The Contractor must arrange for a senior member of its staff and the Supervisor to attend all Site meetings.
19.1.720.1.8. The Contractor must maintain a complete copy of the drawings and specifications and Construction Program at the Site at all times during all phases of the Works.
19.1.820.1.9. The Principal‟s Representative or the Project Manager will produce minutes of all Site meetings and distribute copies to the Principal, the Contractor and other interested parties as soon as possible after the meeting.
19.1.920.1.10. Where appropriate, the minutes of Site meetings shall be regarded as written instructions by the Principal‟s Representative and/or the Project Manager to the Contractor and the provisions of clause 17.1.2 18.1.2 shall apply.
Appears in 2 contracts
Samples: Minor Works Building Works Contract, Minor Works Building Works Contract
Progress of the Works. 19.1.1. Immediately after the date of this Contract, and before possession of site, the Contractor must prepare and submit to the Principal‟s Representative for the Principal Representative‟s approval a construction program for the carrying out of the Works in accordance with this Contract.
19.1.2. None of the Principal‟s Representative or Representative, the Project Manager shall or the Design Consultantshall be liable for any errors in the Construction Program.
19.1.3. A copy of the Construction Program shall be retained at the Site and the Contractor must note on it the actual progress of the Works and inform the Principal‟s Representative or the Project Manager of any circumstances that might affect the Construction Program or delay completion of the Works by the Date for Practical Completion.
19.1.4. The Contractor must submit regular progress reports to the Principal‟s Representative or the Project Manager Manager, as nominated by the Principal‟s Representative, containing information on the progress of the Works, labour and materials on Site and details of any information required by the Principal‟s Representative or the Project Manager.
19.1.5. Site meetings must be held by the Contractor as requested by the Principal‟s Representative or the Project Manager.
19.1.6. The Contractor must arrange for a senior member of its staff and the Supervisor to attend all Site meetings.
19.1.7. The Contractor must maintain a complete copy of the drawings and specifications and Construction Program at the Site at all times during all phases of the Works.
19.1.8. The Principal‟s Representative or the Project Manager will produce minutes of all Site meetings and distribute copies to the Principal, the Contractor and other interested parties as soon as possible after the meeting.
19.1.9. Where appropriate, the minutes of Site meetings shall be regarded as written instructions by the Principal‟s Representative and/or the Project Manager to the Contractor and the provisions of clause 17.1.2 shall apply.
Appears in 1 contract
Samples: Building Works Contract
Progress of the Works. 19.1.1
20.1.1. Immediately after the date of this Contract, and before possession of site, the Contractor must prepare and submit to the Principal‟s Principal’s Representative for the Principal Representative‟s Representative’s approval a construction program for the carrying out of the Works in accordance with this Contract.
19.1.220.1.2. The program will need to take into account Court sitting days and public opening hours.
20.1.3. None of the Principal‟s Principal’s Representative or the Project Manager shall be liable for any errors in the Construction Program.
19.1.320.1.4. A copy of the Construction Program shall be retained at the Site and the Contractor must note on it the actual progress of the Works and inform the Principal‟s Principal’s Representative or the Project Manager of any circumstances that might affect the Construction Program or delay completion of the Works by the Date for Practical Completion.
19.1.420.1.5. The Contractor must submit regular progress reports to the Principal‟s Representative or Principal’s Representative, as nominated by the Project Manager Principal’s Representative, containing information on the progress of the Works, labour and materials on Site and details of any information required by the Principal‟s Representative or the Project ManagerPrincipal’s Representative.
19.1.520.1.6. Site meetings must be held by the Contractor as requested by the Principal‟s Representative or the Project ManagerPrincipal’s Representative.
19.1.620.1.7. The Contractor must arrange for a senior member of its staff and the Supervisor to attend all Site meetings.
19.1.720.1.8. The Contractor must maintain a complete copy of the drawings and specifications and Construction Program at the Site at all times during all phases of the Works.
19.1.820.1.9. The Principal‟s Principal’s Representative or the Project Manager will produce minutes of all Site meetings and distribute copies to the Principal, the Contractor and other interested parties as soon as possible after the meeting.
19.1.920.1.10. Where appropriate, the minutes of Site meetings shall be regarded as written instructions by the Principal‟s Principal’s Representative and/or the Project Manager to the Contractor and the provisions of clause 17.1.2 18.1.2 shall apply.
Appears in 1 contract
Samples: Minor Works Building Works Contract
Progress of the Works. 19.1.120.1.1. Immediately after the date of this Contract, and before possession of site, the Contractor must prepare and submit to the Principal‟s Principal’s Representative for the Principal Representative‟s Representative’s approval a construction program for the carrying out of the Works in accordance with this Contract.
19.1.220.1.2. The program will need to take into account Court sitting days and public opening hours.
20.1.3. None of the Principal‟s Principal’s Representative or the Project Manager shall be liable for any errors in the Construction Program.
19.1.320.1.4. A copy of the Construction Program shall be retained at the Site and the Contractor must note on it the actual progress of the Works and inform the Principal‟s Principal’s Representative or the Project Manager of any circumstances that might affect the Construction Program or delay completion of the Works by the Date for Practical Completion.
19.1.420.1.5. The Contractor must submit regular progress reports to the Principal‟s Representative or Principal’s Representative, as nominated by the Project Manager Principal’s Representative, containing information on the progress of the Works, labour and materials on Site and details of any information required by the Principal‟s Representative or the Project ManagerPrincipal’s Representative.
19.1.520.1.6. Site meetings must be held by the Contractor as requested by the Principal‟s Representative or the Project ManagerPrincipal’s Representative.
19.1.620.1.7. The Contractor must arrange for a senior member of its staff and the Supervisor to attend all Site meetings.
19.1.720.1.8. The Contractor must maintain a complete copy of the drawings and specifications and Construction Program at the Site at all times during all phases of the Works.
19.1.820.1.9. The Principal‟s Principal’s Representative or the Project Manager will produce minutes of all Site meetings and distribute copies to the Principal, the Contractor and other interested parties as soon as possible after the meeting.
19.1.920.1.10. Where appropriate, the minutes of Site meetings shall be regarded as written instructions by the Principal‟s Principal’s Representative and/or the Project Manager to the Contractor and the provisions of clause 17.1.2 18.1.2 shall apply.