PROJECT SCHEDULE DEVELOPMENT REQUIREMENTS. 2.4.1 The Contractor shall assign a standard “Activity Code” using a custom field, to every activity or task; organized by at least the Project phase, xxxxx, xxxxxxxx, xxxxxxxx, xxxxx, xxxx, xxxxxxxxx, xx system, etc., (i.e. work breakdown structure) including the following primary Activity Codes: Activity Code & Description Activity Code & Description CP Contract Procurement C Construction PP Programming/Pre-Project Planning GC General Conditions SD Schematic Design SU Submittals DD Design Development FD Fabricate and Delivery CD Construction Documents CI Contractor Inspections BOR U.T. System Board of Regents OI Owner Inspections GMP Guaranteed Maximum Price Cx Commissioning TH THECB Approval TAB Test, Adjust, and Balance SP Subcontractor Bidding / Procurement OP Owner Provided - Contractor Installed
Appears in 2 contracts
Samples: www4.mdanderson.org, www4.mdanderson.org
PROJECT SCHEDULE DEVELOPMENT REQUIREMENTS. 2.4.1 The Contractor shall assign a standard “Activity Code” using a custom field, to every activity or task; organized by at least the Project phase, xxxxx, xxxxxxxx, xxxxxxxx, xxxxx, xxxx, xxxxxxxxx, xx system, etc., (i.e. work breakdown structure) including the following primary Activity Codes: Activity Code & Description Activity Code & Description CP Contract Procurement C Construction PP Programming/Pre-Project Planning GC General Conditions SD Planning Schematic Design SU Submittals DD Design Development FD Fabricate and Delivery CD Construction Documents CI Contractor Inspections BOR U.T. System Board of Regents OI Owner Inspections GMP Guaranteed Maximum Price Cx Commissioning TH THECB Approval TAB Test, Adjust, and Balance SP Subcontractor Bidding / Procurement OP Owner Provided - Contractor Procurement Installed
Appears in 1 contract
Samples: www4.mdanderson.org
PROJECT SCHEDULE DEVELOPMENT REQUIREMENTS. 2.4.1 The Contractor shall assign a standard “Activity Code” using a custom field, to every activity or task; organized by at least the Project phase, xxxxxstage, xxxxxxxxlocation, xxxxxxxxbuilding, xxxxxfloor, xxxxarea, xxxxxxxxxelevation, xx or system, etc., (i.e. work breakdown structure) including the following primary Activity Codes: Activity Code & Description Activity Code & Description CP Contract Procurement C Construction PP Programming/Pre-Project Planning GC General Conditions SD Schematic Design SU Submittals DD Design Development FD Fabricate and Delivery CD Construction Documents CI Contractor Inspections BOR U.T. System Board of Regents OI Owner Inspections GMP Guaranteed Maximum Price Cx Commissioning TH THECB Approval TAB Test, Adjust, and Balance SP Subcontractor Bidding / Procurement OP Owner Provided - Contractor Installed
Appears in 1 contract
Samples: www4.mdanderson.org