Progress Payments and Retainage. As it completes portions of the Work, the Contractor may request progress payments from the Owner. Progress payments shall be made by the Owner based on the Owner's estimate of the value of the Work properly completed by the Contractor since the time the last progress payment was made. The "estimate of the value of the work properly completed" shall include the net invoice value of acceptable, non-perishable materials actually delivered to and currently at the job site only if the Contractor provides to the Owner satisfactory evidence that material suppliers have been paid for these materials. 1. copies of documents reasonably necessary to aid the Owner in preparing an estimate of the value of Work properly completed; 2. full or partial releases of liens, including releases from subcontractors providing materials or delivery services relating to the Work, in a form acceptable to the Owner releasing all liens or claims relating to goods and services provided up to the date of the most recent previous progress payment; 3. an updated and current schedule clearly detailing the project’s critical path elements; and 4. any other documents required under the Contract Documents. Progress payments shall not be made more frequently than once every thirty (30) calendar days unless the Owner determines that more frequent payments are appropriate. Further, progress payments are to be based on estimates and these estimates are subject to correction through the adjustment of subsequent progress payments and the final payment to Contractor. If the Owner determines after final payment that it has overpaid the Contractor, then Contractor agrees to pay to the Owner the overpayment amount specified by the Owner within thirty (30) calendar days after it receives written demand from the Owner. The fact that the Owner makes a progress payment shall not be deemed to be an admission by the Owner concerning the quantity, quality or sufficiency of the Contractor's work. Progress payments shall not be deemed to be acceptance of the Work nor shall a progress payment release the Contractor from any of its responsibilities under the Contract Documents. After determining the amount of a progress payment to be made to the Contractor, the Owner shall withhold a percentage of the progress payment as retainage. The amount of retainage withheld from each progress payment shall be set at five percent (5%). Retainage shall be withheld and may be paid to: 1. ensure proper completion of the Work. The Owner may use retained funds to pay replacement or substitute contractors to complete unfinished or defective work; 2. ensure timely completion of the Work. The Owner may use retained funds to pay liquidated damages; and 3. provide an additional source of funds to pay claims for which the Owner is entitled to indemnification from Contractor under the Contract Documents. Retained funds shall be held by the Owner in accounts that shall not bear interest. Retainage not otherwise withheld in accordance with the Contract Documents shall be returned to the Contractor as part of the final payment.
Appears in 8 contracts
Samples: Construction Agreement, Construction Agreement, Construction Agreement
Progress Payments and Retainage. As it completes portions of the Work, the Contractor may request progress payments from the Owner. Progress payments shall be made by the Owner based on the Owner's estimate of the value of the Work properly completed by the Contractor since the time the last progress payment was made. The "estimate of the value of the work properly completed" shall include the net invoice value of acceptable, non-perishable materials actually delivered to and currently at the job site only if the Contractor provides to the Owner satisfactory evidence that material suppliers have been paid for these materials.. No progress payment shall be due to the Contractor until the Contractor furnishes to the Owner:
1. copies of documents reasonably necessary to aid the Owner in preparing an estimate of the value of Work properly completed;
2. full or partial releases of liens, including releases from subcontractors providing materials or delivery services relating to the Work, in a form acceptable to the Owner releasing all liens or claims relating to goods and services provided up to the date of the most recent previous progress payment;
3. an updated and current schedule clearly detailing the project’s critical path elements; and
4. any other documents required under the Contract Documents. Progress payments shall not be made more frequently than once every thirty (30) calendar days unless the Owner determines that more frequent payments are appropriate. Further, progress payments are to be based on estimates and these estimates are subject to correction through the adjustment of subsequent progress payments and the final payment to Contractor. If the Owner determines after final payment that it has overpaid the Contractor, then Contractor agrees to pay to the Owner the overpayment amount specified by the Owner within thirty (30) calendar days after it receives written demand from the Owner. The fact that the Owner makes a progress payment shall not be deemed to be an admission by the Owner concerning the quantity, quality or sufficiency of the Contractor's work. Progress payments shall not be deemed to be acceptance of the Work nor shall a progress payment release the Contractor from any of its responsibilities under the Contract Documents. After determining the amount of a progress payment to be made to the Contractor, the Owner shall withhold a percentage of the progress payment as retainage. The amount of retainage withheld from each progress payment shall be set at five percent (5%). Retainage shall be withheld and may be paid to:
1. ensure proper completion of the Work. The Owner may use retained funds to pay replacement or substitute contractors to complete unfinished or defective work;
2. ensure timely completion of the Work. The Owner may use retained funds to pay liquidated damages; and
3. provide an additional source of funds to pay claims for which the Owner is entitled to indemnification from Contractor under the Contract Documents. Retained funds shall be held by the Owner in accounts that shall not bear interest. Retainage not otherwise withheld in accordance with the Contract Documents shall be returned to the Contractor as part of the final payment.
Appears in 7 contracts
Samples: Construction Agreement, Construction Agreement, Construction Agreement